Milestone Schedule

Milestone #MilestonesExit Citeria /DeliverablesDue
DatePaymentFundedCLIN
SUBCLINACRN
1Phase 1 kick-offPhase 1 kick-off slide deckend of month 1
2Signature summary, development and test planSignature summary, development and test planend of month 1
3Mid-phase testing progressTesting progress reportend of month 3
4Signature sensitivity and specficity reportSignature sensitivity and specficity reportend of month 6
Sub-Total Phase 1$ - 0$ - 0
5Phase 2 kick-offPhase 2 kick-off slide deckend of month 7$ - 0TBDTBD
6Prototype system requirements review (SRR)SRR reportend of month 7$ - 0TBDTBD
7Prototype preliminary design review (PDR)PDR reportend of month 10$ - 0TBDTBD
8Prototype critical design review (CDR)CDR Reportend of month 13
9Final technical reportFinal Reportend of month 18
Sub-Total Phase 2$ - 0
Total Agreement$ - 0$ - 0
*Tasks and targets are keyed to Attachment 1 - Task Description Document
HIGHLIGHTED SECTION NOT TO BE FILLED OUT BY PROPOSERS

Attachment 3 - Schedule of Milestones and Payments

Summary of Deliverables:

Phase 1 kickoff slide deck providing background on the performer, signature(s) under study, and technical approach to meet Phase 1 objectives, risks and risk mitigations, and schedule.

Phase 1 signature summary, development and test plan that details the signature(s) under investigation and the plan by which performance metrics will be met.

Phase 1 mid-period testing progress report for month 5 indicating progress in achieving DO metrics Phase 1 final report of signature sensitivity and specificity for month 9 indicating DO metrics can be achieved in a sensor that would be realized in Phase 2 Phase 2 kickoff slide deck summarizing technical approach to meet Phase 2 objectives, including risks and risk mitigations and schedule.

Prototype system requirements review for month 10 that allocates performance and suitability goals of the sensor to proposed sensor components Prototype preliminary design review report for month 12 that provides an initial design of the sensor and all key components that when integrated, achieves DO performance and suitability goals for the proposed use case Prototype critical design review report for month 14 that provides a final design of the sensor and all key components that when integrated, achieves DO performance and suitability goals for the proposed use case Final report summarizing the assessment of sensor performance and 3 working prototype sensors for month 18 Monthly written technical progress reports