This document is a Sources Sought Synopsis for the Galveston Entrance Channel and Houston Ship Channel Bolivar to Redfish Hopper Dredging project in Galveston County, Texas. The U.S. Army Corps of Engineers, Galveston District has a requirement for hopper dredging of the Galveston Entrance Channel and adjacent Houston Ship Channel, with an option for beneficial use beach placement. The estimated construction price range is over $10 million. The government is seeking information from industry, including small businesses, to gauge interest and capabilities for the upcoming solicitation. Responses are due by May 9, 2024, and the anticipated solicitation issuance date is December 2024, with a proposal due date of January 2025 and an estimated award date of February 2025. The contractor must be experienced in hopper dredging operations with beach pump-out and able to meet a production rate of 30,000 cy per day. Performance and payment bonds are required.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1-SOURCES SOUGHT SYNOPSIS
TITLE: Galveston Entrance Channel and Houston Ship Channel Bolivar to Redfish, Hopper Dredging, Galveston County, Texas
Notice Type: SOURCES SOUGHT SYNOPSIS
Source Sought Number: W912HY24X100B
Response Date (10 days) 09 May 2024
The U.S. Army Corps of Engineers, Galveston District has a requirement for the above subject. THIS IS A NOTICE FOR SOURCES SOUGHT ONLY. THIS
ANNOUNCEMENT SEEKS INFORMATION FROM INDUSTRY, WHICH WILL BE
USED FOR PRELIMINARY PLANNING PURPOSES. THIS IS NOT A REQUEST
FOR PROPOSAL OR INVITATION FOR BID. THERE IS NO BID PACKAGE,
SOLICITATION, SPECIFICATION OR DRAWINGS AVAILABLE WITH THIS
ANNOUNCEMENT. IT DOES NOT CONSTITUTE A PROCUREMENT
COMMITMENT BY THE US ARMY CORPS OF ENGINEERS, IMPLIED OR
OTHERWISE. NO CONTRACT WILL BE AWARDED FROM THIS SOURCES
SOUGHT ANNOUNCEMENT. REPONSE IS STRICTLY VOLUNTARY; NO
REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH
PROVIDING INFORMATION IN RESPONSE TO THIS SOURCES SOUGHT
ANNOUNCEMENT OR ANY FOLLOW-UP INFORMATION REQUESTS.
RESPONDENTS WILL NOT BE NOTIFIED OF THE RESULTS OF THE
EVALUATION.
The purpose of this synopsis is to gain knowledge of interest, capabilities, and qualifications of various members of industry, to include the Small Business Community: Small Business, Section 8(a), Historically Underutilized Business Zones (HUB-Zone), Service-Disabled Veteran-Owned Small Business (SDVOSB), Economically Disadvantaged (ED/Woman Owned (WO), Woman Owned (WO) and Woman-Owned Small Business (WOSB). Th e Government must ensure there is adequate competition of responsible firms.
Project Information: The scope of this contract is Hopper dredging of the Galveston Entrance Channel and adjacent HSC Bolivar to Redfish Reach.
Beneficial use beach placement (pump-out) at the West end of Galveston Beach (starting at Sunbather Lane) will be a contract option and will cover the incremental costs related to placing material on the beach in lieu of the ODMDS.
Potential Contract option(s) will also exist for dredging of the Galveston Harbor, Galveston Extended Entrance Channel, and Texas City Ship Channel.
Period of performance: Complete the entire work ready for use not later than 180 calendar days after the date the Contractor receives the Notice to Proceed.
Completion time for Option(s) is 120 calendar days.
In accordance with FAR 36/DFARs 236, the estimated construction price range for this project is: Over $10,000,000.
All construction performance must comply with the USACE Safety and Health Requirements Manual, (EM 385-1-1, and must also comply with all Federal, State and local laws, ordinances, codes and/or regulations.
The North American Industry Classification System code for this procurement is 237990 which has a small business size standard of $37 million.
The Product Service Code is Z1KF.
Small Businesses are reminded under FAR 52.219-14, (Deviation 2019-O0003), Limitations on Subcontracting. Firm will not pay more than 85% of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count toward the 85% subcontract amount that cannot be exceeded.
Prior Government contract work is not required for submitting a response to this announcement.
Contractor should be experienced with hopper dredging operations with beach pump-out. Contractor should be able to meet a production rate of 30,000 cy per day. Contractor should be familiar with the traffic conditions along the Galveston and Houston Ship Channels. Contractor should familiarize themselves with the west end of Galveston Beach (public), near Sunbather Lane going West.
Contractor should provide examples of being a prime contractor conducting hopper dredging with pump-out operations.
Bonding Requirements: Performance and Payment Bonds are required within 5 calendar days after award and the contractor shall begin work within 10 calendar days after receipt of the Notice to Proceed.
If the contractor fails to complete the work within the time specified, the contractor shall pay liquidated damages to the Government in the amount of $3,825.00 for each calendar day of delay until the work is completed or accepted.
FIRMS RESPONSE SHALL INCLUDE THE FOLLOWING INFORMATION:
1. Unique Entity Identifier (UEI) & Commercial and Government Entity (CAGE) (This information can be obtained from your System for Award Management (SAM) Registration at www.sam.gov ).
2. Name of firm w/ address, phone, fax, e-mail address, and point of contact.
3. Indicate whether your firm will submit a bid for this project if set-aside for Small Business (SB), 8(a) Small Business Development Program, Historically Underutilized Business Zones (HUB-Zone), Service-Disabled Veteran Owned Small Business (SDVOSB), Economically Disadvantaged (ED/Woman Owned (WO), Woman Owned (WO) Woman-Owned Small Business (WOSB).
http://www.sam.gov/
4. Firm’s Joint Ventures (existing), including Mentor Protégés and teaming arrangement information is acceptable.
Qualifications: Responses to this source sought announcement shall indicate specialized experience and technical competence in:
a. Contractor must be experience in completing work outlined under the paragraph above for “Project Information.”
1. Firm’s capability to perform the magnitude and complexity outlined in the Scope of Work above or comparable work performed within the past 5 years):
2. Brief description of each project, customer name, and dollar value of the project)– provide at least 3 examples.
3. Firm’s Bonding Capacity (Bid Bond (20% of total bid amount), Performance and Payment Bond (100% of the contract amount) bonding level per contract and aggregate construction bonding level, both expressed in dollars.
Firms responding to this announcement, who fail to provide ALL required information requested and outlined above, may be excluded from further consideration in the review and analysis for acquisition strategy determination.
Anticipated solicitation issuance date is on or about December 2024, and the estimated proposal/bid due date will be on or about January 2025. Estimated award on or about date is February 2025.The official synopsis citing the solicitation number will be issued on Procurement Integrated Enterprise Environment (PIEE) https://piee.eb.mil/ inviting firms to register electronically to receive a copy of the solicitation when it is issued.
Interested Firm’s shall respond to this announcement no later than May 09, 2024, at 10:00 AM (CDT). All interested firms must be registered in SAM.gov to be eligible for award of Government contracts. Email your response to Ms. Danelle Tate at danelle.m.tate@usace.army.mil and Mr.
Curtis Cole Jr. at curtis.cole@usace.army.mil.
https://piee.eb.mil/ mailto:danelle.m.tate@usace.army.mil mailto:%20curtis.cole@usace.army.mil.