This statement of work outlines hydrologic data collection services required by the Bureau of Reclamation within the state of Colorado. The contractor will perform stream gauging twice monthly at the Parshall Flume station and take flow measurements up to three times per year at additional sites. Duties include operating and maintaining data recorder systems, developing rating tables, analyzing results and submitting monthly reports within five days of each month-end. The contractor must have necessary field equipment and follow Reclamation safety standards. The initial contract term is five years from the award date. The solicitation number for this opportunity is 140R4023Q0062 and it was issued by the Department of the Interior Bureau of Reclamation for hydrologic data collection services within their San Luis Valley Project, Closed Basin Division located in south central Colorado.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WBR_1413_106-1_Template_1_Determination_to_solicit_from_SS_under_SAT__FAR_13_Fully_signed.pdf | ||
| Sol_140R4023Q0062.pdf | ||
| Attachment_2_-_WD_2015-5433_Rev_No_24_7_25_2023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
HYDROLOGIC DATA COLLECTION
BACKGROUND
Work consists of tasks listed below for sites located within the Bureau of Reclamation’s Upper Colorado region. The work is to be performed within the state of Colorado, on the San Luis Valley Project, Closed Basin Division. The Closed Basin Division is in south central Colorado in the San Luis Valley in a topographic basin called the Closed Basin. The Closed Basin has a surface area of 2,940 square miles.
The contractor collects hydrologic data from the waterways, pumping plants, and measuring structures within the Closed Basin Division Project area. This data provides the proper accounting of Project waters in compliance with the Rio Grande Compact and a mechanism for the Project personnel to verify the accuracies of the water measuring devices currently being used within the Project.
Accurate reading and analysis of readings are critical to downstream reporting and is presented at the Compact Commission Meeting. Data is reviewed by the Colorado State Engineer and the Rio Grande Compact Engineer Advisor and must meet USGS Standards or greater.
SCOPE
• The gauging and rating program will continue to be followed under this contract as deemed reasonably necessary with respect to circumstances and duties to be performed.
Gauging is performed at Parshall Flume twice a month and a measurement note shall be produced for each measurement
• Contractor personnel will be available to provide Bureau personnel with data and advice regarding water measuring devices located on the Closed Basin Project.
• Monthly discharge records for the Parshall Flume and periodic shift information will be provided to Reclamation within five working days of the end of each month.
• The original data will be filed electronically by the contractor for the period required by the Rio Grande Compact for hydrologic data. These records will be available to Reclamation, the Compact Commission, and other agencies for publication or other related work.
OBJECTIVES
The objective of this contract is to acquire contractor services to collect hydrologic data from the waterways, pumping plants, and measuring structures within the Closed Basin Division Project area.
TASKS
Data Collection Activities: Data will consist of copies of all field measurement records for all sites; developed rating tables for water measuring structures and other devices. Stream gauging to collect surface water data from the Parshall Flume at Sta. 281 + 00 will be performed twice monthly. Contractor personnel will measure the flow through additional water measuring structures and devices at specific locations on an as needed basis, not to exceed three visits per site per year. Other sites are as follows:
Site Normal.
Freq.
CHO1, CHO2, CHO3, CHO4 – all have flow meters various
Alamosa National Wildlife Refuge Pumping Plant – Gauging Station various
San Luis Lake Pumping Plant Discharge – flow meter various
San Luis Lake Feeder Canal - flow meter various
San Luis Lake Flume – flow meter various
San Luis Creek at San Luis Lake – Gauging Station various
Head Lake Turnout – no equipment seldom
Head Lake Flume – no equipment seldom
Big springs Creek Flume – Gauging Station various
Rate Devices: Perform the rating of the Stevens Recorder located at the Parshall Flume at Sta.
281 + 00 defined by Reclamation on a semimonthly basis.
•This data will be utilized by Reclamation to verify the accuracies of the water measuring devices, to monitor surface water conditions, and to account for water salvaged and delivered from the Project.
CONTRACTOR PERSONNEL
The following activities shall be supervised by key personnel:
The gauging and rating program will continue to be followed under this contract as deemed reasonably necessary with respect to circumstances and duties to be performed.
Gauging is performed at Parshall Flume twice a month and a measurement note shall be produced for each measurement
Contractor will provide a shaft encoder and data collection platform system as well as a backup recorder system at the gauging station located adjacent to the 12-foot Parshall Flume. Contractor personnel shall operate and maintain these data recorder systems.
(The equipment belongs to the contractor and cost for its use is included in cost for the service)
When necessary, the chart recorders, shaft encoders, and data collection platforms installed at the 12-foot Parshall Flume gauging station will be repaired or replaced by contractor to ensure data reliability.
Contractor personnel will be available to provide Bureau personnel with data and advice regarding water measuring devices located on the Closed Basin Project.
The data collected is analyzed and the results forwarded within five working days after the end of the month in which the work is performed.
The data consists of copies of all field measurement records for all sites and developed rating tables for water measuring structures and devices.
Monthly discharge records for the Parshall Flume, and periodic shift information will be provided to Reclamation within five (5) working days of the end of each month.
The original data will be filed electronically for the period required by the Rio Grande Compact for hydrologic data. These records will be available to Reclamation, the Compact Commission, and other agencies for publication or other related work.
Key Personnel:
Personnel will coordinate work schedules and changes with Contracting Officer’s Technical Representative twenty-four hours in advance.
Field Equipment Requirements:
All necessary equipment and supplies shall be provided by the Contractor. No additional payment will be made by the Government for the use of other incidental equipment required for the performance of the work.
DELIVERY
REPORTING
Data will consist of copies of all field measurement records for all sites; meter readings, developed rating tables for water measuring structures and other devices; monthly and annual record production conducted by hydrographic technicians, and hydrographic engineers based in the Alamosa CDWR office; reviews conducted by Chief Hydrographic Engineer in Denver and/or the USGS. Costs shall include travel costs. Maintenance of equipment used in performance of this contract will be the responsibility of the contractor. Reports will be submitted to Reclamation monthly within five (5) working days after the end of each month.
The data collected under this contract shall be analyzed and the results forwarded as outlined above to the following Reclamation offices:
Bureau of Reclamation Bureau of Reclamation
Alamosa Field Division Albuquerque Projects Office 10900 Hwy. 160 E. 555 Broadway Northeast, Suite 100 Alamosa, CO 81101-9518 Albuquerque, New Mexico 87102-2352
SAFETY
Field work shall be performed in accordance with Reclamation's publication "Reclamation Safety and Health Standards" (RSHS). The Government has provided the contractor with a copy of this publication.
PLACE OF PERFORMANCE
Contractor will perform and collect surface water data from the Parshall Flume at Sta. 281 + 00 twice monthly.
Contractor personnel will measure the flow through additional water measuring structures and devices at specific locations on an as needed basis, anticipated not to exceed three visits per site per year. Those sites are as follows:
• CHOl, CH02, CH03, CH04- all have flow meters
• Alamosa National Wildlife Refuge Pumping Plant- Gauging Station.
• San Luis Lake Pumping Plant Discharge - flow meter.
• San Luis Lake Feeder Canal - flow meter.
• San Luis Lake Flume - flow meter.
• San Luis Creek at San Luis Lake - Gauging Station. Head Lake Turnout - no equipment.
Head Lake Flume - no equipment.
Big springs Creek Flume - Gauging Station.
Personnel will coordinate work schedules and changes with Contracting Officer's Technical Representative twenty-four hours in advance.
PERIOD OF PERFORMANCE
This will be a five-year contract starting from the award date.