Attachment 1 Performance Work Statement (PWS) Building 4607.pdf

PDF 309 KB Posted

Attached to
Exhaust Troubleshooting
Solicitation number
FA485526Q0038
Issued by

About this file

This is a Performance Work Statement (PWS) for Building 4607 Exhaust System Troubleshooting at Cannon Air Force Base, New Mexico, dated December 16, 2025, with contract status listed as Pending.

The contractor shall provide all labor, personnel, equipment, tools, materials, transportation, supervision, and qualifications necessary to troubleshoot the Building 4607 exhaust system. Key requirements include testing and troubleshooting the communications BUS to all controllers and terminal equipment, with minor repairs such as re-terminating controllers and devices included in scope. Major repairs such as high bay/ceiling wire replacement over 10 feet in height or long wire runs exceeding 25 feet are excluded. The contractor must test network and field controllers' input/output control and monitoring points, verify equipment responses, and work with a remote software engineer to verify system points and equipment in graphic utility interface systems. Systems involved include paint booth air handler units, exhaust fans, breathing air system, chilled water system, heating water system, machine shop air handler and terminal units, office air handler, variable air volumes, pumps, valves, and actuators. Upon completion, the contractor shall compile a comprehensive report on items requiring repair or replacement for submission to 27 SOCES for review.

Contractor personnel must present a neat appearance, be easily recognized as contractor employees, and clearly read, write, speak, and understand English. All contractor employees require base passes and identification from the 27th Special Operations Security Forces Squadron (27 SOSFS), with pass requests submitted to 27th Special Operations Contracting Squadron (27 SOCONS) within three business days. The contractor must provide and maintain all vehicles with company names prominently displayed, maintain professional appearance, and comply with all base traffic regulations. Work hours are 0700-1600, Monday through Friday, excluding U.S. Federal holidays, with any outside-hours work requiring Contracting Officer approval. The contractor must comply with OSHA safety requirements, protect government property, and report any damage to government property or personnel injuries to the Contracting Officer or Contracting Officer's Representative within one hour. Government will provide electricity and potable water subject to availability. Contractor employees are prohibited from possessing weapons, firearms, or ammunition on CAFB.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

BUILDING 4607 EXHAUST SYSTEM

TROUBLESHOOTING

Cannon Air Force Base, New Mexico

Date: 16 Dec 2025

Contract: Pending Attachment 1 Date: 23 Oct 2025

1. DESCRIPTION OF SERVICES. The contractor shall provide all labor, personnel, equipment, tools, materials, transportation, supervision, qualifications and other items and services necessary to troubleshoot building 4607 exhaust system. The Contractor will troubleshoot communications control bus, verify sequence of operations, create deficiency list on non-working controllers and equipment. Once completed contractor will compile a report on the items needed to be repaired or replaced to 27 SOCES for review. The contractor shall perform the requirements of this PWS in compliance with all federal, state, and local laws, regulations and industry standards.

1.2 Requirements. Test and troubleshoot communications BUS to all controllers and terminal equipment. Communication BUS wiring minor repairs such as re-terminating controllers and devices is included. Major repairs such as high bay/ceiling (over 10’ in height) wire replacement & device terminations or long runs (over 25’) are not included. Test network and field controllers I/O control and monitoring points and equipment responses. Work with remote software engineer to verify points and equipment in graphic utility interface systems included – paint booth air handler unit's, exhaust fan's, breathing air system, chilled water system, heating water system, machine shop air handler and terminal units, and office air handler and variable air volume's. All pumps, valves and actuators. Remote software engineer to operate and monitor automation system to verify sequence of operation with on-site technician.

1.3. Utilities: The government will allow the use of electricity and potable water (subject to availability in the area) for accomplishment of service IAW this PWS.

2. GENERAL INFORMATION.

2.1. Personnel: Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. Employees must be clearly able to read, write, speak and understand English.

2.2. CAFB Access: The contractor shall ensure the pass and identification items required for contract performance are obtained for employees. The Pass and Identification Section of 27th Special Operations Security Forces Squadron (27 SOSFS) will provide base entry authorizations/passes to each authorized contractor employee. In addition, contractor personnel wishing to operate a privately-owned vehicle on CAFB must comply with all applicable state and base requirements. Entry authorizations must be renewed as required by the 27 SOSFS Pass and Identification Section. All contractor base pass requests must be sent to the point of contact on the contract from 27th Special Operations Contracting Squadron (27 SOCONS) within three business days of the time needed for the pass.

2.3. Retrieving Identification Media: The contractor shall retrieve all identification media, including vehicle passes, from employees who depart for any reason before the contract expires (e.g., terminated for cause, retirement, etc.).

Contract: Pending Attachment 1 Date: 23 Oct 2025

2.4. Vehicles: The contractor shall provide and maintain all vehicles necessary to perform the requirements of this contract. Contractor vehicles shall have the company name prominently displayed on both sides of the vehicles. Vehicles shall be clean and always have a neat, professional appearance. All vehicles shall be in operable condition. Vehicle repairs, other than emergency repairs, shall not be accomplished on CAFB. Equipment failure shall not alleviate the contractor from performing any requirement contained in this contract.

2.4.1. Only qualified operators shall be permitted to operate the vehicles or equipment for work required under this contract. Vehicle/equipment operators shall possess a valid driver’s license.

2.4.2. Weapons, Firearms, and Ammunition. Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their contractor-owned vehicles or privately-owned vehicle while on CAFB.

2.4.3. Traffic Laws. Contractor employees shall comply with all base traffic regulations. The contractor is not permitted to use cell phones on CAFB while operating a moving vehicle, unless the device is hands-free.

2.5. Work Hours: The work hours and work days for the period of performance are 0700 - 1600, Monday through Friday, with the exception of U.S. Federal holidays (listed below).

Additionally, if the contractor needs to work outside of the normal work hours, a request must be submitted to the Contracting Officer (CO) for approval.

New Year’s Day Labor Day Juneteenth Martin Luther King Day Columbus Day Washington’s Birthday Veterans Day Memorial Day Thanksgiving Day Independence Day Christmas Day

2.6. Security Forces and Fire Protection Services: On CAFB; Contact the appropriate agency in case of emergency by dialing 911. If dialing 911 from a cell phone, the call may be automatically routed to an off-base agency, such as the city of Clovis, NM. Be clear about whom you are communicating with and what your situation requires.

2.7. Safety Requirements: In performing work under this contract, the contractor shall conform to the safety requirements as required by OSHA. The contractor shall provide protection to Government property to prevent damage during the period of time the property is occupied by or in possession of the contractor. The contractor shall record and report promptly (within one hour) to the CO or COR, all available facts relating to each instance of damage to government property or injury to either contractor or government personnel.

PERFORMANCE WORK STATEMENT (PWS)
FOR

File details come from the government source that posted it. Updated .