PERFORMANCE WORK STATEMENT (PWS)

FOR

Ducting Cleaning Service for Building 4280- Weather Flight

1.0 General:

1.1 Scope: The contractor shall visually inspect and clean the HVAC system in building 4280. The contractor shall perform the services specified here in accordance with the current published standards of the National Air Duct Cleaners Association.

1.1.1 Objectives The contractor shall perform a one-time service, identifying damage discovered through non-destructive inspection of the HVAC system in building 4280, providing a report of those findings to the Contracting Officer, and cleaning the HVAC system in building 4280. The HVAC system includes any interior surface of the facility’s air distribution system for conditioned spaces and/or occupied zones. This includes the entire heating, air-conditioning and ventilation system from the points where the air enters the system to the points where the air is discharged from the system. The return air grilles, return air ducts (except ceiling plenums and mechanical room) to the air handling unit (AHU), the interior surfaces of the AHU, mixing box, coil compartment, condensate drain pans, supply air ducts, fans, fan housing, fan blades, air wash systems, turning vales, filter housings, reheat coils, and supply diffusers are all considered part of the HVAC system. The HVAC system also includes other components such as dedicated exhaust and ventilation components that make up air systems, to include separate exhaust, ductwork, and grilles located in the restrooms.

1.2 Background: The facility has not had a duct cleaning since being built in 2004. There have not been any indoor air quality assessments or environmental reports in the building. All ductwork in the building requires a one-time cleaning. Digital mechanical drawings of the building have been included as an attachment to this PWS, and hard copies of the buildings drawing set will be made available upon award of the contract.

1.3 Period of Performance (PoP): The Period of Performance shall be one month to complete after the award of contract.

1.4 General Information:

1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0700-1630 on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Camp Blanding Joint Training Site (CBJTS), Inside Building 4280. At all times, the contractor shall maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

Down Mondays: The base is closed every other Monday. The contractor shall submit in writing a list of all personnel that are needed to perform services on these days. The names need to be submitted by Thursday each week prior to the down Monday. All personnel on the list must have a DBIDS card to enter the base.

1.4.1.1 Telework: The Government does not permit the contractor to telework in support of this requirement.

1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation, including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

1.4.2 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days:

1.4.2.1 New Year’s Day: January 1st

1.4.2.2 Martin Luther King, Jr.’s Birthday

1.4.2.3 President’s Day

1.4.2.4 Memorial Day

1.4.2.5 Juneteenth National Independence Day: June 19th

1.4.2.6 Independence Day: July 4th

1.4.2.7 Labor Day

1.4.2.8 Indigenous People’s Day

1.4.2.9 Veteran’s Day: November 11th

1.4.2.10 Thanksgiving Day

1.4.2.11 Christmas Day: December 25th

1.4.3 Quality Control (QC): Reserved.

1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).

1.4.5 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1. The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

2. The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and full names of employees and subcontractor employees needing access to the base including their driver’s license number. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, and valid vehicle insurance certificate to obtain a vehicle pass.

3. During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

4. Reserved.

5. Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

6. Failure to comply with these requirements may result in withholding of final payment.

1.4.5.1. Reserved.

1.4.5.1.1 Reserved.

1.4.5.1.2 Reserved.

1.4.5.1.3 Reserved.

1.4.5.1.4 Reserved.

1.4.5.1.5 Reserved.

1.4.5.1.6 Reserved.

1.4.5.2 For contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Air Force Instruction (AFI) 10-245, AFI 31-101 and Air Force Manual (AFMAN) 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative)

1.4.5.3 Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR, MSgt Kristina Gatson Harmon, kristina.gatson_harmon@us.af.mil within 15 calendar days after completion of training by each employee or subcontractor personnel.

1.4.5.4 Reserved.

1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.5.6 Reserved.

1.4.5.7 Reserved.

1.4.5.8 Reserved.

1.4.5.9 Reserved.

1.4.5.10 Reserved.

1.4.5.11 Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/Signature Managers/Coordinators will provide OPSEC training or training materials to contract employees within 30 days of employees’ initial assignment to the contract and prior to having access to any critical information (CI) and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) is located on the ADLS website and refresher OPSEC training is conducted annually (at Commander's Call). The contractor shall submit certificates of completion for each contractor employee to the COR, MSgt Kristina Gatson Harmon, within 15 calendar days after completion of training.

1.4.5.12 Reserved.

1.4.5.13 Reserved.

1.4.5.14 Reserved.

1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.7 Special Qualifications: The contractor must me experienced in HVAC cleaning projects of similar size and complexity. The contractor shall employ an NADCA-certified Air Systems Cleaning Specialist or NADCA-certified Ventilation Inspector responsible for project oversight. The contractor shall provide proof that all employees possess all required licenses for professional duct cleaning in the state of Florida. The contractor shall comply with all applicable Federal, State, and local requirements for protecting the safety of the contractors’ employees, building occupants, and the environment. In particular, follow all applicable standards of the Occupational Safety and Heath Administration (OSHA) when working in accordance with this specification. The Contractor shall submit the Safety Data Sheets (SDS) for all products used for cleaning. These requirements do not include education or other qualifications for the position in which the contractor employee is performing, dress codes, or other information. (NOTE: The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified, and otherwise qualified to provide services.)

1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5. The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, MSgt Kristina Gatson Harmon, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification uniforms distinguishing themselves as such. The uniform shall have the company name displayed. It should be display of the work vehicles as well.

1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.

1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero-tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.

1.4.12 Reserved.

1.4.13 Reserved.

1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.15 Reserved.

2.0 Definitions and Acronyms:

2.1 Definitions:

2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.

2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.

2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of the end product or service shall meet contract requirements.

2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 Acronyms:

ACRAir Cleaning and Restoration
ASCSAir Systems Cleaning Specialist
AT/OPSECAntiterrorism/Operational Security
CBJTSCamp Blanding Joint Training SITE
CMContract Manager
CORContracting Officer Representative
DFARSDefense Federal Acquisition Regulation Supplement
DoDDepartment of Defense
EPAEnvironmental Protection Agency
FARFederal Acquisition Regulation
FLANGFlorida Air National Guard
GFP/M/E/SGovernment Furnished Property/Material/Equipment/Services
HEPAHigh Efficiency Particulate Air
HQDAHeadquarters, Department of the Army
HSPDHomeland Security Presidential Directive
IAInformation Assurance
ISInformation System(s)
KOContracting Officer
NGBNational Guard Bureau
NADCANational Air Duct Cleaners Association
NAIMANorth American Insulation Manufacturer’s Association
NFPANational Fire Protection Association
OCIOrganizational Conflict of Interest
OSHAOccupational Safety and Health Agency
PCEParticulate Collection Equipment
POCPoint of Contact
PPEPersonal Protective Equipment
PRSPerformance Requirements Summary
PWSPerformance Work Statement
QAQuality Assurance
QASPQuality Assurance Surveillance Plan
QCQuality Control
QCPQuality Control Program
SCRService Contract Reporting
SDSSafety Data Sheets
SMACNAThe Sheet Metal and Air Conditioning Contractors’ National
Association
SSNSocial Security Number
TETechnical Exhibit

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:

3.1 Property: The Government will furnish the necessary workspace for the contractor to perform services outlined in this PWS to include break space and restrooms.

3.2 Materials: None.

3.3 Equipment: None.

3.4 Services: None.

3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

4.2 Secret Facility Clearance: Reserved.

4.3 Contractor Security Clearance: Reserved.

5.0 Requirements: The contractor shall perform the services specified here in accordance with the current published standards of the National Air Duct Cleaners Association (NADCA, NADCA ASCS, NADCA ACR and NADCA HVAC Inspection Manual). All terms in this PWS are defined as stated in the NADCA Standards. Follow NADCA Standards without modification of deviation.

5.1 Preparation

5.1.1 Prior to the commencement of any cleaning work, the contractor shall perform a visual inspection of the HVAC system in the presence of the COR to determine appropriate methods, tools, and equipment required to satisfactorily complete this project. Cleanliness inspection should include air handling units, and representative areas of HVAC system components and ductwork. Notify the Contracting Officer 10 days prior to the planned inspection. As part of the evaluation, record photographs of each inspection location to document the “as found” condition prior to cleaning. Document damaged system components found during the inspection and submit to the COR clearly labeled “Record of Existing Conditions.”

5.1.2 HVAC System Evaluation shall be conducted without negatively impacting indoor environment through excessive disruption of settled dust, microbial amplification or other debris. In cases where contamination is suspected, and/or in sensitive environments where even small amounts of contaminants may be of concern, implement environmental engineering control measures.

5.2 General HVAC System Cleaning Requirements - The contractor shall:

5.2.1 Collect debris removed during cleaning and take precautions to ensure the debris is not otherwise dispersed outside the HVAC system during the cleaning process.

5.2.2 Where the Particulate Collection Equipment (PCE) is exhausting inside the building, use HEPA filtration with 99.97 percent collection efficiency for 0.3-micron size (or greater). When the PCE is exhausting outside the building, undertake mechanical cleaning operations only with PCE, including adequate filtration to contain debris removed from the HVAC system. When the PCE is exhausting outside the building, take precautions to locate the equipment down wind and away from all air intakes and other points of entry into the building.

5.2.3 Take all reasonable measures to control offensive odors and/or mist vapors during the cleaning process.

5.2.4 Employ cleaning methods such that all HVAC system components are Visibly Clean as defined in applicable standards. Upon completion, return all components to those settings recoded just prior to cleaning operations.

5.2.5 Mark the position of dampers and any air-directional mechanical devices inside the HVAC system prior to cleaning and, upon completion, restore to their marked position.

5.2.6 Utilize service openings as required for proper cleaning, at various points of the HVAC system for physical and mechanical entry, and inspection. Utilize the existing service openings already installed in the HVAC system where possible. Create other openings where needed, created and resealed in conformance with NADCA Standard 05. Place closures so they do not significantly hinder, restrict, alter the air-flow within the system, or compromise the structural integrity of the system. Properly insulate closures to prevent heat loss/gain or condensation on surfaces within the system. Conform construction techniques used in the creation of openings to requirements of applicable building and fire codes, and applicable NFPA, SMACNA and NADCA Standards. Cutting service openings into flexible duct is not permitted. Disconnect flexible duct at the ends as needed for proper cleaning and inspection. Reseal rigid fiber glass ductboard duct systems in accordance with NAIMA recommended practices; NAIMA AH112, NAIMA AH122, and NAIMA AH127. Only closure techniques which comply with UL 181, UL 181A, or UL 181B are suitable for fiber glass duct system closures. Provide access doors for openings that need to be re-opened for future inspection or remediation. Refer to Section 23 31 13.00 40 – Metal Ducts for access doors. Clearly mark all service openings, capable of being re-opened for future inspection or remediation, and report their location in project report documents.

5.2.7 Carefully remove and reinstall ceiling sections to gain access to HVAC systems during the cleaning process. Replace any damaged ceiling sections caused by the removal at no cost to the Government.

5.2.8 Clean all air distribution devices (registers, grilles, and diffusers).

5.2.9 Ensure that supply, return, and exhaust fans and blowers are thoroughly cleaned. Areas for cleaning include blowers, fan housings, plenums (except open ceiling supply and return plenums), scrolls, blades, or vanes, shafts, baffles, dampers and drive assemblies. Remove all visible surface contamination deposits in accordance with NADCA Standards.

5.2.9.1 Clean all air handling unit (AHU) internal surfaces, components and condensate collectors and drains.

5.2.9.2 Assure that a suitable operative drainage system is in place prior to beginning wash down procedures.

5.2.9.3 Clean all coils and related components, including evaporator fins.

5.2.10 Clean duct systems – The contractor shall:

5.2.10.1 Create service openings in the system as necessary in order to accommodate cleaning of otherwise inaccessible areas.

5.2.10.2 Mechanically clean all duct systems to remove all visible contaminants, such that the systems are capable of passing NADCA Cleaning Verification Testing Standards.

5.2.10.3 Any exposed edges in internal duct lining within duct, including but not limited to interfaces with externally insulated duct, shall be fully protected, sealed and encapsulated to prevent future erosion.

5.2.11 Source Removal Cleaning methods. The contractor shall:

5.2.11.1 Clean the HVAC system using Source Removal mechanical cleaning methods designed to extract contaminants from within the HVAC system and safely remove contaminants from the facility. Select Source Removal methods which will render the HVAC System Visibly Clean and capable of passing NADCA cleaning verification methods standards, in accordance with all general requirements. Use no cleaning method, or combination of methods, which could potentially damage components of the HVAC system or negatively alter the integrity of the system.

5.2.11.2 Incorporate the use of vacuum collection devices that are operated continuously during cleaning for all methods used. Connect a vacuum device to the downstream end of the section being cleaned through a predetermined opening. Use a vacuum collection device of sufficient power to render all areas being cleaned under negative pressure, such that the containment of debris and the protection of the indoor environment is assured.

5.2.11.3 Equip all vacuum devices exhausting air inside the building, including hand-held vacuums and wet-vacuums, with HEPA filters (minimum efficiency).

5.2.11.4 Equip all vacuum devices exhausting air outside the facility with Particulate Collection including adequate filtration to contain debris removed from the HVAC system, in a manner that does not allow contaminants to re-enter the facility. Release of debris outdoors which violates any outdoor environmental standards, codes or regulations is not allowed.

5.2.11.5 All methods require mechanical agitation devices to dislodge debris adhered to interior HVAC system surfaces, such that debris may be safely conveyed to vacuum collection devices. Acceptable methods include those which will not potentially damage the integrity of the ductwork, nor damage porous surface materials such as liners inside the ductwork or system components.

5.2.12 Methods of Cleaning Fibrous Glass Insulated Components The contractor shall:

5.2.12.1 Thoroughly clean glass insulation elements present in any equipment or ductwork with HEPA vacuuming equipment. Clean while the HVAC system is under constant negative pressure, and not permitted to get wet in accordance with applicable NADCA and NAIMA standards and recommendations.

5.2.12.2 Do not use cleaning methods that cause damage to fibrous glass components or renders the system capable of passing Cleaning Verification Tests NADCA Standards.

5.2.12.3 Provide surface treatment for insulation for sections of internally-lined duct. Select and apply encapsulants, coatings, and insulation repair products to completely restore surface integrity of fibrous glass surfaces in accordance with applicable standards and manufacturer’s installation instructions.

5.2.13 Damaged Fibrous Glass Material

5.2.13.1 If there is any evidence of damage, deterioration, delamination, friable material, mold or fungus growth, or moisture such that fibrous glass materials cannot be restored by cleaning or resurfacing with an acceptable insulation repair coating, the contractor shall identify them to the Contracting Officer for replacement.

5.2.13.2 When requested or specified, remediate exposed damaged insulation in air handlers and/or ductwork requiring replacement.

5.2.13.3 If insulation is damaged as a result of this work under this specification, notify Contracting Officer and initiate a meeting with same to determine options for repair or replacement of insulation.

5.2.14 Replacement Material

5.2.14.1 If replacement of fiber glass materials is required, the contractor shall conform all materials to applicable industry codes and standards, including those of UL and SMACNA 1966.

5.2.14.2 Replacement of damaged insulation

5.2.15 Cleaning of Coils The contractor shall:

5.2.15.1 Use any cleaning method which renders the coil visibly clean and capable of passing NADCA Coil Cleaning Verification Standards. Coil drain pans are subject to Non-Porous Surfaces Cleaning Verification. Maintain operability of drain for the condensate at all times. Do not damage, displace, inhibit heat transfer, or cause erosion of the coil surface or fins, and conform to coil manufacturer recommendations when available. Thoroughly rinse coils with clean water to remove any latent residues.

5.2.16 Antimicrobial Agents and Coatings – The contractor shall:

5.2.16.1 Perform application of antimicrobial agents used to control the growth of fungal or bacteriological contaminants after the removal of surface deposits and debris.

5.2.16.2 Use only antimicrobial agents registered by the U.S. Environmental Protection Agency (EPA 402-F-91-102) (EPA 401-C-01-001) specifically for use within HVAC system.

5.2.16.3 Apply antimicrobial agents in strict accordance with manufacturer’s instructions.

5.2.16.4 Use only antimicrobial coating products, for both porous and no-porous surfaces, which are EPA registered, water soluble solutions with supporting efficacy data and SDS records.

5.2.16.5 Apply antimicrobial coatings according to manufacturer’s instructions. Spray coating directly onto interior ductwork surfaces, rather than “fog” downstream onto surfaces. Achieve a continuous film on the surface treated by the coating application and apply in strict accordance with manufacturer’s minimum millage surface application rate standards for effectiveness.

5.2.17 Cleanliness Verification

5.2.17.1 Verification of HVAC System cleanliness is determined after mechanical cleaning and before the application of any treatment or introduction of any treatment-related substance to the HVAC system, including antimicrobial agents and coatings.

5.2.17.2 The contractor shall visually inspect the HVAC system to ensure that no visible contaminants are present.

5.2.17.3 If no contaminants are evident through visual inspection, consider the HVAC system clean; however, further verification of the system cleanliness through wipe testing analysis testing may be requested at the discretion of the COR.

5.2.17.4 If visible contaminants are evident through visual inspection, re-clean those portions of the system where contaminants are visible, and subject to reinspection for cleanliness.

5.2.17.5 As part of the inspection, record photographs of inspection locations to document post-cleaning condition.

5.2.18 Post Project Report

5.2.18.1 At the conclusion of the project, provide a Testing Procedures Summary and Post-Project Report indicating the following:

5.2.18.1.1 Success of the cleaning project as verified through visual inspection and photographs.

5.2.18.1.2 Areas of the system found to be damaged and/or in need of repair as verified through visual inspection and photographs.

5.3: Service Contract Reporting: Reserved.

5.10.1 Reserved.

5.10.2 Reserved.

6.0 Applicable Publications: Publications applicable to this PWS are listed below:

Publication (Chapter/Page)

Date of Publication
Mandatory or Advisory
Website

Federal Acquisition Regulation https://www.acquisition.gov/?q=browsefar

Defense Federal Acquisition Regulation Supplement http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html or https://www.acquisition.gov/dfars

DoDM 1000.13-M-V1 DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b) 01/23/2014 (Change 1: 07/28/2020) http://www.esd.whs.mil/Directives/issuances/dodm

Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors (paragraph 9) August 2013 http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf

DoDM 5200.2 Procedures for the DoD Personnel Security Program (PSP)
04/03/2017

https://www.esd.whs.mil/Directives/issuances/dodm/

DoDI 5200.46 DoD Investigative and Adjudicative Guidance for Issuing the Common Access Card (CAC) 09/09/14 (Change 1: 05/04/2018) https://www.esd.whs.mil/Directives/issuances/dodi/

Homeland Security Presidential Directive (HSPD)-12 Policy for a Common Identification Standard for Federal Employees and Contractors 08/27/2004 https://www.dhs.gov/homeland-security-presidential-directive-12

DoDI 5400.11 Department of Defense Privacy and Civil Liberties Programs 01/29/2019 https://www.esd.whs.mil/Directives/issuances/dodi/

DoD 5400.11-R Department of Defense Privacy Program 05/14/2007 https://www.esd.whs.mil/Directives/issuances/dodm/

DoDD 8140.01 Cyberspace Workforce Management

10/05/2020 https://www.esd.whs.mil/Directives/issuances/dodd/

DoD 8570.01-M Information Assurance Workforce Improvement Program 12/19/2005 (Change 4: 11/10/2015) https://www.esd.whs.mil/Directives/issuances/dodm/

DoD 5220.22-M National Industrial Security Program Operating Manual (NISPOM) 02/28/2006 (Change 2: 05/18/2016) https://www.esd.whs.mil/Directives/issuances/dodm/

AFI 10-245

Antiterrorism 03/28/2013 (Certified current 03/30/2017) https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFI 31-101

Security Forces Standards and Procedures 08/18/2020 https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFMAN 31-113

Security Forces Standards and Procedures 03/05/2013 Change 1:

12/02/2015 https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFPD 17-1

Information Dominance Governance and Management 04/12/2016 https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFMAN 17-1301

Computer Security (COMPUSEC) 02/12/2020 https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

AFI 10-701

Operations Security 7/24/2019 (Change 1:

06/09/2020) https://www.e-publishing.af.mil/Product-Index/#/?view=pubs&orgID=10141&catID=1&series=-1&modID=449&tabID=131

6.1 Applicable Forms: Forms applicable to the PWS are listed below:

Form
Date
Website

DD 1172-2

Application for Identification Card/DEERS Enrollment

Mar 2017
http://www.dtic.mil/whs/directives/forms/index.htm

I-9 Employment Eligibility Verification 10/21/2019 https://www.uscis.gov/sites/default/files/files/form/i-9.pdf

DD 441

Department of Defense Security Agreement Feb 2020 http://www.dtic.mil/whs/directives/forms/dd/ddforms0001-0499.htm

DD 250

Material Inspection and Receiving Report

Aug 2000
https://www.esd.whs.mil/Directives/forms/dd0001_0499/

TECHNICAL EXHIBIT 1

Performance Requirements Summary (PRS)

This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

Performance Objective
Performance Standard
Acceptable Quality Levels (AQL)
Surveillance Method / By Whom

5.1.1 Perform Visual Inspection, Report any System Damage, Devise Plan of Methods

The contractor shall record photographs of each inspection location to document the “as found” condition prior to cleaning. Document damaged system components found during the inspection.
Submit to the Contracting Officer, clearly labeled “Record of Existing Conditions.”
Random monitoring / COR

Review of document submittal by COR

5.2 Clean HVAC System

The contractor shall clean HVAC systems as specified in the PWS
Uses NADCA methods to accomplish work. Removes debris and provides photographs showing the system to be visibly clean. Repairs any openings made for cleaning access.
Periodic Inspection / COR

5.2.16 Antimicrobial Agents and Coatings

Perform application of antimicrobial agents used to control the growth of fungal or bacteriological contaminants after the removal of surface deposits and debris.
The contractor shall Perform application of antimicrobial agents used to control the growth of fungal or bacteriological contaminants after the removal of surface deposits and debris.
Random monitoring / COR

5.2.17.2 Visual Inspection The contractor shall visually inspect the HVAC system to ensure that no visible contaminants are present.

Prior to applying antimicrobial coating the contractor will visually verify the cleanliness. If no contaminants are evident through visual inspection, the HVAC system will be considered clean.
Coordinated Inspection / COR

5.2.18 Post Project Report At the conclusion of the project, provide a Testing Procedures Summary and Post-Project Report indicating the following:

Areas of the system found to be damaged and/or in need of repair as verified through visual inspection and photographs.

Success of the cleaning project as verified through visual inspection and photographs.

Submit to the Contracting Officer at the conclusion of the project.
Review of document submittal by COR

TECHNICAL EXHIBIT 2

Deliverables Schedule

PWS Reference / Deliverable Title
Frequency
Number of Copies
Medium/Format
Submit To

5.1.1 Existing Conditions

Prior to commencing cleaning.
2
1 Electronic Submission / 1 Hardcopy
COR

1.4.7 Special Qualifications

Provide prior to commencing cleaning.
1
Electronic Submission
COR

5.2.18 Post Project Report

Within 15 calendar days of project completion.
2
1 Electronic Submission / 1 Hardcopy
COR
1.4.5.3 AT Level 1 Awareness Training Certificates
Provide within 15 calendar days after employee completes training.
1
Electronic Submission
COR

1.4.5.11 OPSEC

Training Certificates

Provide within 15 calendar days after employee completes training.
1
Electronic Submission
COR

Ver. October 2022

File details come from the government source that posted it. Updated .