This solicitation is for a bank stabilization and navigation project on the Missouri River. The scope of work includes repair and maintenance of navigation channels through a variety of activities such as excavation, placement of stone, and construction of features like revetments, roots, sills, dikes, and anchors. Placement will generally be via floating plant but some land access and placement will be required. The agency intends to make multiple small business set-aside awards as part of an indefinite delivery/indefinite quantity contract pool. Responses are due based on the solicitation date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
(For Construction Contract)
Solicitation Number W9128F23R0023
Missouri River Recovery Operation and Maintenance North FY 23
March 2023
US Army Corps of Engineers Omaha District
This page was intentionally left blank for duplex printing.
Missouri River Recovery O&M North FY23 Missouri River, NE MR00106
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 12 00 CONSTRUCTION GENERAL
01 22 00 MEASUREMENT AND PAYMENT
01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 78 39.00 24 AS-BUILT DRAWINGS
01 80 00 AS-BUILT SURVEYS
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 05 33 TURF
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 31 19 STONE
35 31 20 STRUCTURES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 12 00
CONSTRUCTION GENERAL
PART 1 GENERAL
1.1 SCOPE
1.2 CONSTRUCTION RIGHT-OF-WAY
1.3 PROTECTION OF EXISTING FACILITIES AND WORKS
1.3.1 Flood Protection Works
1.4 CARE OF WATER
1.5 Project Survey and Layout
1.6 DISPOSITION OF CONSTRUCTION FACILITIES
1.7 ACCESS ROADS AND HAUL ROADS
1.7.1 Access Roads
1.7.2 Haul Roads
1.7.3 Joint Use of Transportation Facilities
1.7.4 Waterway Crossings
1.7.5 Ramps
1.7.6 Drainage
1.8 Lane Closure
1.9 Traffic Control Devices
1.10 Temporary Traffic Control (TTC)
1.11 Operations
1.11.1 Flaggers
1.12 Road Closure
1.13 State and Federal Highways
1.14 State and Local Public Roads
1.15 City Streets
1.16 Utility Lines
1.17 COOPERATION WITH OTHER CONTRACTORS
1.18 WINTER WORK
1.19 SUBMITTALS
1.20 SPECIAL INSTRUCTIONS FOR PROGRESS CHARTS
1.21 WARRANTY OF CONSTRUCTION (MAR 1994)
1.22 TELEPHONE/INTERNET
1.23 TRANSPORTATION OF GOVERNMENT PERSONNEL
1.24 River Stabilization Structures Report, MRD Form 701
1.25 PORTABLE TOILETS
1.26 FEDERAL HOLIDAYS AND WORKING HOURS
PART 2 NOT USED
PART 3 NOT USED
-- End of Section Table of Contents --
SECTION 01 12 00 Page 1
SECTION 01 12 00
CONSTRUCTION GENERAL
PART 1 GENERAL
1.1 SCOPE
The work covered in this section is outlined as a statement of construction requirements common to all the work. Specific requirements for materials and installations are provided under the Technical Sections herewith. No claims for extras shall be made on account of items presumed to have been omitted from this section.
1.2 CONSTRUCTION RIGHT-OF-WAY
The Contractor will be assigned working areas or working right-of-way limits for use in the prosecution of work under this contract, subject to the SECTION 00 72 00, GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Operations and Storage Areas."
1.3 PROTECTION OF EXISTING FACILITIES AND WORKS
The Contractor shall be responsible for the protection of the work area from damage and upon completion of the work shall leave existing works in a condition equal to that which existed when the work started. All work, storage of materials, and construction plant shall be kept within the limits of the areas assigned. Prior to construction operations, the Contractor shall confer with the Contracting Officer's representative to determine the proximity of any possible under-ground obstructions, pipe or equipment which could be damaged as a result of construction operations.
Existing utility lines that are shown on the drawings or the locations are otherwise made known to the Contractor shall be protected from damage, and if damaged, shall be repaired by the Contractor at no additional expense to the Government. In the event that the Contractor damages any existing utility lines that are not shown or the locations of which have not been made known to the Contractor, the Contractor shall immediately notify the Contracting Officer. The Contracting Officer will review the information and discuss with the Contractor how to proceed. The Contractor will be responsible for the protection of structures from any structural damage during the construction operations. Roads and surfaces shall be protected from damage by the work or if damaged shall be repaired with equal materials at no additional expense to the Government. At all times the plant and work areas shall be kept in a condition conducive to safety of workmen and the public and neat in appearance. Waste or surplus materials shall not be allowed to accumulate in the construction areas.
1.3.1 Flood Protection Works
In all cases where materials in the existing flood protection works are used or connected with the construction of new work under this contract, the work shall be so planned and executed that the new work shall be
SECTION 01 12 00 Page 2 completed to provide protection equivalent to the existing protection as the existing protection is weakened or removed. These operating restrictions shall be followed in order that the new work may be tied in, or connected promptly, by the Contractor, with the existing facilities so as to furnish a continuous service in an emergency. These ties or connections shall be made during periods of suspended construction operations and the Contractor shall leave incompleted pipe outlets and other structures in such conditions as to not interfere with the natural drainage from areas served by these pipes or structures.
1.4 CARE OF WATER
Full responsibility for care of water shall be borne by the Contractor until completion of work under this contract. The Contractor shall provide the materials and equipment and perform all work necessary to facilitate construction and to protect the work from damage by water. The Contractor shall make the needed investigations and determinations of conditions, both existing and anticipated concerning care of water. Plans for care of water are subject to approval by the Contracting Officer prior to construction. Facilities shall be removed upon completion of the work.
1.5 Project Survey and Layout
In addition to the requirements of FAR 52.236-17 Layout of Work, the Contractor shall provide a licensed land surveyor to check initial project control, and to provide and set hubs for project construction. The Contractor shall use (and reference in all as-built data) project stationing as described on the contract drawings. In addition, a licensed land surveyor shall provide final project embankment survey (i.e. to include major breakpoints, riverward toe, profile, top of levee at riverward/landward and landward toe) prior to placement of surfacing for government review and approval. If applicable a licensed land surveyor shall also provide, set and verify as built condition of major flood control structures/features; i.e. flood wall control. These surveys shall provide and verify both horizontal and vertical project control. This survey shall be used for final as-built embankment profile and cross section, and major flood control structure records, and recorded on the as-built condition in accordance with Section, As-Built Drawings.
The Contractor may utilize their own quality control personnel to provide interim surveys for quantity determination for payment in accordance with paragraph entitled Quantity Surveys (Apr 1984).
1.6 DISPOSITION OF CONSTRUCTION FACILITIES
All buildings and facilities constructed by the Contractor shall be maintained in a satisfactory condition with strict observance of the rules of sanitation, safety and order as may be established by the Contracting Officer. Prior to final payment under the contract, all buildings and facilities constructed by the Contractor for the Contractor's use shall be removed from the site by the Contractor.
SECTION 01 12 00 Page 3
1.7 ACCESS ROADS AND HAUL ROADS
1.7.1 Access Roads
Access roads as required for the prosecution of the work shall be maintained (including sprinkling for dust control, safety personnel, and traffic control) within the work areas assigned to the Contractor.
Consideration shall be given to the avoidance of interference with others, safety and frequency of traffic, subject to review and approval prior to construction. Access road areas shall be restored to their original or suitable condition upon completion of this contract. The Contractor shall be responsible for repair of damage to existing roads caused by the Contractor's operation.
1.7.2 Haul Roads
The Contractor shall construct haul roads as may be necessary for the conduct of the work without additional cost to the Government. The Contractor shall arrange the hauling operations so as to cause a minimum interference with traffic and shall develop Temporary Traffic Control (TTC) plan(s) and furnish all necessary traffic control devices and personnel as required to avoid additional hazards to the public. The Contractor shall perform routine day and night inspections of TTC elements as required by MUTCD and maintain all furnished traffic control devices at their expense and without additional cost to the Government. Lines, grades and widths for haul roads, shall be selected to fulfill the requirements for safe and efficient hauling operations and shall be approved by the Contracting Officer prior to construction. Haul roads shall have ample width to provide safety. Preference shall be given to one-way haul roads when these are feasible. All roads shall be maintained in original as-built condition during all periods of their use. Roads shall be sprinkled whenever, in the opinion of the Contracting Officer, control of dust is necessary to insure safe movements of construction traffic. Upon completion of work under this contract, roads shall be disposed of as directed by the Contracting Officer. All traffic control devices, culverts, guards, fences and other improvements on roads constructed for the Contractor's convenience and operations shall be removed from the project site and shall remain property of the Contractor. Use and repair of existing roads and bridges shall be subject to the requirements of local authorities. Prior to start of hauling operations on public roads, the Contractor shall furnish written evidence to the Contracting Officer that an agreement has been consummated with State and County officials on the use of public roads and bridges. Such agreements shall clearly relieve the Government of any responsibility for damage resulting from hauling across or on these roads.
1.7.3 Joint Use of Transportation Facilities
The Contractor may use jointly with Contractors and others, existing access and haul roads constructed by the Government or by others. Unless otherwise specifically authorized in writing, the Contractor will not be granted exclusive use of any access or haul road whether it be an existing road or one constructed by the Contractor. However, the use by others of roads constructed by or assigned to the Contractor primarily for the Contractor's use will be limited by the Contracting Officer to the minimum considered consistent with efficient prosecution of the work under this and other contracts in force. Maintenance of jointly used facilities shall be shared in proportion to use. In the event of a disagreement between this Contractor and others as to the use of any road, the decision
SECTION 01 12 00 Page 4 of the Contracting Officer shall be final. The Contractor shall not obstruct any existing road on the land controlled by the Government.
1.7.4 Waterway Crossings
The Contractor shall construct approved crossings where hauling is to be done across waterways with adequate openings for drainage and streamflow.
Structures for crossings shall be safe for all operating equipment and vehicles and shall be adequate for drainage and flow of the waterway.
After haul for construction has ceased, the structures constructed by the Contractor shall be removed and disposed of as directed.
1.7.5 Ramps
Ramps shall be provided and maintained for access of hauling equipment into excavation and waste areas. Locations, grades and width are subject to review and approval by the Contracting Officer prior to construction.
1.7.6 Drainage
The Contractor shall provide and maintain ditches, dikes and other facilities within and adjacent to the work areas to direct the surface and subsurface flow of water away from abutting private property and work in place or under construction by this and other contracts. The design, location, type and size of drainage facilities are subject to review and approval by the Contracting Officer prior to construction. PUBLIC ROADS
1.8 Lane Closure
One lane of the road must remain open at all times. The Contractor shall determine an appropriate method for the specific Temporary Traffic Control (TTC) zone one-lane, two-ways traffic control method in accordance with MUTCD requirements. The Contractor shall furnish all necessary personnel and traffic control devices, perform routine day and night inspections of TTC elements, and maintain all furnished traffic control devices to provide safety for motorists, bicyclists, pedestrians, workers, enforcement/emergency officials, and equipment as required by MUTCD The Contractor is required to coordinate the road/lane closure with the applicable state's Department of Transportation and USACE.
1.9 Traffic Control Devices
All traffic control devices (signs, arrow boards, barricades, lighting etc) by the Contractor, must conform with the U.S. Department of Transportation, Federal Highway Administration, Manual on Uniform Traffic Control Devices.
1.10 Temporary Traffic Control (TTC)
The Contractor shall be responsible for the safe control of traffic on all haul and access roads used primarily for the work under these specifications and at their crossings with roads used by others. The Contractor shall, at the Contractor's own expense, furnish all personnel, and traffic control devices necessary for the safe movement of all road users through or around Temporary Traffic Control zone. Traffic control plans, including a listing of equipment and its employment, shall be submitted for review and approval prior to construction.
SECTION 01 12 00 Page 5
1.11 Operations
When operations are being conducted near a U. S. or State Highway or when construction equipment is being used on or adjacent to such highway, the Contractor shall furnish all necessary traffic control devices and personnel to provide safe and effective movement of all road users through or around Temporary Traffic Control zone as required by MUTCD All required state and/or local permits shall be obtained at the Contractor's expense in advance and shall be provided to the COR. The highways and streets shall be kept open at all times.
1.11.1 Flaggers
The Contractor shall provide flaggers when:
a) Construction equipment and/or vehicles are blocking the roadway making it difficult for vehicles to pass or see or due to terrain.
b) One-way traffic is required thru a construction zone.
c) Trucks are pulling onto and/or off of a roadway or operating at a reduced speed causing a hazardous situation for drivers.
d) Anytime the Contractor feels that road users are at risk due to Construction activity.
Flagger shall have all qualifications, high-visibility safety apparel, and appropriate hand-signaling devices in accordance with MUTCD requirements.
The flagger shall be properly trained as required by the state. The Contractor shall furnish all necessary traffic control devices to establish appropriate TTC zone when the Flagger Control is utilized.
1.12 Road Closure
At each location designated by the Contracting Officer and where safe operation requires the closing of roads, streets or other travel arteries leading to the work under this contract, the Contractor shall furnish all appropriate traffic control devices to provide safety for motorists, bicyclists, pedestrians, workers, enforcement/emergency officials, and equipment during construction as required by MUTCD. Arrangements for closure of roads, streets or other travel arteries shall be made by the Contractor with local State, County or City officials. The Contractor shall notify the appropriate official in writing at least ten (10) days in advance of the date desired to close a road to traffic and shall furnish a copy of the agreement and approved Temporary Traffic Control plans to the Contracting Officer prior to closure.
1.13 State and Federal Highways
Where the Contractor hauls across or on State or Federal highways, the Contractor shall enter into all agreements with the State Highway Commission and shall comply with any restrictions they may impose relative to load limits, care of traffic and cleanup. Such agreements shall clearly relieve the Government of any responsibility for damages resulting from hauling across or on State highways. Copies of such agreements shall be furnished to the Contracting Officer before the Contractor begins hauling on these highways.
1.14 State and Local Public Roads
(a) Load Limits:
The Contractor is requred to check with the appicapble state's Department
SECTION 01 12 00 Page 6 of Transportation and local County Road Commissions for restrictions on the load weights of haul vehicles using highways and county roads during the spring thaw period. The load restrictions are usually imposed from 1 April through June depending on actual weather conditions.
(b) Hauling Regulations:
Prior to start of hauling operations on public roads, the Contractor shall furnish evidence to the Contracting Officer that an agreement has been consummated with State and County officials on the use of public roads and bridges. Such agreements shall clearly relieve the Government of any responsibility for damage resulting from hauling across or on these roads.
1.15 City Streets
Where the Contractor intends to cross or to use city streets for haul roads the Contractor shall enter into an agreement with the City and shall comply with any restrictions the City may impose relative to load limits, care of traffic and cleanup. Such agreements shall clearly relieve the Government of any responsibility for damage resulting from hauling across or on these highways. A copy of all such agreements shall be furnished the Contracting Officer before the Contractor begins hauling in city streets.
1.16 Utility Lines
It shall be the responsibility and obligation of the Contractor to make all arrangements with the affected companies for the necessary moving and alterations of utility lines and the continuation of service during construction as covered by the plans and specifications.
1.17 COOPERATION WITH OTHER CONTRACTORS
The Contractor shall cooperate and coordinate work with that of the State and others (public and private) working in the area during the life of this contract. The Contractor shall coordinate work with others to avoid undue interference and shall conduct operations, other than approved required access, within the limits of the assigned construction area or construction right-of-way limits. The Contractor shall cooperate with others as necessary in the interest of timely completion of all work and in the event of disagreement the decision of the Contracting Officer shall be final.
1.18 WINTER WORK
No separate payment will be made for winterizing or other protective measures that are required for the Contractor to maintain the scheduled progress. Special requirements for the placement of concrete or embankment in cold weather are covered in the applicable sections of these specifications.
1.19 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office
SECTION 01 12 00 Page 7 that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Proposed Methods of Operation; G-AO
Progress Charts; G-AO
Construction Right-of-Way
(Right-of-Way Agreements)
State and Federal Highways
(Agreements for hauling on highways)
State and Local Public Roads
(Agreements for hauling on roads)
Temporary Traffic Control (TTC); G, AO
SD-02 Shop Drawings
Care of Water; G-AO
SD-11 Closeout Submittals
Warranty of Construction
(List of warranties with copy of each)
1.20 SPECIAL INSTRUCTIONS FOR PROGRESS CHARTS
To be submitted in accordance with the SECTION 00 72 00, GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Schedule for Construction Contracts" shall indicate the required data for each of the principal features of the work. Contract changes or modifications will not include extensions of time unless the updated progress chart shows that the contract completion date is delayed due to the affect of the change on one or more principal features of the work.
1.21 WARRANTY OF CONSTRUCTION (MAR 1994)
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
SECTION 01 12 00 Page 8
(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of--
(1) The Contractor's failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.
(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud. (FAR 52.246-21)
1.22 TELEPHONE/INTERNET
The Contractor is responsible for arranging telephone/Internet service for the Contractor's trailer through the local telephone company.
1.23 TRANSPORTATION OF GOVERNMENT PERSONNEL
The contractor shall provide the on-site Government Representatives with
SECTION 01 12 00 Page 9 transportation from the boat landing to the location of on-site work activity on an as needed basis. This shall be accomplished through two-way radio communication. All marine equipment used to transport personnel shall meet Coast Guard standards, and all weight restrictions and onboard safety device requirements will be strictly enforced.
1.24 River Stabilization Structures Report, MRD Form 701
See Section 35 31 20 for MRD Form 701 requirements.
1.25 PORTABLE TOILETS
Toilet facilities will not be available for Contractor's use. The Contractor shall provide and maintain portable toilets for use by the Contractor's staff and Government staff. Toilet(s) shall be placed at the location directed by the Contracting Officer. To prevent overturning by high winds, all portable toilets shall be anchored down.
1.26 FEDERAL HOLIDAYS AND WORKING HOURS
The Contractor will have access to the facility for work during normal plant business hours from 0700 to 1700 hrs Monday through Friday, excluding any federally recognized holidays or observance days. The Contractor shall plan all work accordingly. These hours will be strictly adhered to unless the Government determines work outside this time is beneficial to the Government or a bilateral modification for extended working hours is executed.
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Juneteenth 19 June Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If the wage determination has a discrepancy with the above list of observed Federal holidays, then the wage determination takes precedence.
PART 2 NOT USED
PART 3 NOT USED
-- End of Section --
SECTION 01 12 00 Page 10
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
PART 2 PRODUCTS
2.1 Entire work, complete, for quarried stoneas shown on the drawings and in the specifications at Sandy Point Chute, Boyer Billabong, and Tobacco Chute (12 Structures)(CLIN #0001)
2.1.1 Work Included
2.1.2 Measurement (Ton)
2.1.2.1 Barge displacement Method
2.1.2.2 Scale Method
2.1.2.3 Scales
2.1.2.4 Barge Displacement Tables
2.1.3 PAYMENT
2.2 ALL REMAINING WORK (CLIN #0002)
2.2.1 Work Included
2.2.2 Measurement
2.2.3 Payment
PART 3 EXECUTION (NOT USED)
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "FIO" designation are for information only. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Data
Barge Displacement Tables; G-AO (Para. 2.1.2.1 b.) if selected method of measurement by Contractor
Method of Stone Measurement; G-AO (Para. 2.1.2)
SD-13 Certificates
Scale Certification and Weigh Bills; G-AO (Para. 2.1.2.2)
PART 2 PRODUCTS
2.1 Entire work, complete, for quarried stoneas shown on the drawings and in the specifications at Sandy Point Chute, Boyer Billabong, and Tobacco Chute (12 Structures)(CLIN #0001)
2.1.1 Work Included
The work includes all material, equipment and labor of furnishing, hauling, handling, stockping, shaping banks for placement, and placing of quarried stone as specified herein and shown on the drawings.
2.1.2 Measurement (Ton)
The "Barge Displacement Method" or the "Scale Method" shall measure stone used in construction of structure repair delivered to the site by waterway for payment. The method used will be at the option of the Contractor, and specified to the Contracting Officer in writing. The "Scale Method" shall measure stone delivered to the construction site by land haul for payment. Measurement shall be in "short tons" (2,000 lbs.) and all cost for measuring the stone for payment shall be borne by the Contractor.
2.1.2.1 Barge displacement Method
If stone is delivered by barge, the weight of each barge load of stone may be determined by barge displacement. A barge of stone to be paid for by displacement method shall not be unloaded or removed from the work site until all necessary measurements are made for determining payment quantities delivered and/or used. The measurements will be made in the
SECTION 01 22 00 Page 2 presence of a Contractor quality control officer, either by the Government Inspector, or by the Contractor in the presence of the Government Inspector.
a. Each barge on which stone is furnished shall be suitably marked with paint of a contrasting color at each of three displacement gaging points along each side of the barge. The marks shall be perpendicular to the edge of the barge, 4 inches wide and 1 foot in length, painted on both the deck and side at three equally spaced points beginning at the rake. The barge name or number shall be affixed to the deck and sides of the barge, both fore and aft, and shall be of sufficient size and legibility so as to be plainly seen and read.
b. Barge Displacement Tables: The Contractor shall furnish to the Contracting Officer a barge displacement table not less than 10 days prior to unloading stone from any barge for which displacement tables have not been previously furnished and approved. The table shall be certified accurate by a person or firm, other than the Contractor, accustomed to performing this service and approved by the Contracting Officer. Barge tables furnished shall contain, in parallel columns, the draft of the barge in feet and tenths from zero to the full depth of the barge, and the corresponding gross displacement to the nearest ton. Tables submitted shall show the name or number of the barge, the barge dimensions, the barge owner, the name of the manufacturer, and the certification of the person or firm preparing the table. The Contractor shall furnish with the barge displacement table a drawing or sketch of each barge, dimensioned in sufficient detail to permit checking of the tables. The drawing shall show as a minimum the length, width, and depth of the barge and dimensions of rake or rakes, including radius, origin of radius, and headlong dimensions.
c. Weight Scales: If the Contractor selects payment by displacement method, he must also ensure that scales approved by the Contracting Officer are available at all times at a location approved by the Contracting Officer. The Contractor will bear the cost and responsibility of weighing stone furnished for this contract on these scales.
2.1.2.2 Scale Method
Stone delivered at the site of the work may be weighed for payment on public scales which have been approved by the Contracting Officer and which have been certified by the State wherein the scales are located.
The stone shall be weighed to the nearest 20 pounds and the net weight reduced to the nearest hundredth of a ton. If public scales are not available, the Contractor may furnish approved scales subject to certification acceptable to the Contracting Officer, and the weighing service may be supplied by an independent professional organization approved by the Contracting Officer. The Contractor shall furnish the Government Inspector a copy of each printed weigh bill when self-printing scales are used, or a copy of the weigh bill signed by the weighmaster as each load is delivered to the job site. Each weigh bill shall contain the following: date, unit number, time of gross weight, time of net weight, name of project, contract number, name of Contractor and signature of the weigher.
2.1.2.3 Scales
If public scales or an independent professional weighing service is not available, stone delivered to the site of the work may be weighed for
SECTION 01 22 00 Page 3 payment by a bonded weighmaster on scales which have been approved by the Contracting Officer and which have been certified by the applicable State wherein the scales are located. The Contractor shall furnish the Government Inspector a copy of each weigh bill signed by the bonded weighmaster as each load of stone is delivered.
2.1.2.4 Barge Displacement Tables
If the Contractor selects payment by the scale method, he must also provide to the Contracting Officer all of the barge displacement tables, drawings, and data required in para. 2.1.2.4 b.
a. Stone shall be weighed for final payment during transport to the site by one of the following methods at the option of the Contractor and with approval of the Contracting Officer. The materials shall be weighed to the nearest 20 pounds and the net weight reduced to the nearest hundredth of a ton.
b. Stone delivered at the site of the work may be weighed on public scales which have been approved by the Contracting Officer and which have been certified by the State wherein the scales are located. If public scales are not available, the weighing service may be supplied by an independent professional organization approved by the Contracting Officer. The Contractor shall furnish the Contracting Officer a copy of each printed weigh bill, when self-printing scales are used, or a copy of the weigh bill signed by the weigh master as each load is delivered to the jobsite. (Each weigh bill shall contain the following: date, unit number, time, tare weight, gross weight, net weight, name of project, contract number, name of Contractor, and signature of weigher.) All costs for weighing the materials shall be borne by the Contractor.
2.1.3 PAYMENT
Applicable unit price times the number of tons of stone placed.
2.2 ALL REMAINING WORK (CLIN #0002)
2.2.1 Work Included
The work of this item shall include but not be limited to labor, material, and equipment needed for the all remaining work not listed above for the completion of the project including, but not limited to, clearing and grubbing, access improvements, site restoration, seeding, mobilization and demobilization.
2.2.2 Measurement
Job.
2.2.3 Payment
Payment for this item shall be the lump sum, made on a progressive basis, based on the percentage of work completed.
PART 3 EXECUTION (NOT USED)
SECTION 01 22 00 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
PART 1 GENERAL
1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.2 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR
PAYROLLS
1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.4 CONTRACTOR PERFORMANCE EVALUATIONS
1.5 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1.6 CONTRACT DRAWINGS AND SPECIFICATIONS
1.6.1 SETS FURNISHED
1.6.2 DISTRIBUTION
1.6.3 NOTIFICATION OF DISCREPANCIES
1.6.4 OMISSIONS
1.7 SUBMITTALS
1.8 PAYMENT
1.8.1 PROMPT PAYMENT ACT
1.8.2 PAYMENT FOR MATERIALS STORED OFFSITE
1.9 AVAILABILITY AND USE OF UTILITY SERVICES
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.11 IOWA SALES AND USE TAX
1.12 CONTRACTOR QUALITY CONTROL (CQC)
1.13 NONDOMESTIC CONSTRUCTION MATERIALS
1.14 DAILY WORK SCHEDULES AND WEEKLY COORDINATION MEETINGS
1.15 AS-BUILT DRAWINGS
1.16 PARTNERING
1.16.1 Team-Led (Informal) Partnering
1.17 PROFIT
1.18 LABOR CONDITIONS APPLICABLE TO TEMPORARY FACILITIES
1.19 DRAWING SCALES
1.20 SIGNAL LIGHTS
1.21 OMBUDSMAN
PART 2 NOT USED
PART 3 NOT USED
SECTION 01 30 00.24 Page 1
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
PART 1 GENERAL
1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
In accordance with FAR 31.105(d)(2)(i)(b), for the predetermined schedule of construction equipment use rates, use Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule. Copies of each regional schedule may be obtained through the following internet site:
https://www.publications.usace.army.mil/USACE-Publications/Engineer-Pamphlets/ on pages 10 and 11 of 13.
1.2 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR PAYROLLS
a. Use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.
b. Obtain and provide for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with the Wage Rate Requirements statute. Use the electronic payroll service to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract. The electronic payroll service must be capable of preserving these payrolls and related basic records for the required three years after contract completion. Obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of the construction contract.
c. The Contractor's provision and use of an electronic payroll processing system must meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the FAR;
(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;
(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export into an Excel spreadsheet to be imported into the contractor's mode of Resident Management System 3.0;
(5) demonstrated security of data and data entry rights;
(6) ability to produce Contractor-certified electronic versions of weekly
SECTION 01 30 00.24 Page 2 payroll data;
(7) ability to identify erroneous entries and track the data/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;
(8) capable of generating a durable record copy in a Compact Disc (CD) or Digital Versatile Disc (DVD) and Portable Document Format (PDF) file record of data from the system database at the end of the contract closeout. This durable record copy of data from the electronic payroll processing system must be provided to the Government during contract closeout.
d. All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service must be included in the Contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services must not be a separately bid or reimbursed item under this contract.
1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
- U.S. Department of Labor Veterans’ Employment and Training Service
(VETS):
https://www.dol.gov/vets/
- Federal Veteran Employment Information: https://www.fedshirevets.gov/
- Veterans Opportunity to Work (VOW) Program:
https://www.benefits.va.gov/vow/
- U.S. Army Warrior Transition Command Employment Index:
https://wct.army.mil/modules/employers/index.html
- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes
1.4 CONTRACTOR PERFORMANCE EVALUATIONS
See Federal Acquisition Regulation (FAR) Subpart 42.1502(e) for the requirements on past performance evaluations for construction contracts.
For construction contracts valued at or above $750,000.00, including all modifications, the USACE will evaluate Contractor's performance using the web-based Contractors Performance Assessment Reporting System (CPARS).
After the USACE drafts an evaluation (interim or final), the Contractor will have the opportunity to access, review, comment and either concur or non-concur with the evaluation in the CPARS system for a period of 60 days. Access to the CPARS system requires either specific software called PKI certification (recommended method) or a username and password. The PKI certification is a Department of Defense recommendation and to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and may be purchased from an External Certificate Authorities (ECA) vendor. Current information
SECTION 01 30 00.24 Page 3 about the PKI certification process and contacting vendors can be found on the web site: https://www.cpars.gov .
1.5 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1. Gener al secur i t y r equi r ement s and gui dance:
The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts.
The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations.
Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures.
The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures-this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
2. Ant i t er r or i sm ( AT) Level I t r ai ni ng:
All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training.
Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).
3. Physi cal secur i t y and access cont r ol r equi r ement s:
All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as "NCIC-III") and Terrorist Screening Database (commonly referred to as
SECTION 01 30 00.24 Page 4
"TSDB"). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.
3.1 Submit a complete, updated and signed, list of all Contractor and subcontractor personnel, including their titles and intended working hours, who will be working on site prior to start of work. This listing shall be revised and resubmitted when personnel changes occur. (SUBMITTAL
FIO)
3.2 Personnel Risk Assessment
A minimum of seven days prior to engaging in work submit, to the COR or Project POC, a Personnel Risk Assessment (PRA) for each employee requiring authorized unescorted access to the Jobsite. The Contractor employee will only be allowed authorized unescorted physical access after the PRA is shown to and approved by the Government.
3.3 Authorized Unescorted Access Requirements
Perform a PRA on all Contractor personnel that require authorized unescorted access to the Jobsite. Costs associated with the execution of the PRA shall be at the expense of the Contractor. The content of the PRA is defined by the requirements as follows: (SUBMITTAL PRA)
a. Criminal Check - Obtain a criminal background check, completed within the last seven years (assuming continuous employment, otherwise a new one must be accomplished), on all Contractor personnel that require authorized unescorted access to the Jobsite. A minimum of a 7-year criminal background check with the state patrol office shall be performed from all states of residence and employment, for the past seven years. The Project Security Officer through the Contracting Officer will approve, disapprove, or revoke authorized unescorted access to the Jobsite as a result of the seven-year background check.
b. Identity Verification - Contractor employees shall provide positive verification of individual identity prior to authorized unescorted access to the Jobsite. Acceptable forms of identity verification are documents issued by a federal Government agency that include: the individual's photograph, name, and date of birth, such as a passport or military identification (ID) card. Additionally, a state issued driver's license or ID card is acceptable for identity verification.
c. The Criminal Check and Identity Verification shall be updated at least every seven years for each employee requiring authorized unescorted access to the Jobsite.
d. Escort Requirements - Contractor personnel not cleared for authorized access to the Jobsite may be escorted by Government or Contractor personnel that have authorized unescorted access to the Jobsite. All costs related to the escorting of non-cleared personnel shall be at the expense of the Contractor. Additional burden shall not be placed upon the Government to provide these escorts. Prior to access, coordination with the Project Security Officer is required, including but not limited to:
SECTION 01 30 00.24 Page 5
(1) Verification of identity with photo identification
(2) Name of escorting individual and verification of unescorted status
(3) Time of entry into the Jobsite
(4) Time exiting the Jobsite.
1.6 CONTRACT DRAWINGS AND SPECIFICATIONS
1.6.1 SETS FURNISHED
Utilize the bid drawings and specifications as amended in the performance of the work until the electronic Adobe Acrobat.pdf conformed specifications and contract drawings (i.e., bid drawings that have been posted with all amendment changes) are sent electronically to the Contractor. The work must conform to the contract drawings, set out in the drawing index, all of which form a part of these specifications. The work must also conform to any of the standard details bound or referenced herein. The Contractor shall be responsible for making copies of all plans and specifications as needed for the duration of the contract.
1.6.2 DISTRIBUTION
The Government will provide the Contractor with a CD-ROM or DVD-ROM or sent electronically containing Adobe Acrobat.pdf contract drawings and conformed specification sets and editable CAD file drawings (format defined in Section 01 78 39.00 24 AS-BUILT DRAWINGS). Prepare final record or as-built drawings as defined in Section 01 78 39.00 24 AS-BUILT DRAWINGS.
1.6.3 NOTIFICATION OF DISCREPANCIES
Check all drawing files furnished by the Government immediately upon their receipt and promptly notify the Contracting Officer of any discrepancies.
Follow dimensions marked on drawings in lieu of scale measurements.
Enlarged plans and details govern where the same work is shown at smaller scales. All scales shown are based on a standard drawing size of 22" x 34". If any other size drawings are furnished or plotted adjust the scales accordingly. Advise sub-contractors of the above. Compare all drawings and verify the figures before laying out the work and take responsibility for any errors which might have been avoided thereby.
1.6.4 OMISSIONS
Omissions from the drawings or…