Attachment 1 SOW Site Prep.pdf
PDF 227 KB Posted
- Attached to
- GMUG NF Mechanical Site Prep Federal contract opportunity
- Solicitation number
- 1240LQ24Q0088
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity related to timber site preparation work on the Grand Mesa, Uncompahgre, and Gunnison National Forests. The SOW details the required mechanical site preparation services across three locations - Big Creek, Long Slough, and Crane - including the rehabilitation of burned slash pile ash pits, reworking of landing slash piles, road opening/clearing, road slashing, and other minor "finesse" work. Specifications are provided for the equipment requirements, work progression, protection of improvements and resources, equipment cleaning, transportation, and personal protective equipment. The contract has an estimated performance period of 21 consecutive days. The related federal contract opportunity has Solicitation Number 1240LQ24Q0088, is a total small business set-aside, and is being procured by the Department of Agriculture Forest Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 2 Map of CraneLongSloughBigCreek.pdf | ||
| Attachment 6 Wage Determination 15-5423.txt | TXT text file | |
| Solicitation for Site Prep Commercial Services_Combined SS RFQ.pdf | ||
| Attachment 4 Long Slough Pile Rehab.pdf | ||
| Attachment 5 Crane_PileRehab.pdf | ||
| Attachment 3 Big Creek Pile Rehab.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1240LQ24Q0088
GMUG NF Timber Site Prep
Statement of Work The solicitation is for crawler tractor work on the Grand Valley Ranger District of the Grand Mesa, Uncompahgre, and Gunnison National Forests. The Contractor shall furnish all labor, equipment, supervision, transportation, supplies, and incidentals to perform all work necessary on the areas specified in the contract.
All aspects of the work program shall be performed in an organized, systematic manner to ensure services are performed over the entire project areas.
Count and location of ash pits was by determined from field reconnaissance and GPS waypoints, cross checked against aerial photographic imagery taken in 2023. Not all slash piles may have been burned in 2023.
No forest products shall be removed from the project area.
This contract is a Performance Based, firm-fixed price contract.
The performance period will be Twenty-one (21) consecutive days.
Location, Access, and Description of Units
Site Preparation – The contracted work will be in three (3) locations on the Grand Valley Ranger District.
Big Creek Site Preparation
The Big Creek Timber Sale area is approximately eight (8) air miles southeast of Collbran, Colorado. It is located on the Grand Valley Ranger District, Grand Mesa National Forest. The legal description is: T. 10 S., R. 94 W. Section 33 and 34; T. 11 S., R. 94 W., Sections 2, 3, 4, 10 & 11, 6th Principle meridian, Delta County, Colorado. The sum acreage of the cutting units is approximately three hundred and nine (309) acres in a gross sale area of one thousand two hundred and thirty-one (1,231) acres.
From Grand Junction, Colorado head east on Interstate 70 for approximately nineteen (19) miles.
Turn onto State Highway 65 N and continue for approximately ten (10) miles. Turn left on State Highway 330 E and continue for approximately eleven (11) miles. Turn right onto County Road 58 ½ and continue for approximately two (2) miles. Turn left onto county road KE for approximately half (½) a mile before county road KE turns right and becomes county road 59.
Continue on county road 59 for approximately four and a half (4 ½) miles, where county road 59 becomes NFSR 121 at National Forest Boundary and continue for approximately four (4) miles.
Turn left onto NFSR 260 and continue for approximately one (1) mile to access the Big Creek timber sale area. Lowboy load/unload locations on the map in Exhibit 1 are suggestions only.
Long Slough Site Preparation
The Long Slough Timber Sale is located approximately seven and two tenths (7.2) air miles northwest of the Grand Mesa Visitor Center and approximately twenty-five (25) air miles east of Grand Junction, Colorado. The legal location is: T. 11 S., R. 95 W., Sections 19, 29, 30, 31 & 32;
6th Principle Meridian, Mesa County, Colorado. The sum acreage of the cutting units is approximately two hundred fifty-three (253) acres.
From Grand Junction, Colorado head east on Interstate 70 for approximately nineteen (19) miles.
Turn onto Highway 65 N and continue for approximately twenty-five (25) miles. The Long Slough timber sale area can be accessed from NFSR 254 and NFSR 250. Lowboy load/unload locations on the map in Exhibit 1 are suggestions only.
Crane Site Preparation
The Crane Timber Sale is located approximately eight and one-half (8 ½) miles southwest of the Grand Mesa Visitor Center and approximately forty-five (45) air miles southeast of Grand Junction, Colorado and sixteen (16) air miles north of Delta, Colorado. The legal location is: T.
12 S., R. 96 W., Sections 22, 23, 26, 27, 34 & 35, 6th Principle Meridian Mesa County, Colorado. The sum acreage of the cutting units is approximately four hundred ninety-two (492) acres in a gross sale area of one thousand four hundred ninety-nine (1499) acres.
From Grand Junction, Colorado head east on Interstate 70 for approximately nineteen (19) miles.
Turn onto Highway 65 N and continue for approximately thirty (30) miles. Turn right onto NFSR 100 and continue approximately one and three-tenths (1.3) miles. Turn left onto NFSR 109 and continue approximately three (3) miles to the Crane timber sale area. Lowboy load/unload locations on the map in Exhibit 1 are suggestions only.
Slash Pile Ash Pits and Landings To Be Completed By Treatment Unit
Sale Name Big Creek Long Slough Crane Unit 1 1 10 8 Unit 2 2 N/A 4 Unit 3 3 N/A 2 Unit 4 2 N/A 1 Unit 5 2 N/A 13 Unit 6 5 N/A 0 Unit 7 2 N/A 7 Unit 8 4 N/A 0 Unit 9 3 N/A 2 Unit 10 1 17 2 Unit 11 3 15 N/A
Total 28 42 39
Specifications or Tactics Planned for Use in the Site Preparation Contract
Specification or Tactic Planned for Use?
Schedule Item(s)
Rehabilitation of Burned Slash Pile Ash Pits Yes 1,2 & 3 Reworking Landing Slash Piles Yes 1,2 & 3 Road Opening/Clearing Yes 1,2 & 3 Road Slashing Yes 1,2 & 3 Other Minor “Finesse” Work Yes Option
Line
Definition of Terms These definitions are given for clarification. Addition definitions and method descriptions are located in the Technical Requirements section.
Ash Pits – The footprint and area surrounding burned slash piles which includes ash, partially burned log ends, and shoulders of unburned or partially burned woody debris, and surrounding woody debris mats. The ash pit itself is usually a depression in the ground.
Slash - All existing woody debris, including but not limited to cull logs, chunks, branches, tops, stumps from push-outs or windthrows, and broken understory trees or brush resulting from natural accumulation, timber felling, logging, thinning, and clearing. Trees severely damaged by the Contractor shall be treated as slash. Tree stumps imbedded naturally in the soil are not considered slash.
Heavy Slash Concentrations - Areas where accumulated larger-diameter slash results in piles or windrows which equal or exceed the following dimensions: average depth of two (2) feet and cover a ground surface of one hundred (100) square feet.
Slash Mats – Areas of deep, compacted, organic material generated during timber harvest operations. Slash mats include cull logs, tops, branches, bark, foliage, and other finely ground organic material, mixed with soil. Untreated slash mats are not suitable seed beds for trees and are not practical to plant trees in.
Slash Piling - The concentrating and compacting of excess amounts of woody debris and slash such that piles may be consumed by burning. Piles must be reasonably dirt-free, compacted, and piled sufficiently tight to facilitate complete burning. Piles in some areas may be left unburned to provide habitat for wildlife.
Road Closure – Treatment to roadways to make them unusable by motorized or mechanized traffic. The roadbed is capable of vegetation production. Drainage is adequate to minimize soil erosion and sedimentation.
Road Obliteration – Treatment to roadbeds to make them no longer strongly evidence as a travel way, and capable of natural vegetation production. The road prism is usually recontoured back to natural slope.
General Specifications Government-Furnished Property
There is no Government-furnished property for this project.
Other Government-Furnished Services
Erosion control seed and seed application will be provided by the Government.
Personnel Qualifications
All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require the Contractor to replace any employee whom the Contracting Officer determines to be incompetent, careless or otherwise objectionable.
Progression of Work
Contractor shall perform the work in a progressive, orderly manner. All road closure, site preparation, brush piling and/or crushing work on one unit shall be completed before work is started on another unit, unless wet ground conditions halts work, or if more than one piece of equipment is on the job.
Past experience in this type of site preparation and road closure work has provided insight into the expected production rates (varying some for terrain, ground condition, and needed treatments). Failure to meet expected production rates could be cause for the Contracting Officer to direct the replacement of operators or pieces of equipment, changes in methodologies, or stopping work on the contract.
Protection of Improvements and Resources
The Contractor will protect all structural improvements such as cattle guards, gates, fences, ponds, ditches, signs, and roads. The Contractor will restore any improvements damaged by the operation in a timely fashion. Improvements will be restored to pre-operation condition at the expense of the Contractor. Equipment will not cross meadows, live streams, springs, primary roads, or any other non-work areas except as designated by the Contracting Officers Representative. Movement of equipment between work areas will only be allowed on open designated roads. Cross country travel is not allowed to prevent establishment of new OHV routes.
Road Damage
Vehicles shall not be operated on roads in the contract area if ground or weather conditions during operation causes lateral displacement or flowing of soil and deep rutting. Such conditions usually develop where frozen ground is thawing, when snow is melting, and during or immediately following rainstorms.
Use Of Roads By The Contractor
In addition to wet weather operating restrictions, it is the intent of this contract that the work be performed with the present system of existing roads. An existing road is one with a distinguishable roadbed that permits vehicle travel without major improvements to the road.
Distinguishable roadbeds that are now reforested (have at least three hundred (300) stems/acres) with trees at least three (3) feet tall, or that would require major earth work to permit vehicle travel are not considered existing roads for the purpose of this contract. Limited improvement of existing roads is permitted to allow for safe vehicle access (e.g., filling or smoothing ruts, removing roadside trees or obstacles, and removing trees less than three (3) feet tall or obstacles from the roadbed).
Upon written approval of the Forest Service, the Contractor may open closed roads to access a work area. Any closed roads opened by the Contractor will be returned to the closed condition in which it was found (e.g., replacing rocks, stumps or logs/slash previously scattered on the roadbed and restoring drainage or barrier structures removed or altered to permit vehicle travel).
Where seasonal road closure gates are closed to limit public motorized traffic during spring snow melt, the Contractor will be required to close and lock the gate after passing through.
Cleaning Of Equipment
In order to reduce the spread of noxious weeds to the project area and other public lands, crawler tractors and other equipment will be cleaned by the Contractor prior to moving the equipment onto public lands and the project area. Equipment will be cleaned of mud, dirt, and accumulations of organic material which may harbor seed or plant parts of noxious weeds.
Steam cleaning is an acceptable method of reducing the import of noxious weeds. Belly pans must be cleaned prior moving in. Fluid leaks shall be repaired prior to moving onto site.
Transportation of Equipment
Equipment must be moved between work sites in such a manner as not to damage permanent road surfaces. A lowboy trailer is considered an acceptable method. Any other method must be approved in writing by the Contracting Officer. Maximum gross vehicle weight and vehicle width allowed is 82,500 lbs. and 10 feet. Equipment on a trailer may be wider but will need to be flagged and placarded with “Over Size Load” signs per State laws. The minimum road or bridge width to be encountered on this project is twelve feet six inches. The Contractor is responsible for transporting Government furnished property or Contractor furnished property to, between, and from all work sites.
The Contractor is responsible for obtaining all necessary permits, licenses, etc., for operating and transporting equipment.
Leave Trees
In cutting units, all live trees shall be left standing to the maximum extent possible. Standing dead true fir and aspen (live or dead) eight (8) inches DBH and larger and standing dead Engelmann spruce ten (10) inches DBH and larger, will be protected.
Slash Disposal
Slash resulting from work on this contract shall be removed from streams, drainages, power lines, telephone rights-of-way, private land, and from within ten (10) feet of property corners.
Slash may be left in roadways which are to be closed. Slash falling upon cut and fill slopes along permanent open roads in the work area shall be removed from cut and fill slopes and scattered into the units in a manner so as to not form piles or windrows. Remaining slash shall be treated to lie within eighteen (18) inches of the ground.
Personal Protective Equipment
The contractor shall train workers in the safe operation and use of equipment that the worker may use before the worker begins using such equipment.
Personal protective equipment (PPE) including hard hats, eye protection, hearing protection, dust masks, gloves, and sturdy work boots should be worn during equipment operations. Personal protective equipment shall be maintained in a sanitary and reliable condition. Defective or damaged personal protective equipment shall not be used.
In any area where the worker is exposed to the potential for flying or falling objects, the contractor shall provide a hard hat, at no cost to the employee, and the contractor shall assure that the employee wears the hard hat. The hard hat must meet the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.
The contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.
The contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise for example, chainsaw operation.
Dust or particle masks should be worn during ash pit rehabilitation operations to minimize the inhalation of wood ash.
Refer to Occupational Safety and Health Administration (OSHA) regulations at 29 CFR 1910.266(d) Logging Operations and 29 CFR 1910 Subpart I (1910.132, 133, 135, 136, and 138).
Camping Permits
Work camp locations will be approved in advance by the Contracting Officers Representative with a District Ranger approved camping permit. Contractors will be required to maintain the camp site in clean, orderly, sanitary condition. Leakage of fuel and oil will be cleaned up and disposed of.
Technical Requirements Equipment Specifications
Past experience has shown that a D-4 to D-5 class dozer is effective for completing the required work. Other types of heavy equipment maybe substituted for the requested type after approval by the Contracting Officer. As a minimum, other types of heavy equipment must meet the standards outlined below for crawler tractors.
Crawler Tractors
Crawler tractors must be equipped with operable Forest Service approved spark arrestor or turbo charger. As a minimum, the tractor(s) shall be equipped with an open canopy, roll-over protective structure (ROPS), logging type, including brush deflector, overhead canopy and rear screen in accordance with SAEJ-395. The tractor will also be equipped with an operable standard brush rake and track grousers (minimum of two inches high). Experience has shown that crawler tractors should be equipped with belly pan and track guards.
Engine size may range from ninety to one hundred twenty (90 to 120) net engine H.P.
Equipment smaller than ninety (90) H.P. may not be powerful enough to complete work in a timely fashion or be able to move through stands without getting hung-up. Lighter equipment may not be able to crush woody debris or be able to pile slash as required (push and lift slash).
Smaller equipment is generally more maneuverable between stumps and residual trees.
Experience has shown that a crawler tractor in the Caterpillar D-4 to D-5 size class (or equivalent size in other manufacturer lines) works best in this type operation.
The crawler tractor must be equipped with a brush rake – clearing blade (with teeth) or brush rake. Heavy duty rock rakes with top guards to permit high piling are satisfactory. Tooth spacing shall be a maximum of eighteen (18) inches and a minimum of twelve (12) inches between teeth. This tooth spacing is necessary to allow debris, rocks, pine cones, and dirt to filter through and not be pushed into the piles.
The dozer must be equipped with rear mounted, hydraulically lifted ripping teeth.
Other Equipment Required
a. Spark arrestor or turbo charger meeting either (I) USDA - Forest Service Standard 5100-1a: or (II) the eighty (80) efficiency level determined according to the appropriate Society of Automotive Engineers (SAE) recommended practices J335 and J350.
b. Fire Extinguishers and Tools on Equipment - while in use, each internal combustion engine including tractors, trucks, yarders, loaders, welder, stationary engines, or comparable heavy equipment shall be provided with at least the following:
One chemical fire extinguisher meeting one of the following specifications:
1. Two and one-half (2.5) pound or larger size of the dry chemical type, minimum ten (10): BC rating.
2. Five (5) pound or larger size of the carbon dioxide type, minimum ten (10): BC rating.
One (1) shovel, sharp, size zero (0) or larger, round-pointed with the handle at least thirty-six (36) inches long.
One axe, sharp, double-bit three and one half pounds (3-1/2lbs), or one (1) sharp Pulaski.
Extinguishers, shovels and axes shall be mounted so as to be readily available from the ground.
All tools shall be maintained in a serviceable condition.
c. Hobbs Meter.
d. Fluid Leaks – the equipment shall be free of leaking hydraulic fluid or oils. Minor leakage of fluid within normal limits may be accepted by the Contracting Officers Representative. When leakage becomes severe, the Contractor will stop operations and repair the leak. Severe leakage is where fluid reaches the ground, creating pools or stained soil. The Contractor will be responsible for cleaning up and removing fluid spills.
Work Specifications
For the rehabilitation of burned slash pile ash pits, the treatment area is the ash pit footprint, and the area surrounding the ash pit covered by compacted woody debris (slash mats) and logging slash. The treatment of the surrounding area may extend thirty (30) to one hundred (100) feet out from the ash pit.
The outer boundaries of the cutting units are marked in orange tree marking paint.
Georeferenced PDF versions of unit maps are available upon request for operations.
The specific type of treatment in a cutting unit or along a road segment will be determined by the Contracting Officers Representative based on site-specific conditions. More than one (1) treatment method may be used in a single cutting unit or along a single road segment as site conditions dictate. Due to adverse ground conditions and desirable regeneration, some areas for non-treatment will be designated by the Contracting Officers Representative.
Not all of the different treatment sections below will be utilized during this contract. They are included to describe scenarios where a different tactic maybe employed to gain the desired result. The variety of tactics are included so that where additional “finesse” type work is encountered, the matching treatment tactic can be utilized.
Methods of Site Preparation for Reforestation and Fuels Treatment
Machine Site Preparation for Tree Planting
This is a treatment where spots of bare soil are created which will be free of competing vegetation, and suitable for hand planting of tree seedlings. The hand planting may be by planting tools such as the “hoedad”, planting tool, shovel, or powered auger. Trees are planted at a spacing of six (6) to fourteen (14) feet depending on the availability of good planting spots with acceptable microsites, tree species, aspect and slope of the ground.
Mechanized treatment will be necessary in areas covered by deep, dense sod, sedge, grass, and forb cover, or areas covered by slash mats and logging slash. Planting spots will need to be at least eighteen (18) to twenty-four (24) inches across. Planting spots will need to be spaced out at six (6) to twelve (12) foot intervals. Potential planting spots occupied by living tree seedlings and saplings do not need to be treated. Where the soil and vegetation has been well disturbed during timber harvest operations, and planting spots are available, site preparation is not necessary.
In areas where slash mats are present, the organic material will be spread out and spots of mineral soil exposed for reforestation requirements. Some mounding of organic material is acceptable when necessary to expose mineral soil. Do not allow organic material from slash mats to be incorporated into slash piles to be burned. Where slash mats are adjacent to roads to be closed, the fine organic material can be spread across the road. The roadbed should be ripped prior or during slash mat spread to reduce soil compaction in the roadbed and help work fine organic material into the soil. Be wary of short logs and high stumps hidden in the slash mat.
Planting beds for seedlings may be created by disturbing the soil surface by turning on the tracks, ripping the soil with the brush rake or rippers, digging and scalping with the blade, by rocking/dipping the blade, by digging or dragging as excavator bucket across the ground, or by moving woody debris across the ground.
Machine Scarification of Seedbeds for Natural Regeneration
For most conifer tree species, bare mineral soil is necessary for natural tree seed to land on in order for consistent, adequate seed germination and seedling establishment. Scarification is the process by which mineral soil is exposed and disturbed (but not displaced) by mechanical means to create an acceptable seed bed for trees. Soil is disturbed by turning on the tracks, ripping the soil with the brush rake teeth or rippers, by digging or dragging an excavator bucket across the ground, by rocking/dipping the blade, or by moving woody debris across the ground.
In areas of treatment units unoccupied by desired trees, it is desired that a minimum of forty (40) percent of the ground be in exposed and disturbed mineral soil seedbeds. Where slope exceeds thirty (30) percent and scarification is directed, the area to be treated is twenty-five (25) percent of the ground surface. Soil is to be disturbed, but not displaced. The scarification is to be scattered across the entire treatment area. Where desired trees are close together, do not treat those areas. Do not scarify the soil under the drip line of the crowns of desired overstory trees (usually within ten (10) feet of overstory tree boles) to avoid damage to root systems.
At the discretion of the Contracting Officers Representative, treatment of specific steep areas will not be conducted to protect resources. Areas with considerable surface rock which are not conducive to machine scarification, and areas which were sufficiently scarified during logging, will be identified by the Forest Service for non-treatment.
In partial cut stands, most of the residual trees are desired for retention. Protect advanced regeneration and desired trees but do grub out or machine trample cull trees. Areas of desirable dense seedlings and saplings will be identified by the Contracting Officers Representative to be avoided. In general, lodgepole pine, Douglas-fir, spruce, fir, and aspen trees should be protected.
In areas where slash mats are present, the organic material will be spread out and spots of mineral soil exposed for reforestation requirements. Some mounding of organic material is acceptable when necessary to expose mineral soil. Do not allow organic material from slash mats to be incorporated into slash piles to be burned. Where slash mats are adjacent to roads to be closed, the fine organic material can be spread across the road. The roadbed should be ripped prior or during slash mat spread to reduce soil compaction in the roadbed and help work fine organic material into the soil. Be wary of short logs and high stumps hidden in the slash mat.
Where roads are identified for closure under this contract, logs and slash mat material may be scattered across the roadway to aid in closure.
Rehabilitation of Burned Slash Pile Ash Pits
In areas where slash piles have been burned in recent years, ash pits exist which will not naturally vegetate for a prolonged period of time. These untreated ash pits do tend to be preferred by several species of undesirable noxious weeds to become established in an area. The ripping and mixing of the ash pit is intended to break-up and mix heat sterilized soil such that desirable vegetation will become established. The established desirable vegetation will deter noxious weed establishment.
For the rehabilitation of burned slash pile ash pits, the treatment area is the ash pit footprint, and the area surrounding the ash pit covered by compacted woody debris (slash mats) and logging slash. The treatment of the surrounding area may extend thirty (30) to one hundred (100) feet out from the ash pit.
The Contractor will rip the charcoal bed and soil below, break up surrounding woody debris slash mats, stir and mix the ash, soil, and woody debris, smooth out humps and piles of dirt and ash, scatter remaining logs and poorly burned log ends across the burned area, and scatter/crush remaining fuels in the area.
Reworking Landing Slash Piles
Landing slash piles which have been ignited, but burned poorly, or did not ignite at all will benefit from being reworked or re-piled. Some slash piles and cull log decks were not well compacted during timber harvest operations. These cull log decks are to be burned to reduce the volume of woody debris in the area. There are uneven log ends on the cull log decks which will not burn well and will become burned log ends or chunks.
The Contractor will pile the cull logs into or onto landing slash piles with the heavy equipment.
Slash piles will be compacted and pushed up to improve consumption of the debris. The Forest Service may provide chainsaw support to break-up the length of cull logs to facilitate piling.
Logging slash piles commonly have a deep slash mat apron around the pile. Fine organic material in slash piles will smolder for a prolonged period of time, which could create air pollution issues later on. Woody debris in slash mats has been observed to smolder and “charcoal” for months, creating the potential for an escaped fire. Use the blade/rake to work the fine organic material back away from the slash pile. Do not push the fine organic material into the pile.
Slash Piling of Excess Amounts of Woody Debris
Slash piling is the concentrating and compacting of excess amounts of slash or woody debris such that the piles may be consumed by burning. Piles must be reasonably dirt-free, compacted, and piled sufficiently tight to facilitate complete burning. Piles in certain areas may be left unburned to provide habitat for wildlife. It is not desired that 100% of woody debris be piled.
Light or scattered amounts of woody debris is okay to be left un-piled on site as long as the debris is within eighteen (18) inches of the ground.
Where specified by the Forest Service, the Contractor shall uniformly pile sixty (60) to eighty
(80) percent of existing larger-sized slash. Logs larger than six (6) inches in diameter, measured at the large end, shall be piled for burning, except that up to twenty (20) logs per acre may be left un-piled provided they are well-scattered, touch the ground for their full length and are not attached to a root wad. Excess slash and logs, including cull standing timber and snags except designated leave trees, shall be moved into piles. It is desired that much of the needles, small twigs and branches, cones, litter, and duff be left on site, un-piled, for nutrient cycling, erosion control, and for a seed source (cones). Undesired live trees will be grubbed out of the ground and piled for disposal or have their root systems so damaged that the potential for survival is nil.
All remaining slash shall be treated to lie within eighteen (18) inches of the ground. At least forty (40) percent of the ground surface shall be scarified, that is, the soil is to be disturbed, but not displaced.
In areas with slopes greater than thirty (30) percent, the Contractor may have the option of either crushing or piling the steeper ground. All remaining slash shall be treated to lie within eighteen
(18) inches of the ground and leave twenty-five (25) percent of the ground surface scarified, that is, the soil is to be disturbed, but not displaced. At the discretion of the Contracting Officers Representative, treatment of specific steep areas will not be conducted to protect resources.
Piles to be burned shall be a minimum of eight (8) feet wide by six (6) feet high and eight (8) and twenty (20) feet long. When it can be done safely, slash shall be piled on the contour rather than parallel to the slope of steep ground to avoid erosion of the soil. Piles must be reasonably dirt-free, compacted, and piled sufficiently tight, steep-sided, and pushed as tall as the equipment will allow in order to facilitate complete burning. Fine organic material from slash mats will not be incorporated into slash piles. If necessary, slash piles will be reworked to reduce the amount of dirt and fine-organic material included in the pile.
Stumps shall not be grubbed out of the ground and incorporated into slash piles due to the amount of dirt. Root wads from down trees will not be included in piles, unless old and dirt-free.
Smaller piles of debris may be built and/or left as directed by the Contracting Officers Representative for wildlife habitat.
Piles of slash to be burned shall be located so that burning operations will not damage desirable standing live trees. Piles shall not be constructed within a one hundred (100) foot of the edge of units, or within one hundred (100) feet of drainage ditches, or within high water marks of live and intermittent streams. All units will be piled in such a manner that after treatment, heavy slash concentrations shall not exist unless otherwise directed by the Contracting Officers Representative.
Experience has shown that treatment of slash mats normally turns up a number of short logs which if in excessive amounts will need to be piled for disposal. The logs will need to be separated from the fine organic debris and dirt during piling to provide for cleaner burning, dirt-free piles. There also tends to be high stumps hidden under slash mats which the operator will need to be careful to avoid for high centering or damaging the equipment.
Crushing Slash and Trampling Cull Trees
Crushing is the process of breaking up, spreading, and compacting slash to reduce slash height, and spreading concentrations of slash out over a larger area by mechanical means.
Trampling is the process of knocking down standing cull and undesired trees, brush, and deep slash; spreading and compacting slash to reduce slash height and spreading concentrations of slash out over a larger area by mechanical means. Trees which are trampled shall have their root systems either grubbed out of the soil or be so damaged as to eliminate the trees potential for survival.
Crushing and trampling of woody debris may be used where heavy slash concentrations do not exist, and most of the slash is comprised of debris less than six (6) inches diameter at the large end. Slash shall be treated to lie within eighteen (18) inches of the ground. Where crushing and trampling is used, areas will be treated in such a manner that after treatment, heavy slash concentrations shall not exist, unless otherwise directed by the Contracting Officers Representative. Small piles of debris may be built and/or left as directed by the Contractor Officers Representative for wildlife habitat.
Methods and Features for Road Maintenance, Road Closure and Road Obliteration
Road closure locations and methods may be designated on the ground by the Forest Service using pin flags or plastic flagging, or as directed by the Contracting Officers Representative.
Ripping and slashing are commonly used together in road closure work. Ripping the roadbed is intended to reduce soil compaction, rehabilitate the soil to a vegetative productive condition, and to make the soil surface receptive to grass and tree seed. Slashing is intended to eliminate the use of the roadbed by motorized and mechanized traffic. Waterbars are installed or maintained during the process for erosion control.
Drainage crossings will be treated to provide for water flow with minimized erosion and sedimentation.
Roads which will be left open to public motorized and mechanized use will be maintained to reduce soil erosion. In general, maintenance will be by installing or improving waterbars, rolling dips, and drainage ditches. The size and shape of drainage facilities will be such to remain effective for an extended period of time while allowing passage by normal high clearance highway vehicles operated by prudent drivers. A minimal amount of road surface blading may be conducted as necessary and practical considering the type of heavy equipment used in the contract work, such as a dozer back blading with a swing brush rake.
The Forest Service may provide chainsaw support for the Contractor during closure operations and apply erosion control seed as needed.
Road Opening/Clearing
Level road closure berms or tank traps, move obstructing slash, stumps, logs, rocks and other debris off to the side to allow full-sized motor vehicles to safely operate on the roadway.
Waterbars and rolling dips will be cleared and made functional. A minimum of road surface blading will be conducted only as needed to facilitate traffic. Otherwise leave “grassed over” road surfaces alone and use the equipment tracks to “smooth” the road surface. Road slashing materials should be conserved at the side of the road for future reuse in closing the roadway.
Roadbed Ripping
Rip the roadbed with rippers or brush rake teeth to break-up soil compaction and roughen the road surface. The ripped road surface will be more receptive to grass and tree seed establishment. Surface water flow is disrupted on the road surface, reducing the soil erosion potential. The intent is to return the roadbed to vegetative production and assist in preventing motorized or mechanized use. The road closure may be for a short number of years, or a permanent closure. Ripping is commonly applied along the entire length of the road segment, except where the road surface is already revegetated, or is too rocky to rip. Pulling up rocks helps in discouraging vehicle traffic. Ripping should be as deep as the equipment will allow.
Short of full road re-contouring, during the ripping process, as much of the fill material on the downhill side of the road is to be pulled back up onto the roadbed. Realistically, the amount of fill to be drifted back up will be dependent on the type of heavy equipment in use, and whether or not a brush rake or straight dozer blade is installed. An excavator is an excellent piece of equipment for pulling fill material back up onto the roadbed. It is not necessary that drifted fill material be spread and smoothed. Mounds and windrows of soil will be acceptable as long as water flow or erosion control is not compromised. Woody debris and rocks maybe mixed into the drifted material.
Waterbars will be installed or maintained to minimize water flowing across the disturbed surface for erosion control. Waterbar frequency or spacing will be dependent on soil type, cross slope, and road grade. Steeper slopes and road grades will necessitate closer waterbar spacing to divert water from the disturbed area.
Road Slashing
Placement of logs, slash, stumps, and rocks on a roadbed to prevent motorized and mechanized use. The roadbed prism may or may not be left intact for future reopening and use. Felling or pushing over nearby trees often provides the woody debris necessary to close the roadway to use.
Caution is required to avoid creating a situation where Off-Road Vehicles are able to pioneer new travel ways adjacent to closed routes because all the obstructing materials are placed in the closed road. Commonly the entire length of road segment to be closed will be treated as needed to prevent use and avoid erosion.
Road Tank Traps or Earth Berms
Large, tall, abrupt, and steep-sided earthen berms installed with the intention of closing roadways to motorized and mechanized use. Placement of rocks, logs, stumps, and slash enhance the road closure effectiveness. The roughened surface will be receptive to grass and tree seed for revegetation. Earth Berms also act as waterbars for erosion control. Tank traps are usually one of several road closure features utilized on a road segment. See “Exhibit 2 - Earth Berms” for an illustration.
Roadbed Re-contouring
Restoring an excavated roadbed prism back to full vegetative productivity by pulling road fill material up on to the roadbed and cut slope, thus returning the ground line back to the natural contour. Prior to re-contouring, the roadbed will be ripped to reduce soil compaction. Logs, slash, stumps, and rocks are placed on the roadbed to further discourage and prevent motorized and mechanized use. An excavator is a better type of equipment for re-contouring.
Other Minor “Finesse” Work
Other minor amounts of unspecified equipment work may be requested by the Contracting Officers Representative while the equipment is in the project area, if contract time allows, and if the minor work is agreed to by the Contractor. Minor “finesse” work could include, but is not limited to, items such as installing or maintaining erosion control facilities away from roads and cutting units, cleaning up other slash concentrations, or closing jeep trails. The ash beds of burned slash piles in previously site prepared cutting units (not included in this solicitation) may be ripped and spread out as time allows.
Minor finesse work will be paid for at the contracted hourly rate of Optional Bid Item.
Performance Requirements Summary
Performance Work
Statement
Performance Standard (Acceptable Quality Level)
Monitoring Methods
Effect Of Not Meeting Standard
Rehabilitation of Ash Pits
The ash and charcoal bed has been ripped and mixed with mineral soil, the site smoothed, and surrounding residual woody debris mats scattered, spread, or broken-up.
Visual inspection by Government Inspector.
Rework the area at no additional cost to the Government.
Methods and Features for
Road Maintenance and Road Closure
Vehicle access has been blocked by scattering, rocks, slash and debris on the roadway, and erosion control features have been implemented in a manner that protects soil from erosion.
Visual inspection by Government Inspector supplemented by sample plots as necessary.
Rework the area at no additional cost to the Government.
Inspections and Acceptance
(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering the services under this contract. Complete records of all inspection work
File details come from the government source that posted it. Updated .