DEPARTMENT OF THE NAVY

HAWAII RMC PEARL HARBOR HI

SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED

SPECIFICATION NUMBER: HRMC-012-21

INCLUDES ALL CHANGES THROUGH 4/14/2021

INDEX

HRMC-012-21

ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.

CATEGORY I. FY-21 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.

ITEM NO. TITLE CHANGE DATE CHANGE

009-01 General Criteria; accomplish 10/01/2019 Original

009-02 Environmental Compliance Report for Material Usage; accomplish 10/01/2019 Original

009-03 Toxic and Hazardous Substance; control 10/01/2019 Original

009-04 Quality Management System; provide 10/01/2019 Original

009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;

accomplish

03/06/2020 CH-2

009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping;

accomplish

07/24/2019 Original

009-08 Shipboard Fire Protection and Fire Prevention; accomplish 10/01/2019 Original

009-10 Asbestos-Containing Material (ACM); control 10/01/2019 Original

009-18 Mine Warfare Ships Magnetic Material; control 04/30/2018 Original

009-19 Provisioning Technical Documentation (PTD); provide 10/01/2018 Original

009-20 Government Property; control 10/01/2017 Original

009-21 Logistics and Technical Data; provide 10/01/2018 Original

009-23 Interference; remove and install 10/01/2018 Original

009-24 Authorization, Control, Isolation, Blanking, Tagging, and Cleanliness;

accomplish

10/01/2019 Original

009-34 Fire Protection of Unmanned Vessel at Contractor Facility; accomplish 10/01/2018 Original

009-39 Technical Manual Contract Requirement (TMCR) for a New Technical Manual for Commercial Equipment/Component; accomplish

10/01/2018 Original

009-40 Contractor Crane, Multi-Purpose Machine and Material Handling Equipment at a Naval Facility; provide

10/01/2019 Original

009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration;

provide and manage

01/14/2020 CH-1

009-61 Shipboard Use of Fluorocarbons; control 07/18/2014 Original

009-67 Integrated Total Ship Testing; manage 04/30/2018 Original

009-69 Heavy Weather/Mooring Plan; provide 04/30/2018 Original

009-70 Confined Space Entry, Certification, Fire Protection, Fire Prevention and

Housekeeping for Unmanned Vessels; accomplish

10/01/2019 Original

009-72 Physical Security at a Private Contractor Facility; accomplish 10/01/2019 Original

009-73 Shipboard Electrical/Electronic Cable Procedure; inspect, test, install, remove, and repair

10/01/2018 Original

009-74 Occupational, Safety and Health Plan; accomplish 01/14/2020 CH-1

009-80 Ship Facilities; maintain 11/18/2016 Original

009-81 Compartment Closeout; accomplish 10/01/2019 Original

009-82 Installation of Equal Component Vice Specified Component; report 03/26/2018 Original

009-84 Threaded Fastener Requirements; accomplish 03/06/2020 CH-2

009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution

Prevention Act (PPA) Information; provide

03/06/2018 Original

009-99 Ship Departure Report; provide 07/18/2014 Original

009-100 Ship's Stability; maintain 03/06/2018 Original

ITEM_NO. TITLE CHANGE DATE CHANGE

009-101 Ship Transit and Berthing; accomplish 03/26/2018 Original

009-106 Work Authorization Form Coordinator (WAFCOR); provide 10/01/2017 Original

009-109 Non-SUBSAFE Work on SUBSAFE-Certified Vessel; accomplish 10/01/2017 Original

009-110 Non-Nuclear Work on a Nuclear Vessel; accomplish 11/18/2016 Original

009-111 Schedule and Associated Reports for Availabilities 9 Weeks or Less in

Duration; provide and manage

04/30/2018 Original

009-117 Combat Systems, Light-Off Suport; provide 10/01/2019 Original

009-118 CG Deck Loading; accomplish 07/18/2014 Original

009-120 Fact Finding and Critique of Unplanned Event; manage 03/06/2018 Original

009-122 Temporary Padeye; install and remove 10/01/2018 Original

009-125 Boats Less Than 65 Feet Long; accomplish 07/11/2020 CH-3

ITEM NO. TITLE

Hazardous Waste Produced on Naval Vessels; control077-11-001

Supply and Exhaust Ventilation Cleaning; accomplish512-11-001

ITEM NO: 512-11-001

COAR: 26 PCN: EA01-8512

CMP: NONE

PLANNER:

SSP: HRMC-012-21 1 of 2 ITEM NO: 512-11-001

1. SCOPE:

1.1 Title: Supply and Exhaust Ventilation Cleaning; accomplish

1.2 Location of Work:

1.2.1 Forward Compartment

1.2.1.1 Throughout First, Second, and Third Platforms, Forward of Frame 65

1.2.2 Engine Room

1.2.2.1 Throughout First, Second, and Third Platforms, Frame 76 to Frame 125

1.3 Identification:

1.3.1 Quantity (One EA), Main Induction Supply Ventilation System 1

1.3.2 Quantity (One EA), Main Induction Supply Ventilation System 2

1.3.3 Quantity (One EA), Recirculation Supply Ventilation System 3

1.3.4 Quantity (One EA), Recirculation Supply Ventilation System 4

1.3.5 Quantity (One EA), Recirculation Supply Ventilation System 5

1.3.6 Quantity (One EA), Recirculation Supply Ventilation System 6

1.3.7 Quantity (One EA), Exhaust Ventilation System 7

1.3.8 Quantity (One EA), Exhaust Ventilation System 8

1.3.9 Quantity (One EA), Battery Compartment Exhaust Ventilation System 9

1.3.10 Quantity (One EA), Recirculation Supply Ventilation System 12

1.3.11 Quantity (One EA), Recirculation Supply Ventilation System 13

1.3.12 Quantity (One EA), Recirculation Supply Ventilation System 14

1.3.13 Quantity (One EA), Recirculation Supply Ventilation System 15

1.3.14 Quantity (One EA), Recirculation Supply Ventilation System 16

1.3.15 Quantity (One EA), Recirculation Supply Ventilation System 17

1.3.16 Quantity (One EA), Recirculation Supply Ventilation System 18

1.3.17 Quantity (One EA), Recirculation Supply Ventilation System 19

1.3.18 Quantity (One EA), Recirculation Supply Ventilation System 20

1.3.19 Quantity (One EA), Recirculation Supply Ventilation System 21

1.3.20 Quantity (One EA), Recirculation Supply Ventilation System 22

1.3.21 Quantity (One EA), Recirculation Supply Ventilation System 23

2. REFERENCES:

2.1 Standard Items, (FY-22)

2.2 501-6225483 Rev B, VENT GALLEY & MESS

SSP: HRMC-012-21 2 of 2 ITEM NO: 512-11-001

2.3 501-6225480 Rev D, VENT CREW LIVING SP ENGNRS OFFICES LAUNDRY & WR

SP 3RD PLATF FR 46-51 PLAN LIST SECT & ELEV

2.4 501-4457545 Rev Z, VENTILATION GEN NOTES STD DET

2.5 501-6986983 Rev J, VENTILATION DIAGRAM 1ST, 2ND, & 3RD PLATFORM

2.6 NAVSEA LETTER 9514 SER 9210/021 DTD 20 MAY 2009, DRY ICE CLEANING OF

VENTILATION DUCTS

3. REQUIREMENTS:

3.1 Accomplish “DRY ICE” cleaning of the interior of supply and exhaust ventilation systems listed in 1.3 and located in 1.2.

3.1.1 Accomplish the requirements of 009-09 of 2.1 for submittal of PCP for NAVSEA approval prior to start of work.

3.1.2 Matchmark and remove ventilation access plates as required, to allow access for cleaning operations. Retain ventilation parts and fasteners for reuse.

3.1.3 Clean ventilation interior surfaces free of loose rust, dirt, grease, lint and other foreign matter.

3.1.4 Accomplish the requirements of 2.6 for the CO2 and O2 and monitoring of all spaces prior to, during, and after all vent cleaning operations.

(V)(G) "CLEANLINESS INSPECTION"

3.2 Accomplish a visual inspection prior to and after cleaning of interior surfaces of each ventilation system listed in 1.3 for verification of cleanliness and completion of work prior to reinstallation of access plates removed in 3.1.2.

3.2.1 Submit one legible copy, in approved transferrable media, of a report listing results of the requirements of 3.3 to the SUPERVISOR.

3.3 Accomplish the reinstallation of matchmarked ventilation components removed in 3.1.2, using retained fasteners and 2.2 through 2.5 for guidance.

3.4 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces to match surrounding areas.

4. NOTES:

4.1 None

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

5.3 KITTED MATERIAL:

1. None.