This is a Statement of Work (SOW) for the procurement of tactical equipment by the U.S. Customs and Border Protection (CBP) El Centro Station.
The procurement requires 355 Micro Map Back Panels and 355 Agilite SAPI Hydration Bladders to support U.S. Border Patrol agents operating in remote, high-temperature environments. The Micro Map Back Panels are modular storage panels compatible with tactical gear, while the Agilite SAPI Hydration Bladders are hydration systems designed for integration with body armor. All equipment must be new, non-refurbished, and Trade Agreements Act (TAA) compliant, with a minimum one-year warranty covering parts and labor. The contractor is responsible for testing and certifying all equipment functionality prior to delivery, providing product manuals and warranty documentation in both paper and electronic formats, and delivering all items to the El Centro Station in Imperial, California within 120 days of order award. The contractor must also provide documentation demonstrating compatibility, suitability, and durability of the products and clearly identify any exceptions taken to the SOW requirements. Payment requests must be submitted electronically through the Invoice Processing Platform (IPP) beginning April 11, 2016, and all procurement must comply with DHS Green Procurement Program requirements for environmentally preferable products. The primary point of contact is Trevor Ambrosini at the El Centro Station, with the period of performance consisting of a one-time delivery within 120 days after award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combined Synopsis-70B03C26Q00000129.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
U.S. CUSTOMS AND BORDER PROTECTION
EL CENTRO STATION
STATEMENT OF WORK (SOW)
Micro Map Back Panels with Agilite SAPI Hydration Bladders
1. BACKGROUND
USBP agents at El Centro Station operate in remote, high-temperature environments and often conduct extended enforcement operations. Current gear lacks sufficient modular storage and hydration capabilities, impacting agent safety, endurance, and operational effectiveness. The procurement of Micro Map Back Panels and Agilite SAPI Hydration Bladders will provide agents with improved hydration and modular storage solutions, ensuring readiness and safety during long shifts and challenging conditions. These items directly support DHS mission objectives of securing and managing borders and strengthening national preparedness and resilience.
2. OBJECTIVE/PURPOSE
The objective of this SOW is to procure 355 (ea) Micro Map Back Panels and 355 (ea) Agilite SAPI Hydration Bladders for USBP agents at El Centro Station.
3. SCOPE OF WORK
3.1 The contractor shall provide 355 (ea) Micro Map Back Panels and 355 (ea) Agilite SAPI Hydration Bladders, or equivalent, meeting the specifications outlined in Section 5.
3.2 The contractor shall deliver equipment to the designated delivery point.
3.3 The contractor shall provide product documentation and warranty information in both paper and electronic formats.
3.4 The contractor shall address all Parts, Sections, and Items in this SOW and clearly identify any exception taken to any Part, Section, or Item.
3.5 The contractor shall provide documentation indicating the compatibility, suitability, and durability of all products.
4. APPLICABLE DOCUMENTS
4.1 Federal Acquisition Regulations (FAR):
https://www.acquisition.gov/browse/index/far
4.2 Homeland Security Acquisition Regulation (HSAR):
https://www.dhs.gov/xlibrary/assets/opnbiz/cpo-acquisition-regulation-0606.pdf https://www.acquisition.gov/browse/index/far https://www.dhs.gov/xlibrary/assets/opnbiz/cpo-acquisition-regulation-0606.pdf
4.3 Code of Federal Regulations (CFR):
https://www.govinfo.gov/app/collection/cfr/2021/
5. SPECIFIC TASKS
5.1 Testing
The contractor shall test and certify the functionality of all equipment prior to delivery.
5.2 Delivery
The contractor shall deliver all equipment as specified in this SOW.
5.3 Documentation
The contractor shall provide product manuals and warranty documentation.
6. DELIVERABLES AND DELIVERY SCHEDULE
6.1 Equipment Descriptions
Micro Map Back Panels: Modular storage panels compatible with tactical gear; new, TAA compliant.
Agilite SAPI Hydration Bladders: Hydration systems designed for integration with body armor;
new, TAA compliant.
Minimum one-year warranty, parts and labor
New, non-refurbished
6.2 Delivery Schedule
Delivery within 120 days after order award.
7. POINT OF DELIVERY
POC: Trevor Ambrosini U.S. Border Patrol, El Centro Station 221 West Aten Road Imperial, Calif. 92251
Phone: (760) 337-7167 Email: trevor.n.ambrosini@cbp.dhs.gov
8. GOVERNMENT FURNISHED EQUIPMENT AND INFORMATION
None.
9. TERM OF CONTRACT AND PERIOD OF PERFORMANCE
One-time delivery: period of performance is 120 days after award.
10. SECTION 508 REQUIREMENTS
https://www.govinfo.gov/app/collection/cfr/2021/ mailto:trevor.n.ambrosini@cbp.dhs.gov
Not applicable; equipment is not considered ICT.
11. ELECTRONIC INVOICE AND PAYMENT REQUIREMENTS - INVOICE
PROCESSING PLATFORM (IPP)
Beginning April 11, 2016, payment requests for all new awards must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
Payment terms for existing contracts and orders awarded prior to April 11, 2016, remain the same. The Contractor must use IPP for contracts and orders awarded April 11, 2016, or later, and must use the non-IPP invoicing process for those contracts and orders awarded prior to April 11, 2016.
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in FAR 32.905(b), "Payment documentation and process" and the applicable Prompt Payment clause included in this contract. The IPP website address is:
https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the
IPP:
-Printable Copy of Invoice (PDF)
The IPP was designed and developed for Contractors to enroll, access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting IPPCustomerSupport@fms.treas.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the contracting officer.
12. ENVIRONMENTAL MANAGEMENT
In compliance with DHS "Green Procurement Program" (GPP) policy, environmentally preferable products and services are required.
https://www.ofee.gov
These program elements include recovered material products, energy and water efficient products, alternative fuels and fuel efficiency, bio-based products, non-ozone depleting substances, priority chemicals, and environmentally preferable products. These program elements are described on the Office of the Federal Environment Executive website (http://www.ofee.gov).
13. TRAVEL
13.1 No travel required.
https://www.ipp.gov/ https://www.ofee.gov/
14. POINTS OF CONTACT
14.1 PRIMARY POC
Trevor Ambrosini Special Operations Supervisors Phone: (760) 337-7167 Email: trevor.n.ambrosini@cbp.dhs.gov
14.2 ALTERNATE POC
Steven Wyatt Acting Special Operation Supervisor Phone: (760) 337-7114 steven.m.wyatt@cbp.dhs.gov
14.3 IPP APPROVER
Juanita Sanchez
(760) 335-5700 ext. 5931 Email: juanita.sanchez@cbp.dhs.gov
15. ACRONYM AND ABBREVIATION LIST:
Acronym Definition
CBP Customs and Border Protection
CFR Code of Federal Regulations
POP Period of Performance
SOW Statement of Work
TAA Trade Agreements Act
USBP United States Border Patrol
USG United States Government mailto:trevor.n.ambrosini@cbp.dhs.gov mailto:steven.m.wyatt@cbp.dhs.gov mailto:juanita.sanchez@cbp.dhs.gov
File details come from the government source that posted it. Updated .