Attachment 1 Schedule of Items - 1240LQ23Q0109 Tomboy Mine Preliminary Inspection.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- Tomboy Mine Preliminary Inspection
- Solicitation number
- 1240LQ23Q0109
- Issued by
-
Department of Agriculture Forest Service
About this file
This attachment provides the schedule of items for Request for Quotation number 1240LQ23Q0109 issued by the Department of Agriculture Forest Service. The RFQ seeks quotations for preliminary assessment and site inspection reports for the Tomboy Mine and optional work at the Victor Mine. For the Tomboy Mine, the schedule includes lump sum line items for preparation of health and safety plans and reports, evaluation of existing data, field work planning and execution including travel, sampling and testing, and risk assessment and standards comparison. An additional lump sum line item is provided for the final report. Optional identical line items are included for the Victor Mine, with a note that field work for both sites would be combined into a single trip if the optional items are awarded. No pricing is included in the schedule.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1
| Schedule of Items |
| RFQ 1240LQ23Q0109 Tomboy Mine Preliminary Assessment/Site Inspection Reports |
| Site | Task # | Deliverable | Quantity | Unit | Cost | |
| Tomboy Mine (BASE) | 1 | Preparation of HASP and QAPP, Evaluation of Existing | ||||
| Data, and Preparation of FSP | 1 | Lump Sum | ||||
| 2(a) | Performing Field Work Plans (Including conducting field work and all associated travel costs) | 1 | Lump Sum | |||
| 2(b) | Sampling and Testing | 1 | Lump Sum | |||
| 3 | Risk Evaluation and Standards/Benchmarks Comparison | |||||
| Assessment Tables | 1 | Lump Sum | ||||
| 4(a) | Final PA/SI Report | 1 | Lump Sum | |||
| Victor Mine (OPTIONAL) | 1 | Preparation of HASP and QAPP, Evaluation of Existing Data, and Preparation of FSP | 1 | Lump Sum | ||
| 2(a) | Performing Field Work Plans (Including conducting field work and all associated travel costs) Note: if awarded optional items, site visits and field work for Tomboy and Victor sites shall be completed in a single field event to reduce travel costs. | 1 | Lump Sum | |||
| 2(b) | Sampling and Testing | 1 | Lump Sum | |||
| 3 | Risk Evaluation and Standards/Benchmarks Comparison Assessment Tables | 1 | Lump Sum | |||
| 4(a) | Final PA/SI Report | 1 | Lump Sum |
| Total (BASE) | $0.00 |
| Total (OPTIONAL) | $0.00 |
| Total (BASE and OPTIONAL) | $0.00 |
File details come from the government source that posted it. Updated .