Attachment 1 - PWS 17 Jun 25.pdf

PDF 1 MB Posted

Attached to
SOURCES SOUGHT ONLY: PURCHASE AND INSTALL TRAFFIC LIGHT CONTROL PANEL (REPLACEMENT)
Solicitation number
FA461325Q00019
Issued by

About this file

This Performance Work Statement (PWS) details a traffic light control panel replacement service for F.E. Warren Air Force Base in Wyoming. The contractor will be responsible for removing existing traffic light control panels, replacing them with new panels, programming the systems, and instructing base personnel on maintenance. The project involves four specific intersections (Randall Ave & Rogers Rd, Randall Ave & Old Glory Rd, Randall Ave & Schiever Rd, and Old Glory Rd & Missile Dr), with work to be performed Monday through Friday from 0730-1630 hours.

Key requirements include installing new aluminum P Cabinets with specific components like MMU216Leip 510 Load Switches, 810 Flasher, BIU, 700 Flash Transfer Relays, Yunex Blade Traffic Controller, and Marathon UPS Battery Backup. The contractor must have a minimum of one year experience in programming traffic light control panels and comply with various security, environmental, and operational requirements. Deliverables include training certificates, hazardous materials authorization requests, OPSEC training documentation, an inspection checklist, quality control plan, and maintenance schedule. The contract emphasizes the need for panels that can function 24/7 and have a proven track record of at least 5 years in similar conditions.

View the file

Other files

File Type Posted
Attachment 2 - Salient Characteristics.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT FOR

TRAFFIC LIGHT CONTROL PANLE

REPLACEMENT & ASSOCAITED

SERVICES

F.E. Warren Air Force Base, Wyoming

27 May 2025

Table of Contents

1. Description of Services

1.1. Basic Services

1.2. Special Services. .......................................................................................... Error! Bookmark not defined.

2. Services Summary

3. Government Furnished Property and/or Services

3.1. Government Furnished Property

3.2. Government Furnished Services

3.3. Government Property Incidental to the Place of Performance

4. General Information

4.1. Quality Control

4.2. Quality Assurance

4.3. Security Requirements

4.4. Physical Security

4.5. Operational Security (OPSEC)

4.6. Anti-Terrorism

4.7. Location/Hours of Operation

4.8. Conservation of Utilities

4.9. Environmental Controls

4.10. Safety Requirements

4.11. Privatized Utility Systems

4.12. Continuation of Essential DoD Contractor Services During Crisis. ............ Error! Bookmark not defined.

4.13. Contractor Personnel

4.14. Records

4.15. Controlled Unclassified Information (CUI). ............................................... Error! Bookmark not defined.

4.16. Special Qualifications and Training

4.17. Contractor Transitions. ............................................................................. Error! Bookmark not defined.

5. Appendices

APPENDIX A – Publications/Instructions

APPENDIX B – Deliverables .................................................................................... Error! Bookmark not defined.

APPENDIX C – Facility Cleaning Frequency ............................................................ Error! Bookmark not defined.

APPENDIX D – Inspection Checklist/Report

1. Description of Services.

The contractor shall provide all management, tools, supplies, equipment, and labor necessary to perform a traffic light control panel replacement service at F.E. Warren Air Force Base, Wyoming, in accordance with all applicable federal, state, local laws and regulations and this performance work statement (PWS).

1.1. Basic Services. The contractor shall remove existing traffic light control panels, replace with new panels, program, and instruct base personal in required maintenance of new systems. The contractor shall provide a maintenance schedule for the panels upon completion of the installation. The contractor shall install program related components/appurtenances. Each panel shall be free of any and all construction debris after panel installation.

2. Services Summary.

The contractor service delivery requirements are summarized into performance objectives that relate directly to standards of performance required to meet mission essential needs. For the Performance Objective to be met, service delivery must be in substantial compliance with applicable performance standards. The Performance Threshold describes the minimum overall levels of service delivery required for acceptable quality control. Failure to meet these Performance Thresholds means that contractor Quality Control is unacceptable. The following is a list of the key performance objectives that will be verified as contractually compliant by Government personnel; however, inspection of any contract requirement is authorized.

Performance Objective PWS Para. Performance Threshold Method of Surveillance

SS-1: Perform 1.1 No more than 1 discrepancy per month from Electrical Shop, COR or validated customer complaint.

Electrical Inspector shall inspect and sign off on each service.

Choose one or more from:

- Periodic Surveillance

- 100% Inspection

SS-2: Conduct 1.2 No more than 1 discrepancy per month from Electrical Inspector, COR or validated customer complaint. All traffic light control panels shall function properly and efficiently, i.e. manage and move traffic through each signalized intersection.

3. Government Furnished Property and/or Services

3.1. Government Furnished Property.

3.1.1. None

3.2. Government Furnished Services.

3.2.1. Utilities. The Government will furnish the electricity (as necessary) for the accomplishment of service IAW this PWS.

3.3. Government Property Incidental to the Place of Performance.

3.3.1. None.

4. General Information.

4.1. Quality Control.

The contractor is required to control the quality-of-service delivery and offer to the Government for acceptance only services which conform to contract requirements. The overall control of quality must meet the specified performance thresholds for each requirement in the Services Summary.

4.1.1. Quality Control Plan

The contractor shall develop and maintain a quality control plan (QCP) to ensure traffic light control panel operations provide a continuous, cost-effective, and efficient treatment of all signalized intersections. The contractor shall develop and implement procedures to track, identify, prevent, remedy, and ensure non-recurrence of defective services. As a minimum, the contractor shall develop quality control procedures addressing the areas identified in para.1.1. The contractor’s QCP shall be submitted to the CO within 10 business days after contract award. The plan must be satisfactory to the Government within 30 calendars for it to be accepted and implemented.

4.2. Quality Assurance

The Government will evaluate the contractor’s performance by appointing a representative(s) to monitor performance to ensure services are received. The Government representative will evaluate the contractor’s performance through on-site inspections and receipt of customer complaints. The Government will inspect each task as completed. The Government will investigate complaints received from customers. The Government representative shall make final determination of the validity of customer complaint(s) in cases of disagreement with customer(s). Remedies for non-conforming services will be resolved IAW the applicable Inspection/Acceptance clause attached within the contract.

4.2.1. The Contracting Officer’s Representative (COR) is the authorized Government representative(s) who will perform assessments of the contractor’s performance. After contract award, the identity of the COR(s), with a letter defining their duties and authority will be promptly furnished to the successful bidder/offeror.

4.2.2. The COR(s) will inform the contract manager when discrepancies occur and will request corrective action. The COR(s) will make a notation of the discrepancy on their surveillance checklist with the date and time the discrepancy was noted and will request the contract manager (or authorized representative) to acknowledge the discrepancy.

4.2.3. Any matter concerning a change to the scope, prices, terms, or conditions of this contract shall be referred to the Contracting Officer and NOT to the COR(s).

4.2.4. The services to be performed by the contractor during the period of this contract shall (at all times and places) be subject to review by the Contracting Officer or authorized representative(s).

4.3. Security Requirements.

The contractor shall be responsible for all passes issued to their employees under this contract. Applications shall be coordinated by the Contracting Officer or designated representative. At the time of application, Security Forces will conduct a background check on employees. Upon termination of employment or contract completion, the contractor shall be responsible for returning identification cards/base passes to Security Forces within 24 hours.

4.3.1. REAL ID-Compliant Identification.

IAW DoDM 5200.08V3_DAFMAN 31-101V3_DAFGM 2024-01, Installation Perimeter Access Control. Base access and Common Access Cards (CAC) requests will require REAL ID-Compliant identification for Base access and CAC creation. Failure of the vendor to ensure personnel have REAL ID-compliant identification will result in denial of Base access and CAC requests.

4.4. Physical Security.

The contractor shall be responsible for safeguarding all Government property provided for contractor use. At the close of each work period, Government facilities, property, and materials shall be secured.

4.4.1. Key Control.

The contractor shall establish and implement methods of ensuring that all keys/key cards issued to the contractor by the government are not lost or misplaced and are not used by unauthorized persons. The contractor shall not duplicate any keys issued by the government.

NOTE: all references to keys also include key cards. No keys issued to the contractor by the government shall be duplicated. The contractor shall develop procedures covering key control. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas.

4.4.1.1. The contractor shall immediately report the occurrences of a lost or duplicate key to the contracting officer.

4.4.1.2. In the event keys, other than master keys, are lost or duplicated, the contractor shall, upon written direction of the contracting officer, rekey or replace the affected lock or locks; however, the government, at its option, may replace the affected lock or locks or perform rekeying. When the replacement of locks or rekeying is performed by the government, the total cost of rekeying or the replacement of the lock or locks shall be deducted from the monthly payment due the contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the government and the total cost deducted from the monthly payment due the contractor.

4.4.1.3. The contractor shall prohibit the use of keys issued by the government by any persons other than the contractor’s employees. The contractor shall prohibit the opening of locked areas by contractor employees to permit entrance of persons other than contractor’s employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.

4.5. Operational Security (OPSEC).

The contractor shall adhere to the following minimum requirements in support of this requirement:

4.5.1. All contractors, subcontractors, their employees, associates, and consultants who have access to critical information and indicators must comply with the Air Force-sponsored Operations Security (OPSEC) program.

4.5.2. OPSEC is an information-related capability that preserves friendly essential secrecy by using a process to identify, control, and protect critical information and indicators. If critical information and indicators are disclosed, it could allow adversaries or potential adversaries to identify and exploit friendly vulnerabilities leading to increased risk to mission failure or the loss of life. The desired effect of OPSEC is to influence the adversary’s behavior and actions by reducing the adversary’s ability to collect and exploit critical information and indicators about friendly activities.

4.5.3. Responsibilities:

4.5.3.1. Contractors must ensure employees receive OPSEC education that includes an overview of the OPSEC process, the definition of OPSEC, its purpose, what is critical information, the individual’s role in protecting critical information, and the general adversary threat to the AF’s critical information. Additionally, OPSEC education must include updated threat information, changes to critical information and indicators, new procedures and/or OPSEC measures implemented, altered, or deleted by the organization.

4.5.3.2. DoD Contractors with OPSEC requirements or that have access to critical information and indicators shall complete initial and annually-recurring refresher training. Accomplishment of initial OPSEC training must not exceed 90 days from initial assignment to a contract with OPSEC requirements. Access to mission-critical information will not be allowed until OPSEC education has been completed and documented.

4.5.3.3. OPSEC education is a continuous requirement. The host unit OPSEC coordinator must track OPSEC training statistics to include the personnel working on the contract, when each individual received the required initial OPSEC training, and when refresher training is due and/or completed.

4.5.4. Contractor personnel shall not discuss government operations in public or over unprotected or unencrypted communications. Controlled unclassified information (CUI) may only be transmitted as directed in this PWS.

4.5.5. The Contractor shall not post to company websites, publications, newsletters, or other media any images, data, or information that reveal sensitive government operations, personnel, equipment, and/or classified or controlled unclassified information. When in doubt, company press releases related to this contract should be coordinated through the COR or CO, as applicable.

4.5.6. Prior to seeking approval through the F. E. Warren AFB Public Affairs, any information to be released outside of official U.S. Government channels, via any media (to include electronic communications), must be approved through an OPSEC review. All personnel must promptly report OPSEC-related incidents, issues, and concerns to the host-unit OPSEC coordinator.

4.5.7. Contractor shall restrict access to those individuals with a valid need-to-know who are actually providing services under the contract. Further dissemination to other contractors, subcontractors, or other government agencies and private individuals or organizations is prohibited unless authorized in writing.

4.5.8. Because observation of events, operations, physical changes, etc., may reveal National Security information, specific restrictions are needed to preclude unintentional release of this information to unauthorized parties. Unauthorized disclosure and transfer of National Security Information is punishable under 18 USC § 793. Therefore, contractor personnel shall not disclose to unauthorized third parties, post to unofficial sites (including Social Networking sites) any images, data/information, or observed events that reveal sensitive government operations, personnel, equipment, including, but not limited to:

4.5.8.1. Tactics, techniques, and procedures, production, or work schedules, any visible or concealed modifications, upgrades, additions to vessels, aircraft, or weapons or equipment; increases, change, or decreases in work/deployment frequency or government personnel, vehicle, vessel, or aircraft movements;

specialized equipment orders, deliveries, shipments, etc. Unauthorized disclosures and attempts to solicit this type of information by unauthorized third parties or others not affiliated with this contract shall be reported to the COR or CO, as applicable.

4.5.8.2. Government issued badges, identification shall be removed and/or concealed from plain sight when off base and shall not be left in vehicles or unprotected areas. Badges and passes may not be duplicated, copied, or loaned to others. Lost or stolen identification badges, vehicle passes, etc., will be immediately reported to the COR, CO, and/or Installation Security Office.

4.6. Anti-Terrorism

4.6.1. Notification: If the Contractor (contract employees/subcontractors) identify any suspicious activity, they shall contact the Base Defense Operations Center (BDOC) at 307-773-3501 (On-installation)/Missile Security Control (MSC) at 307-773-2701 (Off-installation) and notify the CO and COR (if appointed) that they contacted the BDOC and/or MSC.

4.6.2. Training. Contractor employees that require routine physical access to a Federally-controlled facility or military installation shall complete Level I antiterrorism awareness training within 30 days of requiring access and annually thereafter and send a copy of their employees’ training certificate(s) to the CO and COR (if assigned). Training is located at Joint Knowledge Online (JKO) website:

https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf

4.7. Location/Hours of Operation.

4.7.1. Location. Place of performance is at FE Warren AFB WY. Telework shall not be permitted for this task order/contract.

4.7.2. Normal Hours of Operation. The contractor shall perform the services required under this contract during the hours listed within Table 1, Location and Hours of Work. The contractor may work (with prior approval of the CO) extended hours to ensure timely completion of work at no additional cost to the Government.

4.7.3. Recognized Holidays. The contractor is not required to provide service on the following days, unless otherwise noted:

New Year's Day (January 1).

Birthday of Martin Luther King, Jr. (Third Monday in January).

Washington's Birthday (Third Monday in February).

Memorial Day (Last Monday in May).

Juneteenth National Independence Day (June 19).

Independence Day (July 4).

Labor Day (First Monday in September).

Columbus Day (Second Monday in October).

Veterans Day (November 11).

Thanksgiving Day (Fourth Thursday in November).

Christmas Day (December 25).

If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.

Table 1. Location and Hours of Work

Intersection Intersection Location Days Time

1 Randall Ave & Rogers Rd Monday - Friday 0730-1630 hrs

2 Randall Ave & Old Glory Rd Monday – Friday 0730-1630 hrs

3 Randall Ave & Schiever Rd Monday – Friday 0730-1630 hrs

4 Old Glory Rd & Missile Dr Monday – Friday 0730-1630 hrs

4.8. Conservation of Utilities.

The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions which prevent the waste of utilities which include the following:

4.8.1. Lights shall be used only in areas where and when work is being performed.

4.8.2. Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor or by contractor employees unless authorized.

4.9. Environmental Controls.

4.9.1. Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Interstate, federal, state, and local laws, regulations, and requirements regarding environmental protection, to include Section 01 57 19.05 32, Environmental Protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost because of the change, the contractor shall inform the CO pursuant to notice requirements and negotiate a modification to the contract.

4.9.2. Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to the F.E. Warren AFB Fire Dept at 911 (landline) or 307-773-2931 (cell phone). The liability for the spill or release of such substance(s) rests solely with the contractor and its agent.

4.9.3. Hazardous Material (HM). If hazardous materials will be used in the execution of this contract, the contractor shall comply with all federal, state and local regulations concerning the use, storage, and reporting of HM in accordance with AFMAN 32-7002, Environmental Compliance and Pollution Prevention. The contractor shall be required to obtain authorization per the Installation Hazardous Materials Management

Program before ordering or purchasing any hazardous product and may not bring a HM onto F.E. Warren AFB property, nor use a HM, until the contractor receives all required authorizations. This authorization process may take up to three weeks. The contractor shall provide the information listed in Attachment 1 of Section 01 57 19.05 32 to request authorization for all hazardous materials proposed for use on FE Warren AFB or the missile field.

4.9.4. Green Procurement Program (GPP). In performance of this contract, contractors shall use Environmental Protection Agency (EPA) designated recycled content products, Information Technology (IT) Energy Star products/appliances, Federal Energy Management Program (FEMP) Designated Energy Efficient Low Stand By Power products/appliances, U.S. Department of Agriculture (USDA) Bio based/Bio preferred products, Environmentally preferable products, Electronic Product Environmental Assessment Tool (EPEAT) registered products, Water Sense or other water efficient products, non- or Low Ozone depleting substances under the Significant New Alternatives Policy (SNAP), non or Low toxic or hazardous constituents (e.g. non- VOC paint) and any other environmentally sustainable product/method, to the greatest extent possible.

4.10. Safety Requirements.

4.10.1. In performing work under this contract, the contractor shall:

4.10.1.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

4.10.1.2. Record and report promptly (within one hour), to the contracting officer or designated COR, all available facts relating to each instance of damage to Government property or injury to either contractor or Government personnel.

4.10.1.3. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the CO.

4.11. Privatized Utility Systems.

4.11.1. The electrical distribution utility system at F.E. Warren Air Force Base has been sold to High West Energy (“System Owner”) as part of the USAF Utilities Privatization (UP) effort. Therefore, the System Owner is the sole provider of these utility services to the installation and should be viewed just like any other local utility Contractor.

4.11.2. Newly installed system infrastructure and modifications of (or connections to) existing system infrastructure identified in the specifications and drawings must be coordinated with the System Owner prior to the contract start date. The System Owner must be integrated into the design, inspection of construction, tie-in to existing utilities, and conveyance of any exterior utilities. The preferred process for connecting facilities is to request that the System Owner install the required connecting facilities, up to a point of demarcation to be identified by the Government, as a connection charge. However, if a connection charge cannot be negotiated, work may be accomplished by the Prime Construction Contractor and later connected to the System Owner’s system, provided that the System Owner’s connection criteria, as set forth in its utility services contract with the Government, are met. Any fees associated with connecting Contractor constructed infrastructure to the System Owner’s system must be negotiated with the System Owner. All work on the system or facilities expected to connect to the system shall comply with the System Owner’s specifications and construction standards.

In no event shall the Contractor cap, connect to, or otherwise touch the System Owner’s infrastructure without the System Owner’s express written permission. This also applies in the event of a utility strike involving the System Owner’s infrastructure.

4.11.3. System Owner Office Hours:

Monday thru Thursday, 7:30am – 5:00pm MST

4.11.4. If the Contractor requests the System Owner’s efforts outside of the above identified business hours, additional costs may be incurred by the Contractor due to the scheduling of the request.

For a non-emergency, the System Owner may be contacted at:

Project Manager o 307-365-6458

HWE Main Office o 6270 CR 212, PO Box 519

Pine Bluffs, WY 82082 o 307-245-3261

For emergencies or utility strikes involving the System Owner’s infrastructure, please follow standard procedures identified on the Dig Permit Request Checklist.

4.13. Contractor Personnel.

4.13.1. Contract Manager: the contractor shall provide a contract manager who shall be responsible for the performance of the services. The name of the contract manager shall be provided to the CO in writing prior to the beginning of the first performance period. The contract manager must be able to read, write, speak, and understand English.

4.13.1.1 The contract manager shall have full authority to act for the contractor on all contract matters relating to daily operations of this contract.

4.13.2. Contractor Employees: the contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the CO as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population.

4.13.2.1. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges, which contain the company name and employee name in English.

4.14. Records. The contractor shall be responsible for creating, maintaining, and disposing of only those government required records that are specifically cited in this PWS or required by the provisions of a mandatory directive listed in (LIST APPLICABLE APPENDICES) Applicable Publications and Forms. If requested by the Government, the contractor shall provide the original record, or a reproducible copy of any such record within five working days of receipt of the request.

4.16. Special Qualifications and Training.

4.16.1. The contractor must have a minimum of one (1) year experience in programming Traffic Light Control Panels.

5. Appendices

A. Publications/Instructions

B. Deliverables

C. Inspection Checklist

APPENDIX A – Publications/Instructions

Publication/Instruction /Name Date Applicable

Paragraph/Chapter PWS Paragraph

Section 01 57 19.05 32, Environmental Protection 01/2023 Entire Document

Applicable PWS Para. 4.9.1

DoDI 3020.41, Operational Contract Support *

20 Dec 2011 Para 2c. PWS Para 4.10

Publication available at:

*http://dtic.mil/whs/directives/corres/pdf/302041p.pdf

APPENDIX B – Deliverables

All deliverables must meet professional standards and the requirements set forth in the applicable contractual documents. The Contractor shall be responsible for delivering all specified end items. The end items listed in the table below are outputs, which fall within the scope of this effort and are illustrative of the type of work the Government expects to require.

Title Submission Date Distribution Copies AT Level I Training Certificate(s) (PWS para. 4.6.2.)

Within 30 days of requiring access and annually thereafter

COR 1 each

Hazardous Materials Authorization Request and Safety Data Sheets (SDS) (PWS para 4.9.3.)

Three weeks prior to planned use on FE Warren AFB or missile field.

CO 1 each

OPSEC Training (PWS para 4.5.3.2.)

Within 90 days of assignment and annually thereafter

COR 1 each

List of Contractor Work Experience (PWS para 4.10)

With proposal CO 1 each

Inspection Checklist/Report (PWS para 1.1.1.)

Within ten calendar days of performed of installation

COR 1 each

Quality Control Plan (PWS para 4.1.1)

Within ten calendar days of performed of installation

COR 1 each

Maintenance Schedule (PWS para 1.1)

Within ten calendar days of performed of installation

COR 1 each

APPENDIX C – Inspection Checklist/Report

Traffic Light Control Panel Replacement and Service

Intersection Inspected/Replaced:

Date and Time:

Traffic Light Control Panel Contractor:

Identify any damage, in the corrective actions section of this report, to the following:

Electric wires and conduit Interior lighting Cooling System

_ All panel components are functioning properly, to include fans and lights.

Work area is cleaned and restored to pre-installation conditions.

After installation is completed, the contractor will place or display on the panel box door a label indicating the date installed, signal programming date, and the name of the servicing company.

_ Problems, deficiencies, damaged/inoperable equipment annotated in the Corrective Actions Section of this report.

RECOMMENDED CORRECTIVE ACTIONS: (use separate sheet of paper if necessary)

Certifying Official’s Signature:

Name:

Fire Inspector Signature:

Name: