Statement of Work
Background:
The Lake City VA Medical Center has recently done a survey of the sanitary and storm sewer piping underground. During this survey it was discovered that there is an existing 4” pipe connected to manhole #1 (see attached drawing) with a recurring discharge of water at 160 degrees and a section of the discharge piping located outside building 74 (laundry) has a break in the bottom of the pipe between manhole #1 and manhole #2. This section of the sanitary sewer appears to be 10” clay piping and is approximately 75’ long with a manhole on each end.
Objective:
1st Phase (Re-Reroute 4” discharge pipe)- A qualified contractor must sawcut a section of asphalt (approximately 100 linear feet). The contractor then shall excavate near manhole #1 to expose the existing 4” pipe to provide and install a new fitting and remove the remaining pipe from the manhole. Contractor shall seal the manhole penetration and excavate a trench in the dirt approximate 160 linear feet toward the asphalt excavation area. Contractor will properly re-route the pipe from manhole #1 to manhole #3 which is approximately 240’ away. New cast iron piping shall be installed from manhole #1 to manhole #3 and terminate the piping in the manhole with proper tapping and seal the penetration. After inspection they will then backfill, grade, and repair the section of asphalt.
2nd Phase (Pipe Liner Repair) - A qualified contractor must Camera/inspect and provide cleaning procedures, Contractor shall investigate, assess, and repair any underground or surface voids caused by breakage. Contractor shall install approximate 80 linear feet of piping liner, test and re-camera/inspect the piping system from manhole #1 to manhole #2. Contractor to provide required documentation.
Scope of Work:
Re-Reroute 4” discharge pipe
· Contractor must conduct site visit prior to award to investigate damage caused by breakage and assess underground and surface repairs, to ensure its inclusion in proposal.
· Coordinate all work with the Pipefitter and Mechanical Supervisor.
· Sawcut a section of asphalt (approximately 100 linear feet).
· Excavate a trench in the dirt approximate 160 linear feet toward the asphalt excavation area.
· Install approximately 240 LFT of 4” cast iron piping underground and terminate pipe in a manhole.
· Inspect and test pipe before to backfill, compact, grade, and repair the section of asphalt.
· Clean
Pipe Liner Repair
· Jet sanitary line prior to inspection.
· Visually inspect the piping system prior to lining and verify pipe size.
· Install new liner.
· Inject grout to fill voids underground and lay fill dirt at surface to repair ground level and underground voids.
· Visually reinspect the liner once installed for defects and test.
· Provide video footage of before and after inspections.
· System Proposal / final submittal must contain warranty on material and labor
Salient Characteristics of Liner
· Compressed air inflation procedure
· UV or LED curing method
· Pull in place installation
· Unsaturated polyester vinyl ester resin system
· Contain a longitudinal seam
· 70-year recovery period
· Glass fiber stitch bonded fabric, non-woven reinforcement material
· 4.6% allowed stretching in axial direction
· 0% stretching in axial direction
· Textile glass type consistent of west dominate ECR glass which is permanently resistant to chemical agents or corrosion
· Inner foil material PE/PA
· Outer fleece material PP/PP
· Outer protective foil material PE/PA/PE
· Gliding foil material HDPE
Qualifications/Certifications
· The contractor must be qualified and have the required levels of professional and technical experience to perform the work required by this statement of work.
· The contractor and all the individuals working on the project site must have taken the OSHA Certified 10-hour construction safety course.
· Contractor to provide submittal of product prior to award and to include warranty on parts and labor.
Safety Regulations
· All OSHA safety regulations shall be observed during the project.
· The VA Safety Officer shall have full authority to see that the contractor obeys all safety rules and regulations relative to the fulfillment of this project.
· Provide the necessary barricades/signage where required.
· Contractor will be responsible to provide all necessary PPE
Scheduling and Hours of Work
· All work in areas involved shall be scheduled with the VA Maintenance Mechanic Supervisor.
· The 10 holidays observed by the Federal Government, are New Year’s Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas or any other day specifically declared by the President of the United States to be a national holiday.
· Contractor responsible for signing in each morning at engineering office and acquiring ID badges.
Evaluation/Selection Factor:
The project must be performed by a contractor that has the capability and capacity to perform the job. Managerial expertise, Technical expertise, past performance and, cost is always a consideration.