FY26 Brazos Island Harbor (BIH) Texas, Entrance and Jetty Channel Hopper Maintenance Dredging, Cameron County, Texas
Solicitation number
W912HY26X1B38
Issued by

About this file

This is a Sources Sought Synopsis issued by the U.S. Army Corps of Engineers, Galveston District for FY2026 maintenance dredging operations at Brazos Island Harbor (BIH) in Cameron County, Texas. The synopsis number is W912HY26X1B38, with responses due by February 4, 2026, at 10:00 AM Local Time. This announcement seeks preliminary industry information only and does not constitute a procurement commitment or request for proposal; no contract will be awarded from this synopsis, and responses are strictly voluntary with no reimbursement for costs incurred.

The project requires dredging approximately 450,000 cubic yards from the BIH Entrance Channel (125,000 CY) and Jetty Channel (225,000 CY), with placement at Near Shore Feeder Berm 1A/1B on South Padre Island. The estimated construction price range is between $5,000,000 and $10,000,000, with contract completion required within 120 calendar days of Notice to Proceed. Five options are available, including three sea turtle trawling periods (15 days each), alternative beach placement at two South Padre Island locations (adding 14 calendar days), and an additional sea turtle trawling option. Work must comply with USACE Safety and Health Requirements Manual EM 385-1-1 and all federal, state, and local regulations. The NAICS code is 237990 (small business size standard of $37 million) with Product Service Code Z1KB. Liquidated damages are set at $4,300 per calendar day of delay. Performance and Payment Bonds are required within 5 calendar days of award, with work commencing within 10 calendar days of Notice to Proceed. Responses should include UEI/CAGE identifiers, firm qualifications demonstrating prime contractor experience on dredged material placement projects completed within the past five years (minimum three examples with customer names and dollar values), bonding capacity documentation, and indication of small business set-aside eligibility (SB, 8(a), HUB-Zone, SDVOSB, ED/WO, WOSB). The anticipated solicitation issuance is June 2026, with proposal due date approximately July 2026 and estimated award in September 2026. Responses should be emailed to Ms. Lillie Johnson (Lillie.S.johnson@usace.army.mil) and Ms. Joycelyn Rodgers (Joycelyn.R.Rodgers@usace.army.mil). All interested firms must be registered in SAM.gov to be eligible for government contracts.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1-SOURCES SOUGHT SYNOPSIS

TITLE: FY2026 Brazos Island Harbor (BIH) Texas, Entrance and Jetty Channel Hopper Maintenance Dredging, Cameron County, Texas

Notice Type: SOURCES SOUGHT SYNOPSIS

Source Sought Number: W912HY26X1B38

Response Date (15 days) 04 February 2026

The U.S. Army Corps of Engineers, Galveston District has a requirement for the above subject. THIS IS A NOTICE FOR SOURCES SOUGHT ONLY. THIS

ANNOUNCEMENT SEEKS INFORMATION FROM INDUSTRY, WHICH WILL BE

USED FOR PRELIMINARY PLANNING PURPOSES. THIS IS NOT A REQUEST

FOR PROPOSAL OR INVITATION FOR BID. THERE IS NO BID PACKAGE,

SOLICITATION, SPECIFICATION OR DRAWINGS AVAILABLE WITH THIS

ANNOUNCEMENT. IT DOES NOT CONSTITUTE A PROCUREMENT

COMMITMENT BY THE US ARMY CORPS OF ENGINEERS, IMPLIED OR

OTHERWISE. NO CONTRACT WILL BE AWARDED FROM THIS SOURCES

SOUGHT ANNOUNCEMENT. REPONSE IS STRICTLY VOLUNTARY; NO

REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH

PROVIDING INFORMATION IN RESPONSE TO THIS SOURCES SOUGHT

ANNOUNCEMENT OR ANY FOLLOW-UP INFORMATION REQUESTS.

RESPONDENTS WILL NOT BE NOTIFIED OF THE RESULTS OF THE

EVALUATION.

The purpose of this synopsis is to gain knowledge of interest, capabilities, and qualifications of various members of industry, to include the Small Business Community: Small Business, Section 8(a), Historically Underutilized Business Zones (HUB-Zone), Service-Disabled Veteran-Owned Small Business (SDVOSB), Economically Disadvantaged (ED/Woman Owned (WO), Woman Owned (WO) and Woman-Owned Small Business (WOSB). Th e Government must ensure there is adequate competition of responsible firms.

Project Information: The scope of the FY26 Brazos Island Harbor (BIH) Entrance and Jetty Channel maintenance dredging job will consist of dredging approximately 450,000 cubic yards of the Brazos Island Harbor, with five projected (5) options that relate to trail suction dredging and beach placement on South Padre Island.

Schedule No. 1, Hopper dredging of BIH Entrance Channel station -13+000 to station -6+00; estimated volume; 125,000 CY. And Hopper dredging of BIH Jetty Channel station -6+000 to 0+000; estimated volume: 225,000 CY.

Placement Area: Near Shore Feeder Berm 1A/1B

Options 1-3: Sea Turtle Trawling 15 days each. No additional time added to contract duration if awarded.

Option 4: Beach Placement at two locations on South Padre Island in lieu of Near Shore Feeder Berm 1A/1B. If awarded, additional time of 14 calendar days will be added to contract duration.

Option 5: Sea Turtle Trawling 15 days. No additional time added to contract duration if awarded.

Dredging and beach placement option are subject to environmental windows for swimming and nesting sea turtles.

Period of Performance: Complete the entire work ready for use not later than 120 calendar days after the date the Contractor receives the Notice to Proceed.

Completion time for Options 1-5 is 14 calendar days.

In accordance with FAR 36.204(g), the estimated construction price range for this project is: Between $5,000,000 and $10,000,000.

All construction performance must comply with the USACE Safety and Health Requirements Manual, (EM 385-1-1, and must also comply with all Federal, State and local laws, ordinances, codes and/or regulations.

The North American Industry Classification System code for this procurement is 237990 which has a small business size standard of $37 million.

The Product Service Code is Z1KB.

Small Businesses are reminded under FAR 52.219-14, Limitations on Subcontracting, (DEVIATION 2021-O0008), (3) General construction: Firm will not pay more than 85% of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count toward the 85% subcontract amount that cannot be exceeded.

Prior Government contract work is not required for submitting a response to this announcement.

Contractor should demonstrate construction experience as a prime contractor working on Dredged Material Placement Areas. Contractor should observe the typical wet conditions associated with Dredged Material Placement Areas.

Contractor should expect to use equipment with low ground pressure due to the soft/wet material in which the equipment will be operating.

Bonding Requirements: Performance and Payment Bonds are required within 5 Calendar Days after award and the contractor shall begin work within 10 Calendar days after issuance of the Notice to Proceed (NTP).

If the contractor fails to complete the work within the time specified, the contractor shall pay liquidated damages to the Government in the amount of $4,300.00 for each calendar day of delay until the work is completed or accepted.

FIRMS RESPONSE SHALL INCLUDE THE FOLLOWING INFORMATION:

1. Unique Entity Identifier (UEI) & Commercial and Government Entity (CAGE) (This information can be obtained from your System for Award Management (SAM) Registration at www.sam.gov ).

2. Name of firm w/ address, phone, fax, e-mail address, and point of contact.

3. Indicate whether your firm will submit a bid for this project if set-aside for Small Business (SB), 8(a) Small Business Development Program, Historically Underutilized Business Zones (HUB-Zone), Service-Disabled Veteran Owned Small Business (SDVOSB), Economically Disadvantaged (ED/Woman Owned (WO), Woman Owned (WO) Woman-Owned Small Business (WOSB).

4. Firm’s Joint Ventures (existing), including Mentor Protégés and teaming arrangement information is acceptable.

Qualifications: Responses to this source sought announcement shall indicate specialized experience and technical competence in:

a. Contractor must be experience in completing work outlined under the paragraph above for “Project Information.”

1. Firm’s capability to perform the magnitude and complexity outlined in the Scope of Work above or comparable work performed within the past 5 years):

2. Brief description of each project, customer name, and dollar value of the project)– provide at least 3 examples.

3. Firm’s Bonding Capacity (Bid Bond (20% of total bid amount), Performance and Payment Bond (100% of the contract amount) bonding level per contract and aggregate construction bonding level, both expressed in dollars.

Firms responding to this announcement, who fail to provide ALL required information requested and outlined above, may be excluded from further consideration in the review and analysis for acquisition strategy determination.

Anticipated solicitation issuance date is on or about June 2026, and the estimated proposal/bid due date will be on or about July 2026. Estimated award on or about date is September 2026.The official synopsis citing the solicitation number will be issued on Procurement Integrated Enterprise Environment (PIEE) https://piee.eb.mil/ inviting firms to register electronically to receive a copy of the solicitation when it is issued.

Interested Firm’s shall respond to this announcement no later than February 4, 2026, at 10:00 AM Local Time. All interested firms must be registered in SAM.gov to be eligible for award of Government contracts.

Email your response to Ms. Lillie Johnson at Lillie.S.johnson@usace.army.mil and Ms. Joycelyn Rodgers at Joycelyn.R.Rodgers@usace.army.mil.

http://www.sam.gov/ https://piee.eb.mil/ mailto:Lillie.S.johnson@usace.army.mil mailto:Joycelyn.R.Rodgers@usace.army.mil.