Attachment 1 - PWS.docx
DOCX document 55 KB Posted
- Attached to
- Upgrade Refrigeration Equipment Federal contract opportunity
- Solicitation number
- 1232SA26Q0434
About this file
This is a Performance Work Statement (PWS) for upgrading refrigeration equipment at the USDA's Integrated Cropping Systems Research location in Brookings, South Dakota. The project involves the complete demolition and removal of an existing seed storage cooler refrigeration system that is over 18 years old, along with proper EPA-compliant disposal of R12 refrigerant. The contractor must furnish and install a new refrigeration system capable of maintaining precise environmental conditions within the 17 ft × 15 ft 6 in × 10 ft cooler box: temperature between 32–41°F (maintained within 3°F of setpoint) and relative humidity at 40% (maintained within 5% of setpoint).
The new system shall include commercial-grade controls (KE2 Therm or government-approved equivalent) with integrated temperature and humidity monitoring, system status visualization, alarm annunciation, and remote monitoring and adjustment capabilities. The contractor must install a new indoor condensing unit, evaporator coil, refrigeration piping, insulation, wiring, and all accessories necessary for turnkey operation. The system must include continuous monitoring with automatic alerts for out-of-range conditions sent to designated contacts. Both deliverables—removal of the existing system and installation of the new system—are due within 60 days or earlier after contract acceptance. Key personnel requirements include an on-site superintendent and proof of operator certification for equipment operating over buildings or personnel. All personnel must possess a valid U.S. photo ID. Operations and maintenance manuals must be provided in Adobe format. The solicitation is a Total Small Business Set-Aside with a small business size standard of $19.0M under NAICS code 238220 (Plumbing, Heating, and Air-Conditioning Contractors). Access coordination is required with the Location Monitor, Craig McCuin (605-693-5203), and work is expected during standard business hours (0730–1630, Monday–Friday, excluding federal holidays).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1232SA26Q0434.pdf | ||
| Attachment 2 - Wage Determination 2015-5375.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Performance Work Statement
Contents
| Project Title | 3 |
| General Information | 3 |
| 1.0 Background and Purpose | 3 |
| 2.0 Definitions | 3 |
| Contractor Requirements | 3 |
| 3.0 Technical Requirements / Tasks | 3 |
| 4.0 Deliverable / Schedule | 3 |
| 5.0 Government Furnished | 4 |
| 6.0 Travel | 4 |
| 7.0 Contractor’s Key Personnel | 4 |
| 8.0 Security Requirements | 4 |
| 9.0 Data Rights | 4 |
| 10.0 Section 508 - Electronic and Information Technology Standards | 4 |
Project Title Seed Storage Cooler Refrigeration Upgrade
General Information
1.0 Background and Purpose
The current seed storage cooler at the Integrated Cropping Systems Research location in Brookings, SD is over 18 years old. The existing refrigeration equipment, controls, and refrigerant have reached the end of their expected service life and must be upgraded to meet current environmental standards. The cooler box itself is in good condition and does not require replacement.
The Contractor shall demolish and remove all existing mechanical equipment serving the seed storage cooler. The Contractor shall capture all existing R‑12 refrigerant and dispose of it in accordance with applicable EPA regulations.
The Contractor shall provide all labor, equipment, supplies, materials, and coordination necessary for the demolition of the existing refrigeration equipment and the installation of the new refrigeration equipment.
2.0 Definitions
None.
Contractor Requirements
3.0 Technical Requirements / Tasks
The existing cooler box measures approximately 17 ft (L) × 15 ft 6 in (W) × 10 ft (H). The upgraded refrigeration system shall maintain the following environmental conditions within the cooler:
· Temperature: 32–41 °F (0–5 °C), maintained within ±3 °F of setpoint.
· Relative Humidity: 40% RH, maintained within ±5% RH of setpoint.
· The system shall include integrated temperature and humidity controls capable of continuous monitoring and adjustment.
3.1 Removal of Existing Equipment
The Contractor shall:
· Disconnect, isolate, and cap all existing electrical, HVAC, plumbing, and control connections serving the cooler.
· Remove and properly dispose of all existing refrigeration components, including but not limited to evaporator coils, condensing unit, refrigerant piping, humidification equipment, and associated controls.
· Recover and dispose of all refrigerant in accordance with EPA regulations, providing documentation upon request.
3.2 Installation of New Refrigeration System
The Contractor shall furnish and install a complete, operational refrigeration system meeting the following requirements:
Controls
· Provide commercial‑grade control systems suitable for low‑temperature storage applications.
· Controls shall be KE2 Therm or Government‑approved equivalent.
· Controls shall provide:
· Temperature and humidity control
· System status visualization
· Alarm annunciation
· Remote monitoring and adjustment capability
Refrigeration Equipment
· Install a new indoor condensing unit and evaporator coil sized appropriately to maintain required temperature and humidity conditions.
· Provide and install all refrigeration piping, insulation, wiring, and accessories required for a complete system.
· Refrigerant shall comply with current EPA and industry standards at the time of installation.
Monitoring and Alerts
· The control system shall continuously monitor temperature, humidity, and system performance.
· If conditions fall outside specified ranges, the system shall automatically send alerts to designated Government and/or Contractor contacts.
· Alerts shall be configurable and accessible through the remote monitoring interface.
3.3 Cooler Box Preparation
The Contractor shall:
· Prepare the existing cooler box for installation of new controls and sensors.
· Seal, repair, or remove any unused penetrations to maintain thermal integrity and prevent moisture intrusion.
· Ensure all penetrations for new piping, wiring, or sensors are properly sealed and insulated.
Accomplishment of the results contained in this PWS requires work at 2923 Medary Ave, Brookings, SD 57006.
Specific skill requirements: refrigerant usage license or permit.
4.0 Deliverable / Schedule
Submittals on replacement refrigeration equipment shall be made to the Government to show the Contractor’s Quality Assurance that the new equipment meets specifications and requirements for a turnkey installation and operation. Government has up to two weeks to review the Quality Assurance Complete Submittal, and the Contractor has one week for responses to the Government’s review comments.
Key Deliverables
| Item No. |
| Deliverable |
| Objective |
| Due |
| 1 |
| Demo existing refrigeration system |
| Remove and properly dispose of existing refrigerant components including evaporator coils, piping and condensing unit (such as compressor, proportional valve, etc.) including refrigerant |
| 60 days or earlier after contract acceptance. |
| 2 |
| Assemble and install new refrigeration system |
| Install new refrigeration system, including all components and refrigerant that is compliant with current standards |
| 60 days or earlier after contract acceptance. |
5.0 Government Furnished
Normal workdays are Monday through Friday except U.S. Federal Holidays. Workers typically work eight hours per day, 40 hours per week. Core hours of work are from 0730 to 1630 daily. All employees are expected to be available during core hours. If there are any weather or security closures, the contractor will ensure that all buildings are secure to prevent human intrusion prior to leaving the site.
Access to the seed storage cooler area shall be coordinated with the Location Monitor, Craig McCuin 605-693-5203.
6.0 Travel
Not applicable.
7.0 Contractor’s Key Personnel
| A. | On site Superintendent’s name. |
| B. | Operator’s certification or license on equipment that operates over buildings or personnel. |
8.0 Security Requirements
All personnel shall have a U.S. photo ID, such as U.S. Driver’s License, or U.S. passport.
9.0 Data Rights
Not applicable.
10.0 Section 508 - Electronic and Information Technology Standards Operations and Maintenance Manuals in adobe format.
image1.png