ATTACHMENT 1 - FY20 Road 5-31.2 Schedule of Items (1).xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- Road Construction IDIQ - Amendment 3 Federal contract opportunity
- Solicitation number
- 12467020R0033
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12467020R0033 Body - Amendment 3.doc | DOC document | |
| 12467020R0033 Amendment 3 - SF-30.pdf | ||
| 12467020R0033 Amendment 2 - SF-30.pdf | ||
| SF 30 Amendment 1 to Solicitation 12467020R0033.pdf | ||
| 12467020R0033 Body - Amendment 1.doc | DOC document | |
| 12467020R0033 SF1442 - Amendment 1.pdf | ||
| Site Visit Briefing 12467020R0033.pdf | ||
| Sign In Sheet.pdf | ||
| ATTACHMENT 2 - Statement Of Work_P-Area (1).docx | DOCX document | |
| 12467020R0033 Body.doc | DOC document | |
| ATTACHMENT 3 - FY20 Road 5-31.2 Drawings (1).pdf | ||
| ATTACHMENT 6 - Special SR Requirements.docx | DOCX document | |
| ATTACHMENT 7 - Relevant Experience Questionaire.doc | DOC document | |
| 12467020R0033 SF1442.pdf | ||
| ATTACHMENT 4 - FY20 Road 5-31.2 Stakeout Points (1).xlsx | XLSX spreadsheet | |
| ATTACHMENT 5 - DOL Wage Determination.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedulle of Items
| SOLICITATION 12467020R0033 | |||||
| ATTACHMENT 1 - DETAILED SCHEDULE OF ITEMS | |||||
| FY20 Road 5-31.2 Construction Project | |||||
| **All mobilization costs shall be incidental to each pay item. This work consists of moving personnel, equipment, supplies, material, and incidentals to the project and performing work necessary within each pay item shown in Schedule of Items. The SRS is approx. 309.26 square miles in area. | |||||
| Item No. | Description | Estimated Quantity | Pay Unit | Unit Price | Unit Total |
| 15702 | Silt fence (Inlcudes furnishing, installation, and removal and disposal after final acceptance of project. Silt fencing geotextile and posts (wood or steel) shall conform to FP-14 Section 713.16… Submittal required. Place silt fence on both sides of roadway at boundary of clearing limits (typical. to both sides) or as appointed by C.O. and C.O.R.) | 364 | Foot | $ - 0 | $ - 0 |
| 20102 | Clearing and grubbing, disposal method scattering (Includes all clearing and grubbing, also includes excavating up all tree stumps including additional two (2) trees identified on existing trail, 14-ft roadside vertical clearance of existing trail and scattering all slash on site. Place all slash perpendicular to slopes) | 0.11 | Acre | $ - 0 | $ - 0 |
| 20431 | New Roadway Embankment construction w/ construction tolerance class FSSS Table 204-2 (D), includes: subgrade grading, and roadway compaction placement method FP-14 Section 204.11(a)(1) (Includes: constructing 14-ft wide roadway, includes up to 4-ft of embankment excavation or embankment fill construction, 1-ft nominal depth of new ditch construction on both sides of roadway, 1V:3H embankment backslopes/cutslopes or embankment fill slope construction, subgrade grading, and subgrade compaction in NTE compaction layers lifts of 12-inches loose depth) | 2 | Station (1+00.00) | $ - 0 | $ - 0 |
| 30103 | Aggregate base, grading GABC compaction method FP-14 Section 204.11(a)(1) (Inlcudes furnishing, placement, and compacting. Includes 4-inch depth placement of aggregate for finished road surface) | 77 | Ton | $ - 0 | $ - 0 |
| 62201(c) | Water truck, 4,000 gallon minimum and pressurized; w/ operator (Includes watering new roadway subgrade and base rock for compaction) | 8 | Hour | $ - 0 | $ - 0 |
| 65204 | Seeding and Fertilizer, dry method | 0.06 | Acre | $ - 0 | $ - 0 |
| 62505 | Mulching, dry method | 0.06 | Acre | $ - 0 | $ - 0 |
| 63501 | Temporary traffic control | 1 | Lump Sum | $ - 0 | $ - 0 |
| TOTAL PRICE: | $ - 0 |