PERFORMANCE WORK STATEMENT (PWS)
Bureau of Reclamation – Upper Colorado Region – Albuquerque Area Office
BRACKISH GROUNDWATER NATIONAL DESALINATION RESEARCH FACILITY
(Well No. 4 Video Inspection and Cleaning)
A. ABBREVIATIONS, DEFINITIONS, AND ACRONYMS
The following acronyms apply to specifications Divisions 1 through 52:
AAO Albuquerque Area Office BGNDRF Brackish Groundwater National Desalination Research Facility BOR Bureau of Reclamation CLIN Contract Line Item Number CO Contracting Officer COR Contracting Officer’s Representative.
CS Contract Specialist DOI Department of the Interior FAR Federal Acquisition Regulation GPM Gallon per Minute (gpm) MDT Mountain Daylight Time OSHA Occupational Safety and Health Administration RSHS Reclamation Safety and Health Standards, 2014 VFD Variable Frequency Drive
B. FOREWORD, DESCRIPTION, AND PURPOSE
The Bureau of Reclamation, Upper Colorado Region, Albuquerque Area Office, and Brackish Groundwater National Desalination Research Facility has a need for emergency services to inspect and clean existing Well No. 4.
Description of work tasks is to perform a video inspection and clean the existing BGNDRF Well No. 4. This will include pulling the well pump, injecting cleaning chemical, flushing the well, and performing video inspections before and after the cleaning operations. Well 4 has an estimated diameter of 6-inches and the submersible pump depth is unknown. The well is screened from 100 to 185 ft (screens in 20 ft segments) below ground surface (bgs) and static water is around 70 ft bgs. The existing 25 hp pump originally flowed at 230 gallons per minute (gpm) but has recently declined to 130-150 gpm. The electrical supply is 480VAC/3phase/50 amps and a VFD is installed on the well pump. The water is moderately brackish with approximately 3,300 mg/L total dissolved solids.
The well has not been in regular use for some time now but is expected to be in service more once a treatment building is built. This well provides the most flow when operating correctly and needs to be put back into service as soon as possible.
Components of Work. – The following is a short list of the principal work tasks for repairing Well No. 4:
Coordinate Tag-Out/Lock-Out of pumps energizing systems with facility manager.
Remove existing jacketed pipe insulation and store for reuse after repairs are completed on the well.
Pull existing motor and pump assembly for inspection and cleaning. Use existing stainless steel pipe and take caution not to damage existing airline and sound tubing.
Disconnect pump electrical systems.
Install chemical for cleaning and allow to soak per manufacturer suggestions.
Flush well into BGNDRF evaporation ponds. Coordinate this work with BGNDRF staff.
Reset well pump assembly using existing airline and sound tubing by lowering into place with new or existing stainless steel pipe.
Coordinate Tag-Out/Lock-Out to energize electrical systems to test well pump assembly.
If pump is operating correctly move to insulation step. If pump assembly is not working correctly, diagnose/troubleshoot problem and repair systems until pump is working correctly.
Reinstall jacket pipe insulation if possible.
Clean-up area and leave project site.
Offeror shall comply with all state and county codes and permits. Offeror is responsible for all permits required to pull and service water well.
C. STANDARDS AND SUBMITTALS
The following standards and generally accepted engineering principles or practices at this time and location shall govern well repairs under this action:
ASTM International (ASTM):
1. ASTM D 5978-96(11) Standard Guide for Maintenance and Rehabilitation of Groundwater Monitoring Wells
American Water Works Association (AWWA):
1. AWWA Manual M21 Groundwater
Submit the following using English and US Customary Units for review by the Government:
1. Submit Offeror’s safety plan, project scope, and schedule.
2. Submit for each manufacturer the following: shop drawings, product description, operational/owner’s manuals, and specifications for equipment being supplied by the Offeror under this contract.
D. SAFETY AND SITE ACCESS
Contractor shall adhere to the following safety requirements:
1. Contractor shall following the RSHS and the Service’s facility safety protocols.
The RSHS 2014 Edition is available online at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
2. OSHA Safety and Health Standards for the Construction Industry 29 CFR Part 1926.
Contractor shall adhere to the following site access requirements:
1. Contractor shall follow USBR Cleaning Manual Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition available online at:
http://www.usbr.gov/mussels/prevention.
2. Contractor shall use existing established access roads and work within established construction boundaries.
3. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
4. The BGNDRF access will be granted through the existing gate located along the south side of the facility. BGNDRF operational hours are from 7:30 AM MDT to 4:30 PM MDT Monday through Friday, except on federal holidays. Optional hours of operation may be granted by approval from COR. Coordinate access by contacting the facility manager:
Malynda Cappelle, Facility Manager 500 Lavelle Road Alamogordo, New Mexico 88310 Phone No.: (575) 443-6553 Email: mcappelle@usbr.gov
E. Period of Performance
It is expected that this service will be completed within 3 months of award.
F. SITE MAP
The following map provides project location, access gate, main complex, and location of Well No. 4 on facility grounds. The facility is accessed on the southwest portion of the map. Well 4 is on an easement to the north of the evaporation ponds.