This is a Performance Work Statement (PWS) for compressed air supply services at the 177th Fighter Wing, Building 445.

The contractor shall provide immediate preventative maintenance and repair services for two Atlas Copco air compressors (GA30 and GA55), two Atlas Copco air dryers (FX11 and FX14), and one Modern Safety Technologies RP200CA-S1 breathable air purifier located in Building 445, Room 111. The contractor must establish a working breathable air supply system delivering Grade D breathable air or better per OSHA regulations and perform bi-annual preventative maintenance on all equipment in accordance with manufacturer service manuals, beginning immediately after the initial service. Additionally, the contractor shall conduct quarterly air quality sampling of the breathable air purifier using calibrated equipment and send samples to an accredited third-party laboratory for analysis. The Period of Performance consists of a 12-month base year plus four optional 12-month years. Services must be provided Tuesday-Friday, 0730-1630, excluding recognized U.S. federal holidays and facility closures. The contractor shall furnish all personnel, equipment, tools, and materials except utilities, which the Government provides. Performance standards require service initiation within 24 hours of request with 100% completion of manufacturer checklists, 95% on-time bi-annual service completion within a 14-day window of the six-month due date, 100% on-time quarterly sampling (every 90 days ±5 days), and zero deviations from air quality standards with corrective action and re-testing within 48 hours if failures occur. The Contracting Officer Representative will conduct surveillance and inspection of all services.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ver. October 2022

CUI

PERFORMANCE WORK STATEMENT (PWS)

FOR

177th FW Building 445 Compressed Air Supply Services for Government-owned Equipment

1.0 General:

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform Compressed Air Supply Services as defined in this PWS.

1.1.1 Objectives: The objective is to perform the initial repair of Atlas Copco air compressors and air dryers, which includes the setup of compressed breathable air and air purifiers. Following any repairs, an initial service of all the aforementioned components will be conducted. The ongoing responsibilities include bi-annual servicing of all compressed air systems and quarterly sampling of the compressed breathable air.

1.2 Background: The compressed air supply at Building 445 is inoperable following a critical failure caused by a compressor overload. This system shutdown is a direct consequence of the equipment being severely overdue for required maintenance across every metric.

Establishing a comprehensive service contract is now an immediate necessity, not only to return the compressor to operational status but also to implement a preventative maintenance schedule that will ensure the equipment functions reliably and its service life is maximized.

1.3 Period of Performance (PoP): The Period of Performance shall be a base year (12 months) and four (4) 12-month option years. Services will be required bi-annually and quarterly in accordance with the PWS.

1.4 General Information:

1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0730-1630 on Tuesday-Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at 177th FW Building 445, Room 111 The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.1.1 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.1.2 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

1.4.2 Recognized Holidays: The following are recognized United States (US) holidays.

The contractor shall not perform services on these days:

1.4.2.1 New Year’s Day: January 1st

1.4.2.2 Martin Luther King, Jr.’s Birthday

1.4.2.3 President’s Day

1.4.2.4 Memorial Day

1.4.2.5 Juneteenth National Independence Day: June 19th

1.4.2.6 Independence Day: July 4th

1.4.2.7 Labor Day

1.4.2.8 Columbus Day

1.4.2.9 Veteran’s Day: November 11th

1.4.2.10 Thanksgiving Day

1.4.2.11 Christmas Day: December 25th

1.4.3 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).

1.4.4 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection

Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.4.5 The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

1.4.6 The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver s license, current vehicle registration, valid vehicle insurance certificate, and [insert any additional requirements to comply with local security procedures] to obtain a vehicle pass.

1.4.7 During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

1.4.8 Reserved

1.4.9 Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

1.4.10 Failure to comply with these requirements may result in withholding of final payment.

1.4.11 For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Air Force Instruction (AFI) 10-245, AFI 31-101 and Air Force Manual (AFMAN) 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative).

1.4.12 Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel.

1.4.13 Communications Security/Information Technology (COMSEC/IT) Security.

All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.14 Reserved

1.4.15 Contract Manager (CM): The contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.16 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to http://jko.jten.mil/ include signature blocks on e-mail) and dealings with Government or non- Government entities.

1.4.17 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.

1.4.18 Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.

1.4.19 Data Rights: The Government has unlimited rights to all documents/materials produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.4.20 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

2.0 Definitions and Acronyms:

2.1 Definitions:

2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.

2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.

2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.

2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 Acronyms:

AFMAN Air Force Manual CAT Crisis Action Team CM Contract Manager COMSEC Communications Security COR Contracting Officer Representative DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services IT Information Technology KO Contracting Officer NGB National Guard Bureau

POC Point of Contact PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan TE Technical Exhibit

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S):

The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:

3.2 Materials: None

3.3 Equipment: None

3.4 Services: None

3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

5.0 Requirements: The contractor shall perform the following:

5.1 Immediately provide on-site preventative maintenance service for the following equipment, located in Building 445, Room 111 utilizing applicable service manuals detailed in Paragraph 6.0 – Applicable Publications

5.2.1 One Atlas Copco GA30 Air Compressor

5.2.2 One Atlas Copco GA55 Air Compressor

5.2.3 One Atlas Copco FX11 Air Dryer

5.2.4 One Atlas Copco FX14 Air Dryer

5.2.5 One Modern Safety Technologies RP200CA-S1 Breathable Air Purifier

5.2 Establish working breathable air supply to paint booth

5.3 Perform Bi-Annual on-site preventative maintenance of all previously listed equipment in accordance with their respective Service Manuals detailed in Paragraph 6.0 – Applicable Publications, with intervals beginning immediately after initial service

5.4 Perform Quarterly Air Samples of Breathable Air Purifier in accordance with the RP200CA-S1 Operator’s Manual detailed in Paragraph 6.0 – Applicable Publications

6.0 Applicable Publications: Publications applicable to this PWS are listed below:

Publication

(Chapter/Page) Date of

Publication Mandatory or Advisory

Website

Federal Acquisition Regulation/Revolutionary FAR

Overhaul

5/22/2024/Feb

Mandatory https://www.acquisition.gov/?q=browsefar

Defense Federal Acquisition Regulation Supplement/DFARS

Deviations

7/29/2024/Feb http://www.acq.osd.mil/dpap/dars/dfarspgi/current/in dex.html or https://www.acquisition.gov/dfars

AFI 10-245

Antiterrorism

03/28/2013) (Certified current

03/30/2017) https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series

=-1&modID=449&tabID=131

AFI 31-101

Security Forces Standards and Procedures

08/18/2020 Mandatory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series

=-1&modID=449&tabID=131

AFMAN 31-113

Security Forces Standards and Procedures

03/05/2013 Change 1:

12/02/2015

Index/#/?view=pubs&orgID=10141&catID=1&series

=-1&modID=449&tabID=131 Atlas Copco Owner/Operator’s Manual

GA55

See Attachment 1

Atlas Copco Owner/Operator’s Manual

GA30

Mandatory See Attachment 2

Atlas Copco Owner/Operator’s Manual

FX11

Mandatory See Attachment 3

Atlas Copco Owner/Operator’s Manual

FX14

Mandatory See Attachment 4

Modern Safety Technologies Inc.

Service Manual

RP200CA-S1

See Attachment 5 https://www.acquisition.gov/?q=browsefar http://www.acq.osd.mil/dpap/dars/dfarspgi/current/in https://www.acquisition.gov/dfars https://www.e-publishing.af.mil/Product-https://www.e-publishing.af.mil/Product-https://www.e-publishing.af.mil/Product-https://www.e-publishing.af.mil/Product-

TECHNICAL EXHIBIT 1

Performance Requirements Summary (PRS)

This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

Performance

Objective

Performance Standard

Acceptable Quality Levels

(AQL)

Surveillance Method / By Whom

5.1 Immediately

Service specified equipment (5.1.1 through 5.1.5)

Service is initiated within 24 hours of the request. All service procedures are performed in strict accordance with the manufacturer's service manual for each piece of equipment. Only OEM or OEM-equivalent filters, oil, and parts are used. A detailed service report is logged for each machine.

100% Checklist Completion:

100% of the manufacturer's specified service checklist tasks are completed and documented.

95% On-Time Initiation: Service begins within the 24-hour window.

Inspection by Contracting Officer

Representative

5.2 Establish Working

breathable air supply to paint booth

The system must be fully operational and deliver Grade D breathable air or better, as defined by OSHA regulations.

Pressure and flow must meet the specifications of the paint booth and all associated respiratory equipment. All connections must be leak free

100% Compliance: Air quality analysis report confirms 100% compliance with the specified breathable air standard. Zero Faults: No system pressure drops or failures are permissible.

5.3 Perform Bi-Annual

Servicing of all previously listed equipment.

Servicing is scheduled and completed within a 14-day window of the 6-month due date. All standards from Task

5.3 apply. Service logs are updated with dates, actions taken, and parts used.

95% On-Time Completion: The bi-annual service for each piece of equipment is completed within the designated 14-day window.

100% Compliance: No service-related equipment failures occur between service intervals.

5.4 Perform Quarterly

Air Samples of

Breathable Air Purifier.

Air samples are taken from the designated sample port using calibrated equipment.

Samples are sent to an accredited third-party laboratory for analysis against Grade D breathable air standards. Results are received, reviewed, and filed within 10 business days of sampling.

100% On-Time Sampling:

Samples are taken every 90 days (±5 days). Zero Deviations:

If any sample fails to meet the required air quality standard, immediate corrective action and re-testing are initiated within 48 hours.

TECHNICAL EXHIBIT 2

Deliverables Schedule

PWS Reference / Deliverable Title

Frequency Number of Copies

Medium/Format Submit To

1.4.12 AT Level 1

Awareness Training

Certificates

Provide within 15 calendar days after employee completes training.

1 Electronic Submission

COR/KO

1.4.17 Identification

Media

Return within 14 days of employee’s departure from contract performance.

Original(s) Hard Copy COR/KO

File details come from the government source that posted it. Updated .