Attachment 1 QASP.pdf
PDF 240 KB Posted
- Attached to
- Flank Speed Support Service
- Solicitation number
- N0018924R0005
About this file
This Quality Assurance Surveillance Plan outlines performance requirements and monitoring methods for the Flank Speed Support Service contract to provide non-personal contractor support services to the Naval Network Warfare Command. Key performance elements include progress reports submitted monthly with status of support provided to complete missions, a contractor quality assurance plan within 30 days of start and updated annually, monthly activity reports by the 10th of each month, and timely and accurate monthly invoices. Performance will be monitored through reviews, inspections, and assessments conducted by a technical lead and Contracting Officer's Representative. Contractors must meet acceptable quality levels for timely and accurate deliverables to receive a satisfactory performance rating and incentive payments. Failure to do so could result in contract termination or loss of future awards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Flank Speed QA.pdf | ||
| Flank Speed QA.pdf | ||
| Attachment 4 Past Performance Report Form Amend 01.docx | DOCX document | |
| N0018924R0005 P0001.pdf | ||
| Attachment 4 Past Performance Report Form.docx | DOCX document | |
| N0018924R0005.pdf | ||
| Attachment 2 DD254.pdf | ||
| Attachment 3 Past Performance Information Form.docx | DOCX document | |
| Attachment 5 WD 2015-4341 rev 25 12-26-2023.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVAL NETWORK WARFARE COMMAND (NETWARCOM)
Operation Flank Speed
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
1.0 PURPOSE
This Quality Assurance Surveillance Plan (QASP) is a Government developed and applied document used to make sure that systematic quality assurance methods are used in the administration of the
Performance Based Service Contract (PBSC) standards included in this contract. The intent is to ensure that the Contractor performs in accordance with performance metrics set forth in the contract documents, that the Government receives the quality of services called for in the contract and that the Government only pays for the acceptable level of services received.
2.0 AUTHORITY
Authority for issuance of this QASP is provided under FAR 52-212-4(a), Inspection/Acceptance, which provides for inspections and acceptance of the articles, services, and documentation called for in the contract to be accomplished by the Contracting Officer or their duly authorized representative.
3.0 SCOPE
The Contractor, and not the Government, is responsible for management and quality control actions necessary to meet quality standards set forth by the contract. The QASP is put in place to provide
Government surveillance oversight of the Contractor’s quality control efforts to assure that they are timely, effective and are delivering the results specified in the contract. The QASP is not a part of the contract nor is it intended to duplicate the Contractor’s Management Plan. The Government may provide the Contractor an information copy of the QASP as an Attachment to the solicitation to support the
Contractor’s efforts in developing its plan for maintaining the levels of quality anticipated to be delivered under the terms of the contract.
4.0 RESPONSIBILITIES
The Government resources shall have responsibilities for the implementation of this QASP as follows:
Contracting Officer – The Contracting Officer ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the contract and safeguards the interests of the United States in the contractual relationship. It is the Contracting Officer that assures the Contractor receives impartial, fair and equitable treatment under the contract. The
Contracting Officer is ultimately responsible for the final determination of the adequacy of the
Contractor’s performance.
Contracting Officer’s Representative (COR) – An individual designated in writing by the
Contracting Officer to act as his authorized representative to assist in administering a contract.
The source and authority for the COR is the Contracting Officer. COR limitations are contained in the written letter of appointment.
5.0 METHODS OF QA SURVEILLANCE
The below listed methods of surveillance shall be used in the administration of this QASP. The QASP
Matrix (Attachment 1) describes the methods of surveillance that shall be used to monitor the services and deliverables to be provided under the contract.
Random Checks/Inspections – Random checks will be conducted to ensure compliance with the
Standard Operating Procedures (SOP). The COR or Technical Point of Contact (TPOC) will conduct the random monitoring.
6.0 DOCUMENTATION
The COR will maintain a complete Quality Assurance Surveillance file. The file shall contain such documents as copies of all receiving reports, evaluations, recommendations, and any other actions related to the Government’s performance of the quality assurance function. All such records will be retained for the life of this contract. At a minimum, the Quality Assurance Surveillance file shall contain:
Copies of letters of appointment for the COR
A copy of the contract and all modifications
A copy of the QASP and all subsequent revisions
The names and titles of individuals on the contract administration team
A record of all accepted receiving reports, required documentation with the submission of each receiving report and reviews.
Memoranda for the record or minutes of any pre-performance meetings or conferences.
Memoranda for the record or minutes of any meetings or discussions with the contractor, or others, pertaining to the contract or contract performance or changes to the PWS.
7.0 ANALYSIS OF CONTRACTOR PERFORMANCE
The analysis of contractor performance shall be conducted at the end of each month and serves to provide a summary of the Contractor’s performance to the Contracting Officer and the Contractor. Overall performance is important in determining whether to increase, decrease or maintain the current level of surveillance and/or whether to initiate corrective action to bring the Contractor’s work up to the standards of the specification.
QASP MATRIX
Performance
Element Performance Requirement
Surveillance
Method Frequency
Acceptable
Quality Level
(AQL)
Procedures to be taken when performance standards are not met
Progress Review
Reports must include status of support provided to NNWC in completion of assigned missions (deployments and sustainment) in support of NNWC operations and associated tasks specific to PWS.
Review by
Technical Lead and/or COR.
Monthly
95% of reports submitted on time and without rework due to errors.
FAR Clause 52.212-4(a)
Inspection/Acceptance
Contractor Quality
Assurance Plan
Contractor Quality Assurance Plan are submitted as prescribed in the PWS.
Overall contract performance of sufficient quality to earn a satisfactory or higher rating.
Assessment by
Technical Lead provided to, and reviewed by the
COR
Due within 30 days of POP start and updated annually
98% of reports submitted on time and without rework due to errors.
FAR Clause 52.212-4(a)
Inspection/Acceptance
Monthly Status
Reports
Monthly Activity reports are submitted as prescribed in the PWS. Reports provide any issues and concerns that need to be resolved by the COR as contained in the PWS.
Inspection by the
COR/TPOC
By the 10th of each Month
95% of reports submitted on time and without rework due to errors. FAR Clause 52.212-4(a)
Inspection/Acceptance
Invoicing Monthly invoices per contract procedures are timely and accurate.
Review and acceptance of invoice by designated representative of
COR.
Monthly
99% of reports submitted on time and without rework due to errors. FAR Clause 52.212-4(a)
Inspection/Acceptance
Overall Contract
Performance
Overall contract performance of sufficient quality to earn a satisfactory or higher rating
Assessment by
Technical Lead provided to, and reviewed by the
COR
Annual or within one month of end of performance as directed by the
COR.
All performance elements and overall performance rated as satisfactory.
FAR Clause 52.212-4(a)
Inspection/Acceptance
Combatting
Trafficking in
Persons
Contractor shall ensure compliance with FAR 52.222-50 – Combatting
Trafficking in Persons
The Contracting
Officer will review as needed.
As needed
100% Remedies as available to the government, to include those in FAR
52.222-50
Mandatory Annual
Training
Completion of annual training as directed by Department of Defense.
The Contracting
Officer will review as needed.
As needed
100% FAR Clause 52.212-4(a)
Inspection/Acceptance
If performance is within acceptable levels, it will be considered to be satisfactory. If not, overall performance may be considered unsatisfactory.
INCENTIVES/DISINCENTIVES:
The COR makes an annual report on Contractor Performance (CPARS or other annual report). The Contractor’s failure to achieve satisfactory performance under the contract, reflected in the COR’s annual report, may result in termination of the contract and may also result in the loss of future Government contracts. Additionally, the
Contractor’s failure to achieve satisfactory performance under the contract may also result in the non-exercise of available options.
For each item that does not meet acceptable levels, the Government may issue a Contract Discrepancy Report (CDR).
CDRs will be forwarded to the Contracting Officer with a copy sent to the Contractor. The Contractor must reply in writing within 5 days of receipt identifying how future occurrences of the problem will be prevented. Based upon the
Contractor’s past performance and plan to solve the problem, the Contracting Officer will determine if any further action will be taken.
File details come from the government source that posted it. Updated .