This is a Statement of Work (SOW) for flooring renovation services at Building 413 of the Carl Hayden Bee Research Center in Tucson, Arizona, issued by the United States Department of Agriculture Agricultural Research Service on December 29, 2025.
The project involves preparation and installation of polyaspartic flooring coating across approximately 4,050 square feet of building space, excluding two restrooms. Preparation work includes filling and treating cracks, holes, and saw-cut lines in the existing bare concrete floor, followed by diamond grinding to create an even surface with HEPA dust collection. The new installation requires application of 100% polyaspartic coating with client-selected color choices, full flake broadcast with excess flake removal, and anti-slip additives (20/40 rating in the bay work area) meeting 100% UV stability, low VOC, and OSHA slip-resistance requirements. The contractor must provide all labor, equipment, and materials and is responsible for obtaining permits, performing quality control, and maintaining site safety. The contract duration is 90 calendar days from Notice to Proceed. Warranty requirements include one-year coverage on labor and parts from the contractor and a ten-year manufacturer warranty on equipment. Required submittals prior to final payment include a Site-Specific Safety Plan or Accident Prevention Plan, manufacturer's literature with shop drawings, operation and maintenance data, release of liens, and a final invoice. The Location Monitor is Roger Clemo (roger.clemo@usda.gov, 520-330-1896), and the Administrative Officer is Joseph Garrett (Joseph.garrett@usda.gov, 602-303-4860). All work must comply with applicable federal, state, and local codes, UFGS standards, and ARS 242.1M standards.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_1232SA26Q0202.pdf | ||
| Attachment 2 - Wage Determination AZ20260040.pdf | ||
| Attachment 3 - Bldg Floor Plan.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
BLDG 413 Flooring
CARL HAYDEN BEE RESEARCH CENTER
TUCSON, AZ
Date: 12/29/2025
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
a. Project Number: TBD
b. Project Title: Bldg 413 Flooring
c. Project Location: Carl Hayden and Southwest Watershed Research Center 2000 E. Allen Road, Tucson AZ
2.0 PROJECT CONTACT PERSONS:
a. CONTRACTING OFFICER (CO):
NAME
USDA-ARS-PWA
Email: Tel. No.:
b. CONTRACTING SPECIALIST (CS):
NAME
c. LOCATION MONITOR (LM):
Roger Clemo
USDA-ARS-PWA
2000 E. Allen Road, Tucson AZ 85719 Email: roger.clemo@usda.gov Tel. No.: 520-330-1896
d. ADMINISTRATIVE OFFICER (AO):
Joseph Garrett
USDA-ARS-PWA
21881 N Cardon Ln, Maricopa AZ 85138 Email: Joseph.garrett@usda.gov Tel. No.: 602-303-4860
e. CONTRACTING OFFICERS REPRESENTATIVE (COR):
Roger Clemo
USDA-ARS-PWA
2000 E. Allen Road, Tucson AZ 85719 Email: roger.clemo@usda.gov Tel. No.: 520-330-1896
f. AREA SAFETY AND HEALTH MANAGER
Address
g. ENGINEERING PROJECT MANAGER (EPM)
Address
Email: Tel. No.:
mailto:roger.clemo@usda.gov mailto:Joseph.garrett@usda.gov mailto:roger.clemo@usda.gov
3.0 PROJECT
DESCRIPTION:
4.0 PROJECT REQUIREMENTS:
a. Provide a standard commercial warranty against product defects and breakage and one year warranty on labor and other parts.
b. Contractors shall provide and maintain all necessary guards, lights, barricades, etc., to protect persons, property, and materials in and around the site.
c. As builds, shop drawing, Architectural or Engineered drawings
d. Do not disturb hazardous materials and report conditions immediately to the Contracting
Officer’s Representative (COR) regarding potentially hazardous conditions that are uncovered. Stop work in the area of the questionable material or condition until identification and direction is provided.
Note: ALL hazardous materials have been removed from the building
e. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e., IBC, NEC, NSPC, NFPA, EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
f. All work shall meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS
242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs. ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.
4.1 Background & Site Description:
Building 413 is approximately 4050 sq ft. North bay area is approx. 2215 sq ft and the office/storage areas are approx. 1835 sq ft. Does not include two restrooms (these are excluded)
The existing floor is bare concrete and visible with cracks and holes, which will need to be treaded and filled in. ALL joint seems to be filled in for a complete seamless finish.
4.2 Bid Schedule:
Provide all labor, equipment and materials to perform this Statement of Work and Schedule of Items.
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/
4.3 Description of Work:
a. Preparation
i. Fill in cracks, apply compound, and sand down to an even level.
ii. Fill in all saw cut lines and grind down to leveled Surface
i. Grind and fill in holes and areas where old metal anchors are.
ii. Fill in all saw cut lines and grind down to leveled surface.
iii. Sand (diamond grind) concrete to an even level. All machinery shall be equipped with
HEPA dust collectors to minimize dust during the process.
b. New Installation
i. Apply 100% Polyaspartic coating color and clear coat throughout the entire building
(excluding two restrooms). Color choices to be provided for client to choose from.
ii. Full flake broadcast. Color choices to be provided for client to choose from. Excess flakes to be removed.
iii. Apply anti-slip additives, with extra addatives applied to the flooring in the bay work area (Anti slip 20/40). Need to be 100% UV stability, low VOC, and slip resistance exceeding OSHA requirements.
4.4 Government Furnished Equipment\Services
a. The government will furnish a reasonable amount of electricity and water.
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Government. All disturbances of existing systems shall be thoroughly coordinated with the Government to prevent disturbances that might jeopardize on-going operations and research. Government reserves the right to retain any equipment / materials removed as part of the scope of work. The contractor shall coordinate any equipment / materials to be retained with the Government prior to starting demolition operations. The contractor shall legally dispose of any materials removed that will not be retained.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the Location Monitor for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. The contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the Location Monitor. Quality control is the exclusive responsibility of the Contractor.
5.6 Protection of Work and Property/Safety Requirements:
a. Contractor shall furnish a Site-Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) ten days after contract award. SSSP / APP shall be approved by the Government before construction work commences.
b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the Location Monitor.
c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
d. The contractor is responsible for verifying location of any underground utility and is responsible for any damage caused to such utilities.
5.7 Temporary Facilities:
a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.
b. Should the Contractor require any power or utility shutdowns during construction, the
Contractor shall obtain approval for such shutdown from the Location Monitor twenty-one (21) working days prior to the need.
5.8 Materials and Equipment:
a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft, or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/Location Monitor.
c. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the Location Monitor.
5.10 Warranty:
a. Submit data concerning the Provided one year warranty on labor and other parts, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
b. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO
FINAL PAYMENT (other documents may also be required):
a. General contractor’s minimum one (1) year warranty on work.
b. Manufacturer ten (10) year warranty on equipment
c. Operation and Maintenance Data
d. Release of liens.
e. Final Invoice
6.0 PROJECT SCHEDULE: The Contract time for this project is 90 calendar days from Notice to Proceed. Contractor shall install new system prior to demolishing existing AC and coordinate switchover with Location Monitor.
7.0 Figures
Figure 1. Main Building Plans for Location
| United States Department of Agriculture |
| Agricultural Research Service |