Attachment 1- Milestone Payment Plan.pdf
PDF 69 KB Posted
- Opportunity number
- 693JJ325NF00004
About this file
This is a Fixed Amount Milestone Payment Plan attachment detailing the payment schedule for a Federal Highway Administration (FHWA) grant award. The plan outlines five key milestones and deliverables: 1) A virtual kick-off meeting to be held within 3 weeks of award, 2) A draft project summary for the website due 10 months after award with a 30-day FHWA review period and 15-day revision period, 3) Three quarterly project website updates during Year 2, 4) Eight quarterly progress reports documenting activities and issues, and 5) An annual budget review and program plan for Year 2 due 60 days before the anniversary date.
The payment structure is fixed-amount based, meaning the recipient is not required to report actual costs but rather receives predetermined payments upon successful completion of each milestone. Payment amounts are to be filled in at time of award. FHWA will evaluate acceptable completion based on timeliness, quality, professionalism, and compliance with award terms. This payment plan appears to be part of the Garrett A. Morgan Technology and Transportation Education Program (GAMTTEP) grant opportunity, which has a total funding availability of $1.8 million with individual awards up to $300,000.
Attachment 1 - Milestone Payment Plan
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GAMTTEP Signed NOFO.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 1
MILESTONE PAYMENT PLAN
The Recipient may request payment in accordance with the following Fixed Amount Milestone
Payment Plan. Upon successful completion of the following milestones, the Recipient may submit a Request for Fixed Amount Payment as shown below. FHWA will make payment based on determination that the Recipient has successfully completed of the following milestones.
Acceptable completion shall be evaluated by FHWA based on timeliness, quality, professionalism, and compliance with the award terms.
NOTE: Under a fixed amount award, the Recipient is NOT required to report actual costs incurred to the Government. Rather, the Recipient will be paid the fixed amounts listed below for acceptable completion of the milestones, and in compliance with the terms of the award.
FIXED AMOUNT MILESTONE PAYMENT PLAN
Milestone Due Date Fixed Amount
(to be filled in at award)
Task A: Kick-off Meeting – conduct a virtual kick-off meeting with FHWA at a mutually-agreed-upon time. Kick-off
Meeting is estimated not to exceed 2 hours. (Quantity: 1)
Within 3 weeks after the effective date of award.
$(to be filled in at award)
Task B: Draft Project Summary for the website. The
FHWA will provide comments to the Recipient within 30 calendar days after receipt of the proposed updates, for which the Recipient will have 15 calendar days to revise.
(Quantity: 1)
10 months after the effective date of award.
$(to be filled in at award)
Task B: Quarterly Project Updates for the website. Year 2 quarters 1-3. (Quantity: 3) During Year 2 only, due within 30 days after the end of each quarter, Year 2 quarters 1 -3.
$(to be filled in at award)
Reporting: Quarterly Progress Reports – document activities performed, anticipated activities, and any changes to schedule or anticipated issues. See Quarterly Progress Report clause for required content. (Quantity: 8)
Within 30 days of the end of each quarter.
$(to be filled in at award)
Reporting: Annual Budget Review and Program Plan (for
Year 2) – provide a detailed schedule of activities, estimate of specific performance objectives, and schedule of milestones for the upcoming year (for Year 2). See Annual
Review and Program Plan clause for required content.
(Quantity: 1)
60 days prior to the anniversary date of this agreement.