Attachment 1 - FY27 Hopper Groupings_Industry Day.xlsx
XLSX spreadsheet 35 KB Posted
- Solicitation number
- W912PM27HOPPR
About this file
This is a hopper dredging contract groupings document that organizes proposed consolidated dredging projects by geographic district for the U.S. Army Corps of Engineers (USACE) National Enterprise Dredging Center. The document lists nine groupings of hopper dredging and beach nourishment projects scheduled across FY27-28, distributed among nine districts: Norfolk, Jacksonville, New Orleans, Mobile, Portland, San Francisco, Philadelphia, Savannah, Charleston, Wilmington, Baltimore, and New York. Projects are categorized as either maintenance dredging or beach nourishment work, with estimated dredging quantities ranging from 250,000 to 11,000,000 cubic yards or hours. Bid open dates span from December 2026 through August 2027, with expected award dates ranging from December 2026 through September 2027 and performance periods extending through April 2028.
The groupings specify hopper dredges as the primary or exclusive equipment type for all projects, with some locations also accepting bucket or pipeline dredges. Dredged material placement is designated for open-water placement, beach/shoreline nourishment, or confined diked placement depending on project location. Key project locations include Thimble Shoal Channel (Norfolk), Jacksonville Harbor, Calcasieu Bar, Mississippi River corridors, Lower Columbia River, Humboldt Bar, various beach nourishment projects in the Philadelphia district (Cape May, Absecon Island, Barnegat Inlet, Rehoboth, Bethany, Fenwick Island), and Savannah and Charleston harbors. The Sources Sought Notice accompanying this document indicates firms must register in the System for Award Management (SAM) and submit equipment documentation, firm information, and socioeconomic designations by September 4, 2026, at 1500 EST.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hopper List
| Row Labels |
| Baltimore |
| BALTIMORE HARBOR AND CHANNELS (50 FOOT), MD |
| Charleston |
| (blank) |
| Jacksonville |
| JACKSONVILLE HARBOR, FL |
| KINGS BAY ENTRANCE CHANNEL |
| NAVAL STATION MAYPORT |
| Los Angeles |
| WORK FOR OTHERS |
| Mobile |
| FY27 GULF COAST REG HOPPER #1 |
| New Orleans |
| CALCASIEU RIVER AND PASS, LA |
| MISSISSIPPI RIVER, BATON ROUGE TO THE GULF OF MEXICO, LA |
| MISSISSIPPI RIVER, BATON ROUGE TO THE GULF OF MEXICO, LA;CALCASIEU RIVER AND PASS, LA |
| Norfolk |
| NORFOLK HARBOR, VA |
| Philadelphia |
| BRIG. INL TO GRT EGG INL N.J. |
| DE. COAST FROM HENLOPEN TO FENWICK ISLAND, DE |
| DEL COAST CAPE HENL. TO FENWICK |
| DELAWARE COAST BETHANY/S. BETHANY |
| MANASQUAN INLET TO BARNEGAT |
| NJ COASTAL INLETS&BEACHES, CAPE MAY-LOWER TWNSHP |
| Portland |
| COLUMBIA AND LOWER WILLAMETTE RIVERS BELOW VANCOUVER, WA & PORTLAND, OR |
| COLUMBIA RIVER AT THE MOUTH, OR & WA |
| COOS BAY, OR |
| San Francisco |
| HUMBOLDT HARBOR AND BAY, CA |
| OAKLAND HARBOR, CA |
| Savannah |
| BRUNSWICK HARBOR, GA;WILMINGTON HARBOR, NC;SAVANNAH HARBOR, GA |
| Wilmington |
| (blank) |
| (blank) |
| MOREHEAD CITY HARBOR, NC |
| (blank) |
| Grand Total |
Hopper Nav-CSRM Detail
| Potential Groupings (Not Prioirty) | District Name | Job Name | Class(es) of Work | Advertising Date | Bid Open Date | Expected Award Date | Estimated Period of Performance Start Date | Estimated Period of Perfromance End Date | Expected Dredge Types | Estimated Total Dredging Quantity (CY) | Expected Pay Measure | Dredged Material Placement Categories |
| 1 | Norfolk | THIMBLE SHOAL CHANNEL | Maintenance Dredging | 11/6/26 | 12/8/26 | 2/11/27 | 3/5/27 | 8/31/27 | Bucket;Hopper | 1,570,000 | Cubic yards | Beach/Shoreline Nourishment; Construction and Industrial/Commercial Uses; Open-Water Placement |
| 1 | Jacksonville | JACKSONVILLE HARBOR, FL | Maintenance Dredging | 10/13/26 | 11/12/26 | 12/15/26 | 2/15/27 | 8/15/27 | Bucket;Hopper | 750,000 | Cubic yards | Confined (Diked) Placement |
| 2 | New Orleans | CALCASIEU BAR HD 1-25 | Maintenance Dredging | 11/2/26 | 12/2/26 | 12/17/26 | 1/15/27 | 4/15/27 | Hopper | 6,000,000 | Hours | Open-Water Placement |
| 2 | Mobile | FY27 Mobile District IDIQ - Pascagoula | Maintenance Dredging | 12/15/26 | 1/15/27 | 2/15/27 | 4/1/27 | 9/30/27 | Hopper | 500,000 | Hours | Open-Water Placement |
| 2 | Mobile | FY27 Mobile District IDIQ - Panama City | Maintenance Dredging | 12/15/26 | 1/15/27 | 2/15/27 | 8/1/27 | 9/30/27 | Hopper | 250,000 | Hours | Open-Water Placement |
| 2 | New Orleans | MISS RIVER HD 1-27 | Maintenance Dredging | 12/18/26 | 6/10/27 | 6/30/27 | 2/1/28 | 8/31/28 | Hopper | 10,000,000 | Hours | Open-Water Placement |
| 3 | Portland | WCH MAINTENANCE DREDGING - LOWER COLUMBIA RIVER | Maintenance Dredging | 1/22/27 | 3/1/27 | 3/22/27 | 6/15/27 | 11/15/27 | Hopper | 1,470,000 | Cubic yards | Open-Water Placement |
| 3 | San Francisco | WCH MAINTENANCE DREDGING - HUMBOLDT BAR & ENTRANCE | Maintenance Dredging | 1/22/27 | 3/1/27 | 3/22/27 | 6/1/27 | 11/15/27 | Hopper | 900,000 | Cubic yards | Open-Water Placement |
| 3 | Portland | WCH MAINTENANCE DREDGING - MOUTH OF THE COLUMBIA RIVER | Maintenance Dredging | 1/22/27 | 3/1/27 | 3/22/27 | 4/1/27 | 11/15/27 | Hopper | 1,720,000 | Cubic yards | Beach/Shoreline Nourishment; Open-Water Placement |
| 3 | Portland | WCH MAINTENANCE DREDGING - COOS BAY | Maintenance Dredging | 1/22/27 | 3/1/27 | 3/22/27 | 4/1/27 | 11/15/27 | Hopper | 400,000 | Cubic yards | Beach/Shoreline Nourishment; Open-Water Placement |
| 3 | Los Angeles | Pt. Mugu Beach Nourishment | Beach Nourishment | 6/8/27 | 7/7/27 | 8/11/27 | 9/15/27 | 3/1/28 | 600,000 | Beach/Shoreline Nourishment | ||
| 4 | Jacksonville | MAYPORT O&M | Maintenance Dredging | 2/9/27 | 3/11/27 | 4/12/27 | 6/15/27 | 12/30/27 | Bucket;Hopper | 1,000,000 | Cubic yards | Open-Water Placement |
| 4 | Jacksonville | KINGS BAY ENTRANCE CHAN O&M | Maintenance Dredging | 7/9/27 | 8/10/27 | 9/15/27 | 12/15/27 | 3/31/28 | Hopper | 1,200,000 | Cubic yards | Open-Water Placement |
| 5 | New Orleans | MISS RIVER & CALCASIEU BAR HD | Maintenance Dredging | 12/18/26 | 7/15/27 | 7/30/27 | 1/10/28 | 7/31/28 | Hopper | 11,000,000 | Hours | Open-Water Placement |
| 6 | Philadelphia | Cape May Inlet to Lower Twp | Beach Nourishment | 6/4/27 | 7/22/27 | 8/5/27 | 10/1/27 | 1/30/28 | Hopper | 500,000 | Cubic yards | Beach/Shoreline Nourishment |
| 6 | Philadelphia | ABSECON ISLAND | Beach Nourishment | 2/13/27 | 3/16/27 | 4/2/27 | 6/1/27 | 11/30/27 | Hopper;Pipeline | 1,400,000 | Cubic yards | Beach/Shoreline Nourishment |
| 6.1 | Philadelphia | Barnegat Inlet to Little Egg Inlet, NJ | Beach Nourishment | 5/3/27 | 6/4/27 | 6/18/27 | 8/1/27 | 3/30/27 | Hopper | 1,800,000 | Cubic yards | Beach/Shoreline Nourishment |
| 7 | Savannah | Savannah Harbor Entrance Channel Maintenance Dredging | Maintenance Dredging | 7/9/27 | 8/18/27 | 9/15/27 | 12/15/27 | 3/31/28 | Hopper | 950,000 | Cubic yards | Open-Water Placement |
| 7 | Charleston | FY 27 RHDC Charleston District | Maintenance Dredging | 6/17/27 | 7/16/27 | 9/17/27 | 12/15/27 | 3/31/28 | Hopper | 1,500,000 | Cubic yards | Open-Water Placement |
| 7 | Wilmington | FY27-28 SAD REGIONAL HARBOR 11.1 - WILMINGTON | Maintenance Dredging | 6/30/27 | 8/3/27 | 9/5/27 | 12/1/27 | 4/15/28 | Hopper | 900,000 | Cubic yards | Open-Water Placement |
| 8 | Philadelphia | REHOBOTH/ DEWEY BEACHES | Beach Nourishment | 4/1/27 | 5/3/27 | 5/17/27 | 7/1/27 | 10/30/27 | Hopper | 500,000 | Cubic yards | Beach/Shoreline Nourishment |
| 8 | Philadelphia | BETHANY & SOUTH BETHANY | Beach Nourishment | 4/1/27 | 5/3/27 | 5/17/27 | 7/1/27 | 10/30/27 | Hopper | 700,000 | Cubic yards | Beach/Shoreline Nourishment |
| 8.1 | Philadelphia | Fenwick Island | Beach Nourishment | 4/1/27 | 5/3/27 | 5/17/27 | 7/1/27 | 10/30/27 | Hopper | 300,000 | Cubic yards | Beach/Shoreline Nourishment |
| 9 | Savannah | Brunswick Harbor Entrance Channel Maintenance Dredging | Maintenance Dredging | 7/9/27 | 8/18/27 | 9/15/27 | 12/15/27 | 3/31/28 | Hopper | 1,600,000 | Cubic yards | Open-Water Placement |
| 9 | Wilmington | FY27-28 SAD REGIONAL HARBOR 11.2 - MOREHEAD CITY | Maintenance Dredging | 7/19/27 | 8/20/27 | 9/24/27 | 12/1/27 | 4/15/28 | Hopper | 500,000 | Cubic yards | Open-Water Placement |
| 9 | Baltimore | Baltimore Harbor and Channels (York Spit) | Maintenance Dredging | 8/1/27 | 9/1/27 | 10/15/27 | 11/15/27 | 4/13/28 | Hopper | 1,500,000 | Cubic yards | Open-Water Placement |
| TBD | New York | Fire Island Inlet to Montauk Point (FIMP), NY - Contract 3B - Southampton | Beach Nourishment | 4/15/27 | 6/15/27 | 7/15/27 | 11/15/27 | 3/15/28 | Hopper | 1,700,000 | Cubic yards | Beach/Shoreline Nourishment |
File details come from the government source that posted it. Updated .