Attachment 1 - SOW - Bldg 7013 Demolition Work - 14 June.pdf

PDF 219 KB Posted

Attached to
Building 7013 Demolition - Holloman AFB, NM
Solicitation number
FA480123Q0451
Issued by

About this file

This document is a Statement of Work (SOW) for the demolition and removal of Building 7013, a pre-engineered metal building, at Holloman Air Force Base in New Mexico. The SOW specifies that the building is approximately 150' x 60' x 25' and requires the contractor to demolish and dispose of the metal siding, roof, steel skeleton, doors, and any other attached materials. The contractor must also remove and dispose of a wall that separates the building into two bays. The concrete slab foundation can remain in place, but any broken debris must be removed. The project has a 120-day performance period with standard working hours of 7:00 am to 5:00 pm. The related federal contract opportunity, Solicitation Number FA480123Q0451, is for the Department of the Air Force Air Combat Command to procure these demolition services.

View the file

Other files

File Type Posted
Questions and Answers plus Photos.pdf PDF
Attachment 1 - SOW - Bldg 7013 Demolition 26 June.pdf PDF
COMBINED SYNOPSIS - 26 June.docx DOCX document
COMBINED SYNOPSIS - 21 June.docx DOCX document
COMBINED SYNOPSIS - 14 June.docx DOCX document
Site Plan and Photos.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

DEMOLISH BLDG 7013

June 14, 2024

PROJECT SPECIFIC INFORMATION:

1. Location: Bldg 7013

2. Performance Period: 120 Days

3. Working Hours: Standard (7:00 am to 5:00 pm)

4. Restricted Area (as defined in HAFB Instruction 31-102): No

SCOPE OF WORK:

1. The Contractor shall demolish Bldg 7013.

2. Bldg 7013 is 150' long x 60' wide x 25' high. It is a pre-engineered metal building. Six pictures and a Site Plan are attached.

3. Bldg 7013 is located about 12 miles west of the Test Track area.

4. Remove and dispose all the metal siding, metal roof, steel skeleton, doors, and anything else attached to the building.

5. There is a wall inside the building that separates it into two bays. Remove and dispose the wall.

6. Several pieces of siding have blown off the building and are lying around the area.

Remove and dispose these panels.

7. Leave the concrete slab in place. It does not matter if it is damaged during the course of the demolition work. However, if any chunks of the slab are broken out, remove and dispose of this debris. Any anchor bolts in the slab can remain in place.

8. All the utilities to this building have been shut off. Do not remove any underground piping.

9. Sand has accumulated against the sides of the building. Push the sand away from the building before beginning demolition work. Level and grade the ground surface around the building after demolition work is complete.

10. The road out to Bldg 7013 is frequently closed. Notice of any planned closure is provided a week in advance. Contact Mr. Shane Eastman at 575-572-1045 or shane.eastman.2@us.af.mil for daily road closure information.

11. Take several pictures of the site after demolition operations are complete.

----END STATEMENT OF WORK----