This request for proposal solicits bids for the rehabilitation of kettle structures and ponds at the Harrison Lake National Fish Hatchery in Charles City, Virginia. Work includes replacing water control structures, water supply piping, drain piping, and valves for the ponds. Site visits are scheduled for July 28th and August 4th, 2021 starting at 10:00 AM Eastern Time at the hatchery address provided. Bids are due by the date specified in the solicitation issued by the U.S. Fish and Wildlife Service Region 2. The selected contractor will replace existing infrastructure to rehabilitate the pond and kettle systems at the national fish hatchery.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HARRISON LAKE NATIONAL FISH HATCHERY
CHARLES CITY, VA
POND AND KETTLE
REHABILITATION PROJECT
TECHNICAL SPECIFICATIONS
MARCH 2021
ENGINEERING • PLANNING • DEVELOPMENT • MANAGEMENT
126705 – Harrison Lake National Fish Hatchery TOC-1
TABLE OF CONTENTS
HARRISON LAKE NATIONAL FISH HATCHERY
WATER SUPPLY
REHABILITATION PROJECT
TECHNICAL SPECIFICATIONS
Division 1 - General Requirements
01010 Summary of Work 01052 Surveys and Layout 01150 Measurement and Payment 01300 Submittals 01410 Testing and Laboratory Services 01575 Temporary Erosion and Sedimentation Control 01666 Pipe & Manhole Leakage Testing 01700 Project Closeout 01710 Cleaning 01720 Project Record Documents
Division 2 - Site Work
02100 Clearing and Grubbing 02113 Demolition and Modifications 02221 Excavating, Trenching and Backfilling 02250 Soil Compaction 02260 Earth Dam 02401 Dewatering 02483 Topsoil and Seeding 02520 Gravel Well Construction 02605 Buried Pipe & Fittings 02641 Buried Valves & Stops 02642 Stainless Steel Gates
Division 3 - Concrete
03100 Concrete Formwork 03300 Cast-in-Place Concrete
126705 – Harrison Lake National Fish Hatchery 01010-1
SECTION 01010 - SUMMARY OF WORK
PART 1 – GENERAL
1.01 DESCRIPTION
A. The work to be performed under this Contract is shown on the Drawings and defined in the Specifications.
This Section covers certain specific information to further clarify the intent and requirements of the Contract.
B. The DESCRIPTION paragraph in each section is a statement or short word summary of the content of the section. This paragraph is not intended to "scope" the section or to imply a trade responsibility. It is merely a brief description of the significant items described in the section and is used to simplify the finding of specific information.
C. The "related work" paragraphs are also not meant to be all inclusive. Again, they serve the function of assisting the reader in locating specific information.
1.02 SUMMARY OF WORK DESCRIPTION
A. The project will include the replacement of existing water control structures (commonly referred to as kettles), water supply piping, drain piping, and valves as shown on the engineering drawings.
1.03 Work Restrictions
A. Contractor shall provide competent, suitably qualified personnel to survey and lay out the Work and perform construction as required by the Contract Documents.
Contractor shall at all times maintain good discipline and order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during normal work hours, Monday through Friday. Contractor will not perform Work on a Saturday, Sunday, or any legal holiday. Contractor may perform Work outside regular working hours or on Saturdays, Sundays, or legal holidays only with
126705 – Harrison Lake National Fish Hatchery 01010-2
Owner’s written consent, which will not be unreasonably withheld.
1. Normal work hours shall be Monday through Friday, 7 AM to 5 PM.
C. Contractor shall be responsible for laying out the Work, shall protect and preserve the established reference points and property monuments, and shall make no changes or relocations without the prior written approval of Owner. Contractor shall report to Engineer whenever any reference point or property monument is lost or destroyed or requires relocation because of necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such reference points or property monuments by professionally qualified personnel.
D. Contractor shall confine construction equipment, temporary construction facilities, the storage of materials and equipment, and the operations of workers to the Site, adjacent areas that Contractor has arranged to use through construction easements or otherwise, and other adjacent areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and such other adjacent areas with construction equipment or other materials or equipment. Contractor shall assume full responsibility for (a) damage to the Site; (b) damage to any such other adjacent areas used for Contractor’s operations;
(c) damage to any other adjacent land or areas; and
(d) for injuries and losses sustained by the owners or occupants of any such land or areas; provided that such damage or injuries result from the performance of the Work or from other actions or conduct of the Contractor or those for which Contractor is responsible.
E. If a damage or injury claim is made by the owner or occupant of any such land or area because of the performance of the Work, or because of other actions or conduct of the Contractor or those for which Contractor is responsible, Contractor shall (a) take immediate corrective or remedial action as required by Paragraph 7.12, or otherwise; (b) promptly attempt to settle the claim as to all parties through negotiations with such owner or occupant, or otherwise resolve the claim by arbitration or other dispute resolution proceeding, or at law; and (c) to the fullest extent permitted by Laws and Regulations, 126705 – Harrison Lake National Fish Hatchery 01010-3 indemnify and hold harmless Owner and Engineer, and the officers, directors, members, partners, employees, agents, consultants and subcontractors of each and any of them from and against any such claim, and against all costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against Owner, Engineer, or any other party indemnified hereunder to the extent caused directly or indirectly, in whole or in part by, or based upon, Contractor’s performance of the Work, or because of other actions or conduct of the Contractor or those for which Contractor is responsible.
END OF SECTION
126705 – Harrison Lake National Fish Hatchery 01052-1
SECTION 01052 - SURVEYS AND LAYOUT
PART 1 - GENERAL
1.01 DESCRIPTION
A. The Work covered by this Section includes the survey-ing, staking and laying out of the Work.
B. The contractor is responsible to establish the proposed baselines, establish and maintain control at the site. The contractor shall bear the costs for this work.
1.02 QUALITY ASSURANCE
A. All survey work for laying out the Work, for measuring pay items, and for preparing Record Drawings shall be done by the Contractor by use of a qualified Surveyor, as Chief of Party, and qualified assistants experienced in this type of work.
B. Contractor is responsible for the accuracy of his own work and shall maintain all reference points, stakes, etc., throughout the life of the Contract.
1.03 SUBMISSIONS
A. See Section 01300.
B. Copies of computations and reference points specified in Paragraph 3.04, submitted daily.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Provide all instruments, rods, measures, stakes, rib-bons, nails and all other materials and equipment to perform the work of this Section accurately. All materials/equipment shall be appropriately calibrated and in good working condition.
126705 – Harrison Lake National Fish Hatchery 01052-2
PART 3 - EXECUTION
3.01 INSPECTIONS
A. Carefully examine the Drawings and immediately report to Engineer any error, apparent discrepancy in the data shown or omissions of data required for accurately accomplishing the Work.
3.02 LAYOUTS
A. Establish any additional base lines which may be re-quired to locate the Work and provide suitable, ade-quate and sufficient number of bench marks, slope stakes, batter boards, and other required control and reference points.
B. Perform all required surveys and accurately lay out the Work.
3.03 MEASUREMENTS
A. Make all measurements for payment purposes as set forth under Section 01150.
3.04 FIELD NOTES AND COMPUTATIONS
A. Make all computations necessary to establish the exact position of the Work. Maintain field notes of all ties, baselines, reference points, bench marks and other control points. Also maintain field notes of all data required to be shown on the record drawings.
3.05 TIES
A. Property Monuments - Prior to any work in the vicinity of an existing property monument or marker, accurately provide at least four ties to physical objects which will not be damaged, destroyed or disturbed in the course of the Work.
B. New Underground and Underwater Work - On all new Work which will be buried or submerged in water and will not be visible at the completion of the Work, such as ends of house connections, stub-outs, dead ended pipes, outfall pipes, and like objects, provide elevations and three ties to physical objects to facilitate the locating of such items at a later date.
126705 – Harrison Lake National Fish Hatchery 01052-3
3.06 REPLACEMENTS
A. All existing and new reference points, ties, bench marks, property markers and other control points dam-aged, destroyed or disturbed during construction shall be reestablished and replaced.
126705- Harrison Lake National Fish Hatchery 01150-1
SECTION 01150 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.01 DESCRIPTION
A. This Section covers the requirements for measurements and records for payment purposes, and describes the items under which payments will be made for all work performed under this Contract.
B. Items not specified to be measured or paid for shall be considered subsidiary to appropriate specified items at no change in the specified item cost.
1.02 MEASUREMENT REQUIREMENTS
A. Where payments will be made for removing existing materials, notify the Engineer so that they may inspect the materials to be removed, so that they may witness the measuring, and so that they may approve the record of measurements. All materials removed without conforming to the above procedures, and which Engineer cannot verify or substantiate, will not be paid for.
B. Maintain complete, neat, clean, and legible field notes for all measured items. Notes shall contain spaces for Contractor's and Engineer's signatures plus additional space for comments. An original and copy shall be made for all notes and one copy shall be turned over to Engineer daily. The Engineer's signa-ture shall not be construed as an acceptance of the Work, or the measurements made, but shall mean that he was present when the measurements were made.
1.03 SUBMITTALS
A. See Section 01300.
B. Field notes of all measurements for payment purposes delivered to Engineer daily.
126705- Harrison Lake National Fish Hatchery 01150-2
1.04 SCHEDULING
A. Notify Engineer, as far in advance as possible, of the making of measurements so that the Engineer may observe existing conditions, work being performed, and measurements being made.
B. Allow for and afford Engineer ample time, space and equipment to observe measurements and to verify measurements and elevations.
PART 2 - PRODUCTS
2.01 GENERAL
A. Provide all labor, materials, facilities, levels, measuring devices and all other equipment necessary to properly and accurately perform all measurements for payment purposes.
PART 3 - EXECUTION
3.01 GENERAL REQUIREMENTS & STIPULATIONS
A. Perform all measuring required under this Section.
B. No separate payments will be made for work under this Contract except for the pay items stipulated in this PART 3. All costs in connection with the Work shall be included in one or more of the pay items as appropriate.
C. Each pay item shall be full compensation for all costs in connection with the item including but not limited to:
1. The furnishing of all materials, labor, equipment, tools, and all incidentals.
2. The installation of all materials, equipment, facilities, accessories and appurtenant items.
3. The proper share of overhead and profit.
4. All testing requirements.
126705- Harrison Lake National Fish Hatchery 01150-3
5. All dust control measures.
6. All related and incidental work and items necessary or required to complete the Work.
7. Record and maintain record drawings throughout the project construction period.
D. Each pay item which specifically involves excavation shall be considered to include full compensation for:
1. Backfilling with suitable excavated material in compacted lifts unless paid for under other items.
2. Excavation in earth.
3. Disposal of any surplus.
4. Installation and removal of sheeting and bracing.
3.02 MEASUREMENT & PAYMENT ITEMS
A. The names of the following items are abbreviated forms of the Bid Items as contained in the Bid Form. The names, as shown below or on the Bid Form, shall not be construed to represent a complete description of all of the Work included under such items and are provided only as a means of identification and for ease of conversation.
Item No.1: MOBILIZATION/DEMOBILIZATION:
Lump sum, no measurement required.
Payment shall be lump sum for work items necessary for the movement of personnel, equipment and materials to the project site, establishment of all field offices and related facilities necessary to perform the work on the project and for all other costs and operations which must be performed prior to the beginning of the work. In addition, this pay item will include all costs associated with movement of personnel, equipment and materials from the project site by final acceptance of the project and all clean up work as required herein.
The first 60 percent (60%) of the lump sum shall be paid once all personnel, equipment and
126705- Harrison Lake National Fish Hatchery 01150-4 materials necessary to initiate excavation and foundation preparation is on site. The final 40% shall be paid at Substantial Completion, once a majority of Demobilization has occurred.
Item No.2: CONTROL OF WATER / DEWATERING (SEC. 02401):
Lump sum, no measurement required.
Payment shall be lump sum for complete control of water, including installation and subsequent removal of temporary cofferdams, placement, handling and maintenance of pumps and any other miscellaneous work necessary to keep the work area dry. This item also includes the installation and removal the plugs for the existing intake pipes to allow for the removal and installation of new valves and appurtenances within the gate chamber.
The first 60 percent (60%) of the lump sum shall be paid once the temporary cofferdam and appurtenances are in place and properly functioning. The remaining 40% shall be paid by equal installments throughout the remaining con-tract period, with 100 percent being paid upon final completion of the project.
Item No.3: CLEARING AND GRUBBING (SEC. 02100):
Lump sum, no measurement required.
Payment shall be lump sum for the removal and off-site disposal of vegetation, cutting of trees, removal of roots, stumps, rocks, muck, and other objectionable materials deleterious to the work as shown on the Drawings and/or as directed by the Engineer.
Item No.4: EROSION PREVENTION & SEDIMENT CONTROL (Section 01575):
Lump sum, no measurement required.
Payment shall be lump sum for the installation, maintenance and removal of erosion control and slope protection measures to prevent the
126705- Harrison Lake National Fish Hatchery 01150-5 discharge of turbid water and/or sediment from the project site as shown on the Drawings.
Item No.5: GENERAL EXCAVATION (Section 02221):
Measure cubic yardage of material excavated and stockpiled from the site for the construction of the spillways and piping based on the payment limits on the Drawings.
Payment shall be per cubic yard of common material excavated as specified.
Item No.6: EMBANKMENT MATERIAL (Sections 02250):
Measure the cubic yardage of Embankment Material required to be placed, compacted, and tested as indicated by the payment limits shown on the Drawings and/or directed by the Engineer.
Laboratory confirmation testing for compliance to the gradation specification and field density tests are considered subsidiary to this item.
Payment shall be per cubic yard of Embankment Material placed, compacted, and tested.
Item No.9: LANDSCAPE RESTORATION (SEC. 02483):
Lump sum, no measurement required.
Payment shall be lump sum for applying loam/topsoil, seed, and hay mulch to restore the landscape as shown on the Drawings and other area disturbed due to the activities of the project as directed by the Engineer.
Item No.10: CONCRETE DEMOLITION:
Lump sum, no measurement required.
Payment shall be lump sum for the demolition and disposal of all concrete as required or directed by the Engineer.
Item No.11: CAST-IN-PLACE CONCRETE (SECTION 03100/ 03200/ 03300):
126705- Harrison Lake National Fish Hatchery 01150-6
Measure the cubic yard volume of Cast-In-Place Concrete, based on payment limits shown on the Drawings to extend the height of the kettle walls as shown on the Drawings and/or directed by the Engineer.
Payment shall be per cubic yard, placed as specified for all cast in place concrete. The unit price shall include the cost for form work, reinforcing steel, proper cleaning and preparation of all surfaces on which concrete will be placed, curing, and finish work.
Item No.12: REMOVAL & SALVAGE OF EXISTING PIPING AND
VALVES:
Lump sum, no measurement required.
Payment shall be lump sum for the removal, salvage and transport of existing piping and valves from the site to a location designated by USFWS. Excavation and disposal of existing material required for the work shall be paid for subsidiary to GENERAL EXCAVATION.
126705 – Harrison Lake National Fish Hatchery 01300-1
SECTION 01300 - SUBMITTALS
PART 1 - GENERAL
1.01 DESCRIPTION
A. This Section generally describes the types of submit-tals required during construction, procedures for making submittals, the preparation of submittals and the times submittals are required.
B. Additional submissions are required by the Instructions to Bidders and the General Conditions.
Such submittals generally include such things as Bids and Bidding Documents, insurance policies, certifications of bond and insurance coverage, Applications for Payment, requests for Change Orders, guarantees, permits, certifications and documents required by Federal, State and Local authorities, submissions required by utility companies and other persons, firms or organizations and other such submit-tals.
C. The requirements of this Section are general in nature and basically apply to all Sections of the Specifica-tions. Additional submissions and more specific requirements on submissions are contained in the various Specification Sections. In each individual Section, no attempt was made to cover or repeat the submissions contained in this Section and, therefore, the total of all submissions required are the combina-tion of those described in this Section plus those specified in the various other Sections.
D. All shop drawings and design submittals shall be submitted to the Engineer for approval.
1.02 IDENTIFICATION OF SUBMITTALS
A. Completely identify each submittal and resubmittal by showing at least the following information (attached form may be used):
1. Name of Project.
2. Name, address and telephone number of Contractor and Contractor's stamp of approval, indicating
126705 – Harrison Lake National Fish Hatchery 01300-2 that the submission has been thoroughly checked by Contractor for conformance and fit.
3. Name, address and telephone number of individual, firm or organization who will be doing the fabri-cation, supplying or manufacturing of equipment and materials and the name of the individual who may be contacted for further information.
4. Drawing number and Specification Section number to which submittal applies.
5. The location, service, equipment designation and other information to specifically indicate the item for which acceptance is requested.
6. Whether it is an original submittal (first submission) or a resubmittal (second, third, etc., submission).
Submissions not containing the above will be returned to Contractor, unreviewed by Engineer.
1.03 COORDINATION OF SUBMITTALS
A. Prior to submitting to Engineer and NHDES, fully coordinate all interrelated work. As a minimum, do the following:
1. Determine and verify all field dimensions and conditions, materials, catalog numbers and similar data.
2. Coordinate with all trades, subcontractors, other contractors, public agencies, and utility com-panies and secure all necessary approvals, in writing.
3. Clearly indicate any deviations from the Contract Documents.
B. Make submittals in groups containing all associated items that in some way depend upon each other. This also applies to color charts, as one color may not be able to be selected without the selection of other colors so as to form a color coordinated group.
Engineer may elect not to review partial, incomplete submissions, whereupon he will return the incomplete submission to the Contractor for a resubmission of a complete submittal.
126705 – Harrison Lake National Fish Hatchery 01300-3
1.04 TIMING OF SUBMITTALS
A. Except where otherwise specifically noted, allow 15 days, after receipt by Engineer, for Engineer to review and process submittals. Make submittals far enough in advance of scheduled dates of installation to provide time for reviews, for securing necessary acceptance, for possible revisions and resubmittals, and for placing orders and securing delivery.
B. Submissions may be returned unreviewed, rejected for several reasons, accepted conditioned upon submission of related items or for other reasons set forth in the Contract Documents.
C. Make submissions well in advance as the returning or rejecting of submissions or other similar circumstan-ces are possible and are deemed "avoidable delays" as defined in the General Conditions. Costs for these delays or those attributed to Contractor's tardiness in making submittals shall be borne by the Contractor.
1.05 DESTINATION OF SUBMITTALS
A. Unless otherwise specified, copies of every submission shall be sent to Engineer's home office as follows:
DuBois & King, Inc.
28 North Main Street P.O. Box 339 Randolph, Vermont 05060
ATTN: Harrison Lake National Fish Hatchery
Facsimile transmissions will not be accepted.
1.06 CLARITY OF SUBMITTALS
A. All printed materials shall be neat, clean, clear and legible, and of such quality that they can be easily reproduced by normal photocopying or blueprinting machines. Copies not conforming to this paragraph may be returned to Contractor, unreviewed.
1.07 CONTRACTOR'S APPROVAL STAMP
A. The stamp shall have the following wording: "I hereby certify that I have carefully examined the enclosed submittal(s) and have determined and verified all
126705 – Harrison Lake National Fish Hatchery 01300-4 field measurements, construction criteria, materials, catalog numbers and similar data, coordinated the submittal(s) with other submissions and the work of other trades and contractors, and that to the best of my knowledge and belief, the enclosed submittal(s) is/are in full compliance with the Contract requirements, except as follows (enter NONE if there are no exceptions):"
B. Each copy of every submittal shall be stamped with the Contractor's approved stamp.
1.08 ENGINEER'S REVIEW
A. Engineer will review and comment on each submission conforming to the requirements of this Section and shall be reflective of review comments provided by the USFWS. Engineer's review will be only for conformance with the design concept of the Project and will be confined to general arrangement and compliance with the Contract Documents only, and will not be for the purpose of checking dimensions, weights, clearances, fitting, tolerances, interferences, or coordination of trades or contractors. The acceptance of a separate item does not represent acceptance of an assembly in which the item functions. Engineer's review and comments will in no way relieve Contractor of any of his responsibilities under the Contract.
B. Submittals will be marked as follows:
1. Accepted - Submittal appears to conform to Contract Documents and Contractor may proceed with ordering and installation.
2. Accepted As Corrected - Same as "Accepted," except it is accepted on the basis that the modifications or notes added to the submittal by Engineer will be complied with by Contractor.
3. Rejected, Revise and Resubmit - Submission is not acceptable and shall be revised and resubmitted by Contractor.
4. Rejected-Unacceptable - Submission is unacceptable as it does not appear to conform to the Contract Documents. A completely new submission of other equipment or different materials is required.
126705 – Harrison Lake National Fish Hatchery 01300-5
C. No payment will be made on any item for which a submission is required if such submission:
1. has not been made,
2. has been made but was not stamped "Accepted" by Engineer,
3. has been made and stamped "Accepted As Corrected," but Contractor has not complied with Engineer's notes marked on the submittal,
4. has been made and stamped "Accepted," but item provided does not conform to the shop drawing nor to the Contract Documents.
1.09 RESUBMISSIONS
A. Prepare new and additional submissions, make required corrections, and resubmit corrected copies until accepted. On or with resubmittals, clearly describe revisions and changes made, other than the corrections requested by Engineer, which did not appear on the previous submissions.
1.10 CONTRACTOR'S RESPONSIBILITIES
A. Engineer's acceptance of submittals shall not relieve Contractor of responsibility for any deviation from the requirements of the Contract Documents unless Contractor has informed Engineer, in writing, of such deviation at the time of submission and Engineer has given written acceptance to the specific deviation, nor shall Engineer's acceptance relieve Contractor from responsibility for errors or omissions in the submittals.
B. No portion of the Work requiring a submission shall be commenced until the submission has been accepted by Engineer.
PART 2 - SUBMITTALS
2.01 SCHEDULE OF VALUES
A. Within fifteen days after the signing of the Agreement, submit to Engineer two (2) copies of a schedule of values of the various portions of the Work, including quantities aggregating the total
126705 – Harrison Lake National Fish Hatchery 01300-6
Contract Price, and supported by such data to substantiate its correctness as Engineer may require.
Each item in the schedule of values shall include its proper share of overhead and profit. This schedule, when accepted by Engineer, shall only be used as a basis for Contractor's Periodic Estimate. No payments will be made to Contractor until such Schedule has been submitted and accepted by Engineer.
B. Within fifteen days after the signing of the Agreement, submit to Engineer 2 copies of a Cashflow Schedule including estimated monthly payment schedule for the Project in accordance with the General Conditions, Article 3.3.
C. On "unit price" items, the schedule of values shall contain unit prices for various stages of work, such as restoration of surfaces broken down into paved, unpaved and other types of areas to be restored.
D. On "per each" or "lump sum" items, break prices down sufficiently to provide a convenient and realistic means for determining the amount of work done during various stages of progress.
E. Where prices are not broken down sufficiently to accurately determine the value of Work completed, Engineer will estimate the value of the Work completed and will deduct some amount so as to arrive at a conservative value which will allow Owner to easily complete the Work with the unpaid balance. When the required detail in the Schedule of Values is not provided by Contractor, Contractor agrees to accept Engineer's determinations.
2.02 CERTIFICATIONS
A. Submit in triplicate certifications of compliance whenever required by the Specifications or Engineer.
Certifications shall be complete and exact, they shall be properly authenticated by the written signature, in ink, of an owner, officer or duly authorized representative of the person, firm or organization issuing such certification, and they shall guarantee that the materials or equipment are in complete conformance with the requirements of these Specifications. Submit the "Certificate of Compliance" attached hereto, or a reasonable facsimile.
126705 – Harrison Lake National Fish Hatchery 01300-7
2.03 CONSTRUCTION SCHEDULE
A. Within fifteen days after the signing of the Agreement, submit for Engineer's and Owner's information, a construction schedule showing, in detail, the proposed sequence of the Work and the estimated date of starting and completing each stage of the Work in order to complete the Project within the Contract Time and as outlined in the Proposed Construction Sequence on Sheet 2. Prepare the schedule in a manner so that the actual progress of the Work can be recorded and compared with the expected progress. Coordinate the construction schedule with the proposed schedules of other contractors, if any, engaged in work at, or adjacent to, the Project site.
B. Coordinate the Work and make every effort to maintain the construction schedule. In the event actual progress begins to lag the schedule, promptly employ additional means or methods of construction to make up the lost time.
C. Notify Engineer in writing (1) 72 hours before commencing any work at the site, (2) 4 weeks before resuming work after a winter shutdown, and (3) at least 48 hours before resuming work in the case of a temporary suspension of work.
D. Keep the construction schedule current and revise or confirm the schedule in accordance with General Conditions to accurately reflect the conditions of the Work, past progress, and anticipated future progress.
E. Prepare and submit, with the Construction Schedule, a separate schedule listing dates for submission of major shop drawings, submittals, and material samples.
2.04 SHOP DRAWINGS
A. Submit shop drawings for all fabricated work, for all manufactured items and for all other items specifically required by the Specifications.
B. Unless otherwise specified, submit six copies of each drawing, catalog cut, procedure, or other material.
If a resubmission is not required, Engineer will retain four copies and return the remaining copies to Contractor to be distributed.
126705 – Harrison Lake National Fish Hatchery 01300-8
C. Subcontractors must submit shop drawings directly to Contractor for checking. Thoroughly check subcontractors' shop drawings for measurements, sizes of members, details, materials, and conformance with the Contract Documents. Return submittals that are found to be inaccurate or in error. Do not submit to Engineer until corrections have been made.
D. Clearly show the relation of the various parts, and, where the Work depends upon field measurements, make measurements and include them on the shop drawings before submitting to Engineer.
E. Reference all submissions to clearly indicate the Specification Section, location, service and function of each particular item. Submissions for a single item, or group of related items, shall be complete.
When submitting manufacturers' catalogs, pamphlets or other data sheets, in lieu of prepared shop drawings, specifically identify in ink the items for which acceptance is being sought.
F. If the shop drawings contain any departures from the Contract requirements, specifically describe them in Contractor's letter of transmittal. Where such departures require revisions to layouts or structural changes to the Work as shown, Contractor shall, at his own expense, prepare and submit revised layout and structural drawings. Make drawings the same size as the Contract Drawings.
2.05 SAMPLES
A. Where required, submit sample or test specimens of materials to be used or offered for use. Samples shall be representative, in all respects, of the material offered or intended, shall be supplied in such quantities and sizes as may be required for proper examination and tests, and shall be delivered to Engineer, prepaid, along with identification as to their sources and types or grades. Submit samples well in advance of anticipated use to permit the making of tests or examinations.
B. Samples will be checked with reasonable promptness only for conformance with the design and for compliance with the information given in the Contract Documents.
126705 – Harrison Lake National Fish Hatchery 01300-9
C. The Work shall be in accordance with the accepted sample. The use of materials or equipment for which samples are required to be submitted for acceptance is not permitted until such acceptance has been given by Engineer.
2.06 SPARE PARTS
A. For each item, provide a list of parts and supplies that are normally furnished at no extra cost or are specified to be furnished under this Contract, and a separate list of additional items which manufacturer recommends having "on hand" in order to insure efficient and proper operation for the first year of service.
2.07 INSTALLATION - APPLICATION INSTRUCTIONS
A. In addition to the installation instructions required, submit copies of all manufacturers' application instructions and turn over, to the Resident Project Representative, all printed instructions and labels that are attached to or shipped with equipment and materials. These documents are, in many cases, valuable to Owner in his operation and maintenance program.
2.08 MANUFACTURER'S SERVICE STATIONS
A. The product of a manufacturer who does not maintain an adequate service station and a sufficient stock of spare parts in a reasonable vicinity of the Project, is subject to rejection by Engineer solely on that basis. With each submission, submit information on manufacturer's facilities and give complete details of their service policies and capabilities, and a general idea of the stock of spare parts available.
2.09 TEST RESULTS AND INSTALLATION
A. Whenever tests are required on materials and equipment, such tests shall be performed and two (2) copies of the test results submitted to Engineer. Do not deliver to the Project or incorporate into the Work any materials or equipment for which Engineer has not issued a written acceptance of the required tests and test results.
126705 – Harrison Lake National Fish Hatchery 01410-1
SECTION 01410 - TESTING AND LABORATORY SERVICES
PART 1 - GENERAL
1.01 DESCRIPTION
A. This Section covers the requirements for utilizing the services of an approved independent testing laboratory to perform tests and inspections to determine compli-ance with these Specifications.
B. Sampling and testing methods and procedures can also be found in the following Sections:
Soil Compaction 02250 Cast-in-Place Concrete 03300
1.02 QUALITY ASSURANCE
A. In order to establish compliance with the Contract Documents, materials shall be thoroughly and completely tested, examined and evaluated before they are incorporated into the Work. During and after installations, additional tests, examinations, and evaluations shall be made to determine continued compliance throughout the course of the Work.
B. Testing laboratory shall be a reputable, experienced and independent firm which is capable of performing all of the required testing and a firm that is regularly engaged as a testing laboratory. Contractor shall be responsible for retaining the testing laboratory and paying all cost of testing.
C. Perform all sampling and testing in strict accordance with specified procedures and use the materials, in-struments, apparatus, and equipment required by the codes, regulations and standards. Where specific testing requirements or procedures are not described, perform the testing in accordance with all pertinent codes and regulations and with recognized standards for testing.
D. In the event that samples and test specimens are not properly taken, handled, stored or delivered, or if other requirements of this Section are not complied with, Engineer reserves the right to delegate any or
126705 – Harrison Lake National Fish Hatchery 01410-2 all of this work to others, or to take whatever action he deems necessary to ensure that sampling and testing are properly accomplished, for which all costs shall be the responsibility of the Contractor.
E. Engineer further reserves the right to disallow the use of a specific testing laboratory, even after prior acceptance if the laboratory fails to meet or comply with the requirements of this Section. If this should occur, immediately dispose of the testing laboratory's services and retain the services of a different labo-ratory acceptable to Engineer.
1.03 SUBMITTALS
A. See Section 01300.
B. Within five (5) days after Notice to Proceed, submit brochures or other documentation from a qualified laboratory, clearly indicating experience, location, qualifications of staff, available equipment and facilities, standard fees, other pertinent informa-tion, and descriptions of any limitations or restric-tions. Based upon this material, Engineer will authorize or reject the use of the proposed testing laboratory. In the case of rejection, Contractor shall submit brochures or other documentation of a second firm for review.
C. Certified copies of each test result. Mail copies directly from the laboratory to Engineer, at both his field office and his home office. Contractor shall make arrangements with the laboratory to secure his own copies.
1.04 DELIVERY, STORAGE AND HANDLING
A. Extreme care shall be exercised in the taking, storage, handling and delivery of samples and test specimens to avoid breakage, damage and disturbance.
B. Provide all required storage facilities.
C. Carefully deliver all samples and test specimens to the laboratory.
126705 – Harrison Lake National Fish Hatchery 01410-3
1.05 SCHEDULING
A. Except where otherwise specified, Engineer will deter-mine the number of samples to be taken, the date and time samples will be taken and tests made, the number and type of tests to be performed, who will collect the samples, how they will be handled and stored, and when laboratory personnel are required on site.
B. Engineer will notify Contractor of his decision to take samples and/or have tests made and provide him with the pertinent information. Contractor is responsible for notifying the testing laboratory and for having the testing performed, on schedule.
C. In addition to the above, Contractor shall make his own arrangements for the sampling and testing of materials he/she proposes to incorporate into the Work.
D. Notify Engineer at least 24 hours in advance of the times at which scheduled samples or tests will be conducted.
E. If samples and/or tests cannot be taken or performed when required, delay the Work until such time that they can be accomplished. Where possible, any work which has been installed but has not been sampled or tested as required, shall be tested by other means.
Upon Engineer's request, uncover any work that has been buried or covered and perform special tests designated by Engineer. If the work cannot be tested by other means, Engineer may declare the work unacceptable. All costs associated with noncompliance and for special testing shall be the responsibility of the Contractor.
F. Should the testing laboratory be scheduled to take or collect samples or to perform tests, and finds that it is unable to do so as result of delays in construction, inclement weather, or any other reason, reschedule the tasks for a date acceptable to Engineer.
G. Plan all work and operations to allow for the taking and collection of samples and allow adequate time for the performance of tests. Delay the progress of ques-tionable work until the receipt of the certified test reports.
126705 – Harrison Lake National Fish Hatchery 01410-4
PART 2 - PRODUCTS
2.01 TESTING LABORATORY
The testing laboratory shall meet the following criteria:
A. Be capable of performing all of the required tests.
B. Be regularly engaged in performing the types of services required, and be independent from the contractor.
C. Have adequate facilities, materials, equipment and personnel to perform the services.
D. Have an adequately trained, experienced, and qualified staff.
E. Have at least one registered professional engineer who shall be capable of performing field tests, super-vising laboratory testing, and who can interpret test results. The professional engineer shall be thoroughly knowledgeable in materials, soils, bituminous paving and concrete.
F. Must be able to be on the Project site within four (4) hours after being notified to come.
2.02 TEST REPORTS
A. Each report shall be in writing and shall include the testing method used, the test results, the specified results, the exact location of where the test specimens were taken, the date taken, Project identification, Contractor's name, and other pertinent information required for a complete and meaningful test report.
B. Each report shall be signed and certified by a respon-sible officer of the testing agency.
C. Mail reports directly to Engineer within 24 hours after the sample is taken, except in those instances where tests cannot be immediately performed because of required curing or incubation periods, or lengthy testing procedures.
126705 – Harrison Lake National Fish Hatchery 01410-5
D. The laboratory shall verbally communicate test results to Engineer, when he/she requests same. This does not eliminate nor replace the requirements for a written report.
PART 3 - EXECUTION
3.01 CONTRACTOR COOPERATION WITH TESTING LABORATORY
A. The Contractor shall coordinate, schedule and bear all costs associated with testing as designated in other Sections. Costs for testing services shall be considered subsidiary to relevant payment items.
B. Allow representatives of the testing laboratory access to the Work at all times.
C. Provide all equipment, labor, materials and facilities required by the laboratory to properly perform its functions.
D. Cooperate with and assist laboratory personnel during the performance of their work.
3.02 TEST SPECIMENS AND SAMPLES
A. Test specimens and samples shall be taken by the per-son(s) designated in other Sections, or as directed by Engineer. Do field sampling and testing in the pres-ence of Engineer.
B. Provide all materials, equipment, facilities and labor for securing samples and test specimens and for per-forming all field testing.
126705 – Harrison Lake National Fish Hatchery 01575-1
SECTION 01575 - TEMPORARY EROSION PREVENTION AND
SEDIMENTATION CONTROL
PART 1 – GENERAL
1.01 DESCRIPTION
A. Work covered by this Section includes the installation, maintenance and removal of temporary erosion prevention and sediment control devices.
B. Related work specified elsewhere includes:
Clearing and Grubbing 02100 Excavating, Trenching and Backfilling 02221 Soil Compaction 02250 Dewatering 02401 Topsoil and Seeding 02483
C. Additional requirements of this Section include:
1. Prevention of erosion due to construction activities.
2. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.
3. Restoration of areas eroded due to insufficient preventive measures.
4. Compensation of Owner for fines levied by authorities having jurisdiction due to non-compliance by Contractor.
1.02 PERFORMANCE REQUIREMENTS
A. The Contractor shall comply with the requirements of Virginia DEQ regulations and as required in the Plans.
B. Develop and follow an Erosion Prevention and Sedimentation Control Plan consistent with the plan, details, and notes provided on the engineering drawings. Contractor shall submit periodic inspection reports to the Engineer.
C. Do not begin clearing, grading, or other work involving disturbance of ground surface cover until applicable permits have been obtained; furnish all
126705 – Harrison Lake National Fish Hatchery 01575-2 documentation required to obtain applicable permits.
1. Owner will obtain permits and pay for securities required by authority having jurisdiction.
2. Owner will withhold payment to Contractor equivalent to all fines resulting from non-compliance with applicable regulations.
D. Timing: Put preventive measures in place as identified on the Plans, or, if not identified, soon as possible after disturbance of surface cover and before precipitation occurs.
E. Storm Water Runoff: Control all increased storm water runoff due to disturbance of surface cover due to construction activities for this project.
F. Erosion On Site: Minimize wind, water, and vehicular erosion of soil on project site due to construction activities for this project.
1. Control movement of sediment and soil from temporary stockpiles of soil.
2. Prevent development of ruts due to equipment and vehicular traffic.
3. If erosion occurs due to non-compliance with these requirements, restore eroded areas at no cost to Owner.
G. Sedimentation of Waterways On Site: Prevent sedimentation of waterways on the project site, including rivers, streams, lakes, ponds, open drainage ways, storm sewers, and sanitary sewers.
1. If sedimentation occurs, install or correct preventive measures immediately at no cost to Owner; remove deposited sediments; comply with requirements of authorities having jurisdiction.
2. If sediment basins are used as temporary preventive measures, pump dry and remove deposited sediment after each storm.
H. Maintenance: Maintain temporary preventive measures until permanent measures have been established.
126705 – Harrison Lake National Fish Hatchery 01575-3
1.04 SUBMITTALS
A. See Section 01300 - Administrative Requirements, for submittal procedures.
B. Erosion Prevention and Sedimentation Control (EPSC) Plan:
1. Include:
a. Site plan showing grading; new improvements;
temporary roads, traffic accesses, and other temporary construction; and proposed preventive measures.
b. Schedule of temporary preventive measures, in relation to ground disturbing activities.
2. Obtain the approval of the Plan by authorities having jurisdiction.
3. Obtain the approval of the Plan by Owner.
C. Certificate: Mill certificate for silt fence fabric attesting that fabric and factory seams comply with specified requirements signed by legally authorized official of manufacturer; indicate actual minimum average roll values; identify fabric by roll identification numbers.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Mulch: Use one of the following:
1. Straw or hay. Other mulch materials, such as wood chips or shavings, wood fiber cellulose or compost may be used if approved in advance by the Engineer. Anchor straw / hay mulch with peg and twine or other, approved equivalent anchoring method.
B. Grass Seed for Temporary Cover: Select a Ryegrass (Empire / Pardee variety) or a winter Ryegrass, depending on planting season and intended purpose. If same area will later be planted with permanent vegetation, do not use species known to be excessively competitive or prone to volunteer in subsequent
126705 – Harrison Lake National Fish Hatchery 01575-4 seasons.
C. Temporary Rolled Erosion Control (RECP) Products (also noted as “Erosion Control matting”)
1. Temporary rolled erosion control (RECP) products shall consist of mesh or woven biodegradable natural fiber netting. Only woven and interlocked products are allowed for use. RECP products having chemically-bound joints in supporting mesh are not allowed and shall not be used.
2. Mulch Control Nets shall have mesh or woven biodegradable natural fiber netting.
3. Netless Rolled Erosion Control Blankets shall have natural fibers mechanically interlocked together to form the RECP.
4. Single-net or Double-net erosion control blankets shall have processed biodegradable natural fibers mechanically bound together by a natural fiber netting of processed natural yarn or twines woven into a continuous matrix.
D. Silt Fence Fabric: Polypropylene geotextile resistant to common soil chemicals, mildew, and insects; non-biodegradable; in longest lengths possible; fabric including seams with the following minimum average roll lengths: Woven wire fabric (min. 14-1/2-gauge w/max. 6” mesh spacing) shall be used in conjunction with the silt fence.
1. Equivalent Opening Size: 40-80 U.S. Std. Sieve, maximum, when tested in accordance with ASTM D 4751.
2. Slurry Flow Rate: 0.30 gal/min/sf.
3. Ultraviolet Radiation Stability: 90 when tested in accordance with ASTM G-26
4. Puncture Strength (lbs) 40 when tested in accordance with ASTM D751 (modified).
5. Elongation at Failure (%): 50 percent minimum, when tested in accordance with ASTM D1682.
126705 – Harrison Lake National Fish Hatchery 01575-5
6. Grab Tensile Strength: 90 lb, minimum, when tested in accordance with ASTM D1682.
E. Silt Fence Posts: One of the following, minimum 3 feet long:
1. Steel U- or T-section, with minimum mass of 1.33 lb per linear foot.
2. Hardwood, sound quality, 2 by 2 inches in cross-section.
F. Other Erosion Control Measures:
1. Other erosion control measures are identified on and required as shown on the engineering drawings. Contractor shall notify the engineer immediately of any conflicts.
PART 3 - EXECUTION
3.01 EXAMINATION
A. Examine site and identify existing features that contribute to erosion prevention; maintain such existing features to greatest extent possible.
3.02 PREPARATION
A. Schedule work so that soil surfaces are left exposed for the minimum amount of time as identified on the Drawings.
3.03 SCOPE OF PREVENTIVE MEASURES
A. In all cases, if permanent erosion prevention measures have been installed temporary preventive measures are not required.
B. Linear Sediment Barriers: Made of silt fences.
1. Provide linear sediment barriers:
a. Along downhill perimeter edge of disturbed areas, including soil stockpiles.
b. Along the toe of cut slopes and fill slopes.
2. Space sediment barriers with the following maximum slope length upslope from barrier:
a. 1V:2H, 25-ft:
b. 1V:3H, 50-ft
126705 – Harrison Lake National Fish Hatchery 01575-6
c. 1V:4H, 75-ft
d. 1V:5H, or flatter 100-ft
C. Soil Stockpiles: Protect using one of the following measures:
1. Cover with polyethylene film, secured by placing soil on outer edges.
2. Cover with mulch at least 4 inches’ thickness of pine needles, sawdust, bark, wood chips, or shredded leaves, or 6 inches of straw or hay.
D. Mulching: Use only for areas that may be subjected to erosion for less than 6 months.
E. Temporary Seeding: Use where temporary vegetated cover is required.
3.04 INSTALLATION
A. Silt Fences: