v2.6 – MAY2021
PR # 1300933291
STATEMENT OF WORK
(SOW)
DT-705A Sensor Assemblies Production Contract
PR No. 1300933291
1.0 Background
The Fleet Sensors & Cables Engineering Branch (Code 1535) of the Sensors and Arrays
Division (Code 153) of the Naval Undersea Warfare Center Division Newport serves as the
Navy's Technical Design Agent (TDA), and In-Service Engineering Agent (ISEA) and assists with Acquisition Engineering Agent (AEA) activities for surface ship and submarine transducers, hydrophones, and sensor assemblies (collectively referred to as transducers).
Code 1535 maintains the Navy's transducer inventory in large part by establishing contract vehicles to procure transducers that are delivered both to the stock system to support emergent fleet needs and to new construction shipyards for initial outfitting.
1.1 Places of Performance
All work will be performed at the contractor’s facility or a facility that the contractor specifically arranges.
1.2 Authorized Users
This contract is applicable to the Sensors and SONAR Department, Code 15, of the Naval
Undersea Warfare Center Division Newport, RI.
1.3 Sponsors
• PMS 401 Submarine Acoustic Systems
• PMS 450 Virginia Class Program Office
• PMS 397 Columbia Class Program Office
• FMS Foreign Military Sales Office
• Type Commanders
• Naval Shipyards
1.4 Types of Funding
• Operation & Maintenance, Navy (O&MN)
• Other Procurement, Navy (OPN)
• Research, Development, Test & Evaluation, Navy (RDT&EN)
• Shipbuilding and Conversion, Navy (SCN)
• National Sea-Based Deterrence Fund (NSBDF)
• Foreign Military Sales (FMS)
2.0 Scope
This SOW reflects a build-to-performance specification approach. The contractor shall design, document, manufacture, test, package, and deliver DT-705A First Article and Production Sensor
Assemblies that meet the performance requirements of the DT-705A Sensor Assembly Critical
Item Performance Specification (CIPS).
3.0 Applicable Documents
The contractor shall perform the tasking required in Section 4.0 in accordance with the below
Applicable Documents.
3.1 NAVSEA Drawing No. 53711-
7333534L
Critical Item Performance Specification
(CIPS) for the DT-705A Sensor Assembly
3.2 NUWC Drawing 50225-00267RD Configuration Management Engineering
Drawing Requirements
3.3 NUWC Drawing 50225-00266MN Configuration Management Engineering
Change Document Manual
4.0 Technical Requirements
The contractor shall design, document, manufacture, test, package, and deliver First
Article and Production DT-705A Sensor Assemblies that meet the requirements of
Applicable Document (AD) 3.1. Table 1 defines the requirements for this procurement.
The following terms apply throughout this requirements section:
Configuration Item The configuration items (CI) for this contract is the DT-705A
Sensor Assembly.
Functional Baseline The Functional Baseline is established at contract award and is defined by AD 3.1.
First Article Baseline The First Article Baseline is established prior to First Article testing and consists of the engineering drawings and applicable revisions that define the CI.
Product Baseline The Product Baseline is established upon completion of the
Functional and Physical Configuration Audits (FCA and PCA) and consists of the engineering drawings and applicable revisions that define the CI.
Table 1. Requirements
Task Task Description
Contract
Timeframe Deliverable
4.1 GENERAL
4.1.1 Contract Kick-Off
Meeting
The contractor shall conduct a Contract Kick-Off meeting at its facility. The contractor shall prepare the kick-off meeting agenda. The contractor shall present its planned configuration and present a
Program Objectives and Milestone Schedule
(POAMS) for the First Article and Production phases to include:
- tasks and milestones
- requirements review
- data submittals
- schedule
The contractor shall prepare meeting minutes and shall submit the POAMS with the meeting minutes.
Within 45 days after contract award
CDRL A001
DI-ADMN-81249B (Agenda)
CDRL A002
DI-ADMN-81250B
(Meeting Minutes)
4.1.2 Progress Reports The contractor shall prepare and submit Progress
Reports using Government Furnished Information
(GFI) item 5.1.
Monthly over the life of the contract
CDRL A003
DI-MGMT-81867 (Production
Progress Report)
4.1.3 Failure Reports The contractor shall have a system to handle all material it determines to be non-conforming. This system shall also handle all sensor assemblies that fail a First Article or Production Acceptance test.
The contractor shall submit Failure Summary and
Analysis reports that identify the nature of the failure, and identify remedial and corrective action for preventing future occurrences.
System to handle all non-conforming material shall be in effect for the life of the contract
CDRL A004
DI-SESS-80255A (Failure
Summary and Analysis Report)
4.2 DT-705A SENSOR
ASSEMBLY FIRST
ARTICLE PHASE
4.2.1 DT-705A Sensor
Assembly First Article
Hardware
The contractor shall design, document, inspect, fabricate, test, package and deliver First Article
DT-705A Sensor Assemblies. The contractor shall sequentially serialize the First Article sensor assemblies starting with FA001. The contractor shall fabricate the First Article DT-705A Sensor
Assemblies to meet the performance requirements of applicable document 3.1.
Prior to fabrication, the contractor shall perform
100% inspection of all incoming parts for First
Article sensor assemblies. The contractor shall record variables data for all dimensions specified on the drawings for all first article parts. The contractor shall have this information available at the First Article Physical Configuration Audit (see section 4.2.4).
Defined in
Delivery
Orders (DO)
Applicable Deliverables identified in subsequent sections.
Task Task Description
Contract
Timeframe Deliverable
4.2.2 DT-705A Sensor
Assembly Preliminary
Configuration Review
(PCR)
The contractor shall conduct a PCR via Video
Teleconference (VTC), conference call, or other remotely enabled delivery system. The purpose of the PCR is to evaluate the technical adequacy of the contractor's preliminary build configuration in meeting the Functional Baseline requirements.
Prior to the PCR, the contractor shall deliver the top level drawing in NAVSEA format in accordance with applicable document 3.2 and using GFI items 5.2 and 5.3.
Within 90 days after First
Article sensor assemblies delivery order award.
CDRL B001
NUWC DRAWING 50225-
00267RD (Top Level Drawing -
Product Drawings and
Associated Lists)
4.2.3 DT-705A Sensor
Assembly Final
Configuration Review
(FCR)
The contractor shall conduct an FCR at its facility.
The purpose of the FCR is to evaluate the technical adequacy of the contractor's final build configuration in meeting the Functional Baseline requirements. At the FCR, the contractor shall be prepared to review:
- the drawing package
- manufacturing flow chart which identifies the manufacturing build steps, in-process steps and inspection points and final production acceptance tests
- POAMS
- Any risks and mitigation plans if applicable
The contractor shall deliver the complete drawing package in NAVSEA format in accordance with applicable document 3.2 and using GFI items 5.2 and 5.3.
The contractor shall resolve all technical discrepancies noted at the PCR and FCR prior to delivering First Article sensor assemblies. The contractor shall provide the Government copies of all changes that occur subsequent to the FCR.
After PCR and prior to delivering
First Article sensor assemblies
CDRL B001
NUWC DRAWING 50225-
00267RD (Product Drawings and Associated Lists)
4.2.4 DT-705A Sensor
Assembly First Article
Physical Configuration
Audit (FA-PCA)
The contractor shall conduct an FA-PCA. The purpose is for the Government to validate that the components that comprise the First Article sensor assemblies match the technical documentation and that all key processes are properly documented.
The contractor shall have copies of the drawing package available for audit team members at the
FA-PCA. The contractor shall have all First
Article piece parts available and shall provide the incoming inspection variables data for all the parts.
The contractor shall deliver any drawings that have changed since the FCR (which includes changes resulting from discrepancies identified at the PCR and FCR).
Prior to First
Article sensor assembly fabrication
CDRL B001
NUWC DRAWING
50225-00267RD
(Product Drawings and Associated Lists)
Task Task Description
Contract
Timeframe Deliverable
4.2.5 DT-705A Sensor
Assembly First Article
Test Procedures
The contractor shall develop First Article test procedures for contractor-performed tests and inspections in accordance with applicable document 3.1. The contractor shall include applicable acceptance and rejection criteria for
First Article tests and inspections to ensure that the
CI meets the requirements.
Prior to First
Article testing
CDRL A005
DI-NDTI-80603A (First Article
Acceptance Test Procedures)
4.2.6 DT-705A Sensor
Assembly First Article
Baseline Configuration
The contractor shall document changes to the CI that occur between FA-PCA and First Article (FA) testing and include that information in the First
Article Baseline Report.
Upon successful FA-
PCA and prior to commencing
First Article testing
CDRL A006
DI-MISC-80508B (First Article
Baseline Report)
CDRL B001
NUWC DRAWING
50225-00267RD
(Product Drawings and Associated Lists)
4.2.7 DT-705A Sensor
Assembly First Article
Test and Inspection
The contractor shall verify that the First Article sensor assemblies meet the CIPS requirements by performing First Article tests and inspections using the test procedures developed in SOW section
4.2.5. In the event that any First Article unit fails
to meet CIPS requirements, the contractor shall be responsible for redesign, rework, retest, and First
Article unit replacement. The contractor shall submit a First Article Test Report detailing the contractor-performed First Article tests and corresponding test results for each First Article sensor assembly identified by serial number.
Test Report upon completion of contractor-performed
First Article testing
CDRL A007
DI-NDTI-80809B (First Article
Test Report)
CDRL A004
Summary and Analysis Report)
4.2.8 DT-705A Sensor
Assembly Functional
Configuration Audit
(FCA) and Physical
Configuration Audit
(PCA)
The contractor shall conduct a concurrent FCA and PCA at its facility. The FCA is to verify that the CI is compliant with the CIPS; the PCA is to verify that the First Article CI conforms fully to the First Article Baseline. The contractor shall have the following documentation available for auditing at the FCA/PCA:
- The complete drawing package
- Inspection/Test Flow Chart with inspection/test criteria and procedures
- Manufacturing methods and process sheets
- Incoming inspection control procedures
- Production acceptance test procedures
- Test method sheets and standards selection procedures describing operation and calibration of test equipment
- Non-standard parts and parts requiring source control
Upon
Government
First Article testing completion
CDRL A001
DI-ADMN-81249B (Agenda)
DI-ADMN-81250B (Meeting
Minutes)
Task Task Description
Contract
Timeframe Deliverable
- Material Review Board (MRB) and
Failure Review Board (FRB) process and procedures
The contractor shall deliver the complete drawing package in NAVSEA format in accordance with applicable document 3.2 and using GFI items 5.2 and 5.3. The complete drawing package includes changes resulting from discrepancies identified at the PCR, FCR, FA-PCA, and during FA testing phase.
4.2.9 DT-705A Product
Baseline Configuration
The contractor shall establish the Product
Baseline. The contractor shall deliver the final drawing package in NAVSEA format in accordance with applicable document 3.2 and using GFI items 5.2 and 5.3.
Upon successful
FCA and PCA
CDRL B001
NUWC DRAWING 50225-
00267RD (Product Drawings and Associated Lists)
4.3 DT-705A SENSOR
ASSEMBY
PRODUCTION PHASE
4.3.1 DT-705A Sensor
Assembly Production
Hardware
The contractor shall manufacture, test, package and deliver Production sensor assemblies to meet the performance requirements of applicable document 3.1 and the Product Baseline. The contractor shall serialize the production sensor assemblies in accordance with GFI item 5.4.
Defined in
Delivery Order
Applicable Deliverables identified in subsequent sections.
4.3.2 DT-705A Sensor
Assembly Production Test and Inspection
The contractor shall develop Production
Acceptance Test Procedures in accordance with applicable document 3.1. The contractor shall perform final acceptance testing of all production hardware items prior to delivery to the
Government. Through acceptance testing, the contractor shall ensure that all DT-705A Sensor
Assemblies meet the requirements of applicable document 3.1 and the Product Baseline.
During active production
CDRL A008
DI-NDTI-80603A (Production
Acceptance Test Procedures)
4.3.3 DT-705A Sensor
Assembly Production
Acceptance Test and
Inspection Reports
The contractor shall record actual test results for each production unit by serial number, including date of acceptance by the Government. In the
Production Acceptance and Inspection Reports, the contractor shall identify units that failed
Production Acceptance Tests or were otherwise accepted only after rework and retest and shall explain the circumstances and corrective actions taken where rework occurred.
During active production
CDRL A009
DI-NDTI-80809B (Production
Acceptance Test and Inspection
Data)
CDRL A004
Summary and Analysis Report)
4.3.4 DT-705A Sensor
Assembly Certification
Card
The contractor shall complete a Certification Card for each DT-705A Sensor Assembly to be delivered in accordance with applicable document
3.1. Certification cards submitted to the
Government shall be in electronic format.
During active production
CDRL A00A
NAVSEA DWG. No. 53711-
7333534K
(Transducer/Hydrophone
Certification Card)
Task Task Description
Contract
Timeframe Deliverable
4.3.5 Production Program
Reviews (PPRs)
The contractor shall conduct Production Program
Reviews annually. The purpose of the PPRs is to review programmatic and technical issues.
During active production
CDRL A001
DI-ADMN-81249B
(Agenda)
DI-ADMN-81250B (Meeting
Minutes)
4.3.6 Engineering
Changes
The contractor shall prepare Engineering Change
Documents in accordance with applicable document 3.3.
As required during production
CDRL A00B, A00C
DI-SESS-80639D,
DI-SESS-80640D (Engineering
Change Proposal, Request for
Deviation/Waiver)
NOTE: In the case of First Article waiver, task (and sub-tasks) 4.2 DT-705A SENSOR
ASSEMBLY FIRST ARTICLE PHASE will not be applicable and will be marked
‘RESERVED’.
5.0 Government Furnished Information
5.1 DD Form 375 Production Progress Report Form
5.2 NAVSEA drawing
templates
Government will provide the contractor formatted drawing templates (.dwg and/or .slddrw, .xlsx, .docx) upon contract award.
5.3 53711-XXXXXXX
through
53711-XXXXXXX
Block of NAVSEA drawing numbers for the
Drawing Package for the DT-705A sensor assembly.
5.4 Production sensor
assembly serial numbers
Block of serial numbers that the contractor shall use to serialize DT-705A sensor assemblies.
File details come from the government source that posted it. Updated .