Attachment 1_SOW Install Grain Storage System_Redacted.pdf
PDF 3 MB Posted
- Solicitation number
- 12405B24Q0316
About this file
This document is a Statement of Work (SOW) for the installation of a grain storage system at the Central Crops Research Station in Clayton, NC. The key requirements are:
The contractor shall furnish all materials, labor, equipment, and supervision to install a complete grain storage system, including site preparation, slab construction, bin erection, wiring, and coordination with the local power utility. The work includes preparing the site, installing the slab/foundations, delivering and erecting the grain bins, and modifying the electrical infrastructure. The contractor must also provide operations and maintenance manuals and train the farm staff. The period of performance is 120 calendar days from contract award. The contractor is responsible for all waste disposal and must make efforts to recycle materials.
The related federal contract opportunity is a solicitation (number 12405B24Q0316) issued by the USDA Agricultural Research Service for the installation of this grain storage system in Clayton, NC. The NAICS code is 236220 with a $45M small business size standard. A site visit is scheduled for August 14, 2024, and the registration deadline is August 8, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_12405B24Q0316_Amd_0001.pdf | ||
| QAs.pdf | ||
| Attachment 8_Past Performance Questionnaire.docx | DOCX document | |
| Attachment 7_Experience Sheet.docx | DOCX document | |
| Sol_12405B24Q0316.pdf | ||
| Attachment 2_Davis-Bacon Act WD NC20240126.pdf | ||
| Attachment 3_ARS-371.pdf | ||
| Attachment 5_ARS Facilities Design Standards ARS-242.1.pdf | ||
| Attachment 4_ARS-372.pdf | ||
| Attachment 6_SF 24 Bid Bond.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
Installation of Grain Storage System
Central Crops Research Station 13223 US Business 70 West
Clayton NC 27520
Table of Contents
1. Project Site Map Page 3
2. Project Points of Contact Page 4
3. Project Requirements Page 4
4. General Requirements Page 5
5. Temporary Facilities Page 7
6. Project Schedule Page 7
7. Specifications Page 7
8. Site Pictures Page 9
1.0 PROJECT SITE MAP:
Project Title: “Installation of Grain Storage System” at the Central Crops Research Station, Clayton NC
2.0 PROJECT POINTS OF CONTACT:
LOCATION POINT OF CONTACT (LPOC) Email:
ialist
ADMINISTRATIVE OFFICER (AO) Email:
ENGINEER PROJECT MANAGER (EPM) Email:
3.0 PROJECT REQUIREMENTS:
The objective of this project is to furnish materials, labor, equipment, and supervision to install a complete grain storage system to meet or exceed specifications and salient characteristics listed in Section 7.0 - Specifications. Work will include system design, site preparation, slab construction, material delivery, bin erection, wiring, coordination of necessary infrastructure changes with local power utility (Duke Energy).
1. The major items of work are listed in the following task list:
1. Prepare site for slab construction as described in this Statement of Work.
2. Install slab/foundations as indicated in this Statement of Work and grain bin manufacturer’s recommendations.
3. Deliver materials and erect grain storage bins.
4. Install, modify, and otherwise adapt electrical infrastructure, perform testing and startup procedures.
5. Instruct farm staff on proper operation of grain storage system.
6. Provide Operations and Maintenance Manual outlining operation procedures, safety considerations, and manufacturer recommended maintenance intervals and procedures.
2. The Contractor shall be responsible for handling and disposal of debris at an off-site, certified disposal site consistent with all Local, State, and Federal requirements.
3.1 Pre-Construction:
a. Pre-Construction Submittals
Prior to commence of onsite work, the following submittals must be submitted to the Contracting Officer Representative (COR) for approval:
1. Work Hours, per Section H.30 entitled, MAXIMUM WORKWEEK – CONSTRUCTION SCHEDULE. The work hours will include the daily starting and stopping time, and days of the week the Contractor proposes to carry out the work. Daily Facility hours are from 8:00a.m. to 5:00 p.m. excluding weekends and Federal holidays. Contractor shall submit a work schedule conforming to the times of operation listed above and list the anticipated completion date.
2. A completed ARS-371 CONSTRUCTION PROGRESS AND PAYMENT SCHEDULE
3. Site plan, foundations, and materials submittals; include grain bin makes, models, specifications, and drawings.
4. Quality Control Plan.
5. Site Specific Accident Prevention Plan/Safety plan complete with contact info and map to nearest emergency room and minor medical facility.
6. The construction contractor (CC) shall provide to the COR a list of contract personnel of the general and subcontractors, who will be emergency contacts, including address, and telephone numbers for use in an emergency. As changes occur and additional information becomes available, the CC shall update the list.
7. Waste Management Plan: Plan should be submitted within 14 days of contract award.
Approval of the contractor’s plan does not relieve the contractor of responsibility for compliance with any applicable environmental regulations. This plan should include all proposed disposal sites and should include waste diversion and recycling when possible.
3.2 Government Furnished Equipment\Services: No Government owned equipment or service shall be provided.
4.0 GENERAL REQUIREMENTS:
4.1 Permits:
Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
4.2 Utility Severance Certificates: Not required.
4.3 Installation Plan:
Submit a comprehensive installation plan, describing the proposed sequence, schedule, methods, equipment, storage requirements, and laydown areas.
4.4 Installation Schedule:
Contractor shall coordinate assembly and installation with Local Point of Contact or COR. All disturbances or disruptions of service as a part of work for this project shall be coordinated with the LPOC or COR to prevent jeopardizing on-going research.
4.5 Quality Control:
The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.
4.6 Protection of Work and Property/Safety Requirements:
a. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work.
Any damage to property shall be repaired at the Contractor’s expense to pre-damaged condition to the satisfaction of the COR.
b. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities for the protection and safety of pedestrians and vehicular traffic.
c. The Contract Documents may not represent all current conditions at the site and adjoining areas.
The known conditions are as indicated and shall be compared with actual conditions before commencement of work. Any notable differences shall be memorialized in writing and brought to the attention of the LPOC and COR for further consideration.
d. Government will not furnish any labor or equipment to unload or move materials or supplies.
4.7 Hazardous material:
a. If the Contractor discovers suspected hazardous materials at this worksite, the LPOC, CO and COR will be notified immediately for further action.
4.8 Disposal of Waste Materials and Debris:
a. Dispose of waste, trash, and debris in a safe, acceptable manner, in accordance with applicable laws and ordinances and as prescribed by authorities having jurisdiction.
b. Burying of trash and debris on the site will not be permitted. Burning of trash and debris at the site will not be permitted.
c. Remove trash and debris from the site at frequent intervals so that their presence will not delay the progress of the work or cause hazardous conditions for workers and the public.
d. The contractor should make every effort to recycle as much of the waste as possible.
5.0 Temporary Facilities:
a. Temporary utilities (water and electricity) are not available at the site.
b. Should the Contractor require any power or utility shutdowns during demolition, the Contractor shall obtain approval for such shutdown from the COR three working days prior to the need.
5.1 Cleanup:
The work site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
5.2 Final Payment/Contract Closeout:
The following documents are REQUIRED PRIOR TO FINAL PAYMENT (other documents may also be required):
a. Release of liens.
b. Release of Claims
c. Employee payroll\time sheets
d. Invoice
6.0 PROJECT SCHEDULE: The performance period for this project is 120 calendar days from contract award. Mandatory preconstruction conference shall be required after submittals have been approved and/or prior to commence of work.
7.0 Specifications
7.1 Foundation Specifications – The following are minimum specifications. If cases where specific grain storage bin manufacturer foundation requirements exceed these minimum specifications, the more rigorous specification shall apply.
a. Contractor will adhere to the American Concrete Institute guidelines and standards for concrete placement, vibration, testing, finishing, curing, hot weather, cold weather, etc. Contractor will provide the Design Mix for minimum 3500 psi. with approval from USDA EPM.
b. Concrete shall be tested per each 20 CY of concrete by a certified concrete testing laboratory provided by the contractor. Tests shall include slump, air, temperature, and compressive strength.
2 sets of cylinders shall be made per each 20 C.Y. concrete. 1 set for 7 day strength and 1 for 28 day strength. Certified reports shall be sent to the EPM and COR.
c. The Contractor's approved laboratory shall collect samples of fresh concrete in accordance with ASTM C172/C172M during each concrete pour as required to perform tests specified herein. Make test specimens in accordance with ASTM C31/C31.
d. The Contractor's approved laboratory shall perform concrete slump tests in accordance with ASTM C143/C143M. Take samples for slump determination from concrete during placement. Perform tests at the beginning of a concrete placement operation to ensure that specification requirements are met.
e. Make four test specimens for each set of tests. Test two specimens at [7] days, and the other two at [28] days. Concrete strength will be considered satisfactory when the minimum of the [28]-day test results equal or exceeds the specified [28]-day strength. Concrete which is determined to be defective shall be removed and replaced with acceptable concrete.
f. All demolished materials, removed soil, and other debris generated shall be removed by the
Contractor.
g. Strip vegetative material and excavate as necessary to provide a stable base for the concrete slab to include grading, soil removal, soil addition, compaction, subbase installation, and any other work necessary for slab construction.
h. Hot Weather: Maintain required concrete temperature in accordance with Figure NRMCA NOMOGRAPH FOR ESTIMATING EVAPORATION RATE ON THE BASIS OF MENZEL FORMULA in ACI
305.1 to prevent evaporation rate from exceeding 0.2 pound of water per square foot of exposed concrete per hour. Cool ingredients before mixing or use other suitable means to control concrete temperature and prevent rapid drying of newly placed concrete. After placement, use fog spray, apply monomolecular film, or use other suitable means to reduce the evaporation rate. Start curing when surface of fresh concrete is sufficiently hard to permit curing without damage. Cool underlying material by sprinkling lightly with water before placing concrete. Follow practices found in ACI 305.1.
i. Finished dimensions, elevation, and surrounding earth shall allow for farm vehicles/machinery to access the grain storage bin loading and unloading areas on smoothed, flat or gently sloped terrain.
Picture 3 – Picture taken on site at pole location, facing North-Northwest.
Picture 4 – Picture taken on site at approximate midpoint of site, facing North.
Picture 5 – Picture taken on site, at road North of proposed location of grian bin. Facing South.
Picture 6 – Power pole and pole identification facing west.
File details come from the government source that posted it. Updated .