Attachment_1_-_SJC___MRG-EV_Elevator_Load_Testing_Section_C_PWS_v0.docx

DOCX document 42 KB Posted

Attached to
SJCP El Vado and Heron Elevator Load Testing Servi Federal contract opportunity
Solicitation number
140R4023Q0006
Issued by
Department of the Interior Bureau of Reclamation

View the file

Other files for this federal contract opportunity

Other files attached to SJCP El Vado and Heron Elevator Load Testing Servi, newest first.
File Type Posted
Sol_140R4023Q0006_Amd_0002.pdf PDF
Sol_140R4023Q0006_Amd_0001.pdf PDF
Attachment_5_-_Site_Visit_information_0001.docx DOCX document
Attachment_3-_Site_Maps.pdf PDF
Attachment_2_-_Price_Schedule_SJC___MRG-EV_Elevator_Load_Testing.docx DOCX document
Attachment_4_-_Wage_Rate___2015-5451_Dated_7-19-2022.pdf PDF
Sol_140R4023Q0006.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SJC Elevator Load Testing Services Performance Work Statement SJCP El Vado and Heron Elevator Load Testing Services Part 1 – General Information

1.0 Abbreviations, Acronyms, and Definitions

The following abbreviations and acronyms are used throughout this performance work statement:

AAO -Albuquerque Area Office (BOR)
ASME -American Society of Mechanical Engineers
BOR -Bureau of Reclamation (USBR)
CFD -Chama Field Division
CO -Contracting Officer
COR -Contracting Officer's Representative
FAR -Federal Acquisition Regulation
GFM -Government Furnished Materials
MDT -Mountain Daylight Time
NAICS -North American Industry Classification System
NEIEP -National Elevator Industry Educational Program
NTPNotice to Proceed
OSHA -Occupational Safety and Health Administration
PWS -Performance Work Statement
UCB -Upper Colorado Basin (Interior Region 7, Reclamation)
U.S.D.O.I. -United States Department of the Interior
1.1Background

The Government has determined that El Vado and Heron reservoirs facility elevators require system loading testing by a qualified elevator technician as defined by ASME QE1.1. The Load Test shall include performing and supplying the weights and preparing a final report for each site to be used by the Government and Government contractor performing the elevator inspections. Elevator load test is 500 lbs. representing a 2-person capacity.

1.2 North American Industry Classification System (NAICS)

The NAICS for this work is 541350 – Building inspection services.

1.3 Site Visit

Reclamation plans to hold a site visit for perspective Offerors on Thursday, November 27, 2021 at 11:00 AM DST.

1.4 Location and Hours of Operations

The Reclamation’s Chama Field Division facility is located at 193 North Pinon Drive, P.O. Box 426, Chama, New Mexico 87520 in Rio Arriba County at Latitude 36º 55’ 02.0” and Longitude 106º 34’ 42.6”. Chama Field Division facility standard business hours are Monday through Friday from 07:30 AM to 3:30 PM MST except Federal Holidays. Reclamation is a smoke, drug, and alcohol free facility.

1.4.1 Facility Access and Deliveries

Contractor shall inform the CO and COR a minimum of 5 working days prior to mobilizing personnel, equipment, and materials/supplies to the project site. In addition, if the Contractor would like to have materials/components directed shipped to the project site, the Contractor shall notify Mr. Bill Russom a minimum of 5 working days prior to the delivery of materials/components to arrange temporary storage for this project. The Contractor shall provide Mr. Bill Russom the following: a list of items to arrive, the shipper/carrier information, and estimated day and time of delivery to project site. Dean contract information is as follows:

William (Bill) Russom, Facility Manager Bureau of Reclamation Chama Field Division 193 North Pinon Drive P.O. Box 426 Chama, New Mexico 87520

(575) 756-2175 WRussom@usbr.gov

El Vado is located in Rio Arriba county New Mexico at latitude 36° 35’ 35.3”N, longitude -106° 44’ 01.9” W is approximately 16.8 miles southwest of Tierra Amarilla, New Mexico at the junction of US 84 and County Road 112. Heron is located in Rio Arriba county New Mexico at latitude 36° 39’ 56.6”N, longitude -106° 42’ 15.1” W is approximately 10.3 miles southwest of Los Ojos, New Mexico at the junction of US 84 and County 95.

1.5 Scope and Objectives

Scope of this procurement: The Government shall provide access to the facilities when determined to be acceptable within the current operation activities. The Contractor shall provide all labor, equipment, supplies, materials, test weights, etc. to make whole the requirements for load testing as detailed under ASME A17.1 and report documentation.

The Objective of this procurement is to perform load testing at two Government facilities in accordance with ASME A17.1 and provide written documentation of such load testing inspections.

1.7 Standards

The PWS shall following the standard set-forth in the following paragraphs.

1.7.1American Society for Mechanical Engineers (ASME):
ASME A17.1 (2019)Safety Code for Elevators and Escalators
ASME A17.1 (2016)Handbook on Safety Code for Elevators and Escalators
ASME A17.2 (2017)Guide for Inspection of Elevators, Escalators, and Moving Walks
ASME A17.3 (2017)Safety Code for Existing Elevators and Escalators
ASME A17.4 (2015)Guide for Emergency Personnel
ASME A17.6 (2017)Standard for Elevator Suspension, Compensation, and Governor Systems
ASME QEI-1 (2018)Standard for the Qualification of Elevator Inspectors
1.7.2Bureau of Reclamation (USBR):
Cleaning Manual 2019Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition, posted at http://www.usbr.gov/mussels/prevention.
RSHS 2020Reclamation Safety and Health Standards including revisions posted at https://www.usbr.gov/safety/rshs/index.html
1.7.3National Association of Elevator Contractors (NAEC)
NAEC/ASME QEI -1 StandardQualified Elevator Inspector - 1 Standard
1.7.4Occupational Safety and Health Administration (OSHA)
OSHA 1917.116Elevators and escalators
1.8Travel Expenses

The Contractor shall be reimbursed for travel expenses if authorized by the Contracting Officer in accordance with rates provided within the Federal Travel Regulation (FTR) and applicable General & Administrative Costs (G&A).

1.9 Submittals

Submit the following for Government review or approval:

· Prepare in English.

· Label with contract number and title including Required Submittal Number (RSN).

· Measurement Units: US Customary Units.

· Provide a unique transmittal tracking number for each submittal.

· Drawings and sketches shall following the U.S. National CAD Standard, Version 6.

· Required certifications shall be performed by a registered professional.

· Manufacturer’s certifications shall be signed by authorized representative.

· Review of submittals:

· Time required: The Government will require a minimum of 3 days to review each submittal or resubmittal, unless otherwise specified.

· Excess Time: Should the Government require additional review time, the CO may extend the contract completion date to allow completion of work. Time extension will be to the extent that the excess review time caused delay to contract completion.

· Submit the following for Government approval or review.

· Submittal Types: A – Action requiring Government approval and I – Informational requires Government written receipt.

· Submit to COR one electronic (eMail) copy for review.

Submittal Table

RSN
Required Submittal and Description
Due Date or Delivery Time
Type
S1
Project Schedule shall include the following key milestones:

· Proposed dates for mobilization to project site.

· Proposed steps and time for performing elevator load testing inspection steps.

· Proposed date for delivery of draft and final load test inspection reports.

Within21 days after contract award.
A
S2
Description of items/materials to be used for weight tests.
Within 21 Days after contract award.
A
S3
Site Specific Safety Plan and JHAs
Within 14 Days before mobilizing to project site
A
S4
Final Load Test Inspection Reports
Provide with Final Payment Invoice
I

PART 2 – WORK REQUIREMENTS

2.0 Tasks for Schedule A (Periodical Inspections with Load Testing) Under Schedule A the following work tasks are to be performed:

· Inspect the governor trip speed and pull-through calibration

· Test the buffer at rated load and rated speed

· Test the brake at 125% of rated load

· Test emergency stopping distance

· Inspect and test normal, final, and emergency stopping devices

· Test inner landing zone for static control elevators

· Inspect operation of fire emergency service, emergency backup power and power door systems

· Load the elevator with (500 U.S. Pounds) weights equal to its rated capacity

· House keeping and site cleanup includes removal all debris and unused items from all areas associated with inspections activities

· Submit final inspection reports for each site (El Vado and Heron) in one non-bound copy and one electrical document in Adobe “pdf” format

· Comply with Safety Standards

2.1 Government Furnished Materials/Equipment (GFM/E)

The Government will not be suppling any materials or equipment under these specifications. The Contractor maybe given access to 110 volt, 20 amp electrical circuit, potable water source, and restrooms if left in equal or better condition.

PART 3 – CERTIFICATIONS

3.0 Qualified Elevator Inspector

The QEI certification shall ensure inspectors have the skills, knowledge and education to safeguard the public by confirming elevators, escalators, and other conveyances are code compliant and operating safely.

3.0.1 Qualification & Experience Requirements

The following are the minimum criteria to accept a resume of a Qualified Elevator Inspector under this specifications:

· The QEI shall comply with the requirements in ASME QEI-1 Standard.

· The QEI shall be certified by the National Elevator Industry Educational Program or equal.

· The QEI shall have a minimum of 2-years of documented education.

· The QEI shall have a minimum of 3-years experience in mechanical and electrical aspects of elevator industry and recognized as a person meeting the A17.1 Code definition of “Elevator Personnel” performing and assistance in testing as specified in A17.1 Section 8.10 or 8.11 and A18.1 standards. Education can be used to reduce one year of experience.

3.0.2 Code of Ethics

The QEI and Supervisors shall have the following fundamental principles:

· Inspectors and supervisors shall uphold and advance the competence, integrity, honor, and prestige of the inspection profession through the following:

· Using their knowledge and skills for the enhancement of human welfare.

· Being honest and impartial, and serving with fidelity the public, their employers and clients; and QEI Program.

· Fundamental Standards:

· Inspectors and inspection supervisors shall hold paramount the safety, health and welfare of the public in accordance with the QEI-1 Standards.

· Inspectors and supervisors shall perform services only in the areas of their competence.

· Inspectors and supervisors shall continue their professional development throughout their careers and shall provide opportunities for the professional and ethical development of those inspectors under their supervision.

· Inspectors and supervisors shall act professionally with Government and public personnel.

· Inspectors and supervisors shall build their professional reputation on the merit of their services.

· Inspectors and supervisors shall issue public statements and written reports in an objective, impartial and truthful manner.

· Inspectors and supervisors shall consider environmental impacts in the performance of their professional duties.

PART 4 - QUALITY ASSURANCE SURVEILLANCE PLAN

4.1 Quality Assurance Surveillance Plan (QASP)

The Government will perform Quality Assurance (QA) activities under this PWS according to the following QASP. After contract award and during the Pre-Meeting, the QASP will be reviewed, if required modified/changed, and signed by Contractor and Government personnel listed.

Task Order Title:
SJC El Vado and Heron Elevator Inspection Services

Contractor:

Contractor’s Representative:
SignatureDate
Contracting Officer
SignatureDate
Contracting Officer’s Representative
SignatureDate
Onsite Government’s Representative
SignatureDate

Signature Date

Task or Activity
Description
Responsible Person
Inspection Period
Place
Inspection Method
Project Schedule
Contractor’s ability to meet schedule
CO & COR
Review of Baseline Project Schedule
AAO or CFD
Direct or Observation
Site Visits and Meetings
Contractor’s ability to be on schedule, coordinate with attendees, and engage in the conversations
CO & COR
Per meeting or Site Visit
Project Site or AAO
Direct or Observation
Safety
Contractor’s ability to meet Safety requirements
COR or OGR
Daily
Project Site
Observation or Random
Reports
Contractor’s ability to prepare and finalize Inspection Reports timely
CO & COR
Meeting schedules
AAO or CFD
Direct or Observation

Definitions for Methods of Surveillance The following four surveillance methods will be consider during the period of performance of this PWS:

· Comments is defined as feedback or complaints provided by customers

· Direct is defined as an activity onsite or reviewing documents

· Observation is defined as feedback from the CO and COR during performance of work activities

· Random is defined as unscheduled site visits or data reviews