Attachment 1 - Draft Statement of Work_548 CTS MPU5 Install.pdf

PDF 306 KB Posted

Attached to
548 CTS MPU5 ANTENNA INSTALLATION AND TOWER CLIMB
Solicitation number
H91270522226
Issued by

About this file

This Draft Statement of Work (SOW) details the installation of MPU5 antennas on 4 permanent towers at the Fort Johnson training area for the 548th Combat Training Squadron (CTS). The contractor will install 9 S-Band Integrated Sector Antennas (12dBi Gain 120° Sector Antenna by Persistent Systems) across four specific sites: Mill Creek (3 antennas), Cemetery (3 antennas), Peason West (2 antennas), and Peason East (1 antenna). Antennas will be installed approximately 250 feet above the tower base, oriented toward a central point, with the 548th CTS providing CAT 6 cable and installation brackets.

Key performance requirements include a 14-working-day period of performance, daily site clean-up, compliance with safety regulations (EM 385-1-1 and OSHA), and a one-year warranty on workmanship. The contractor will also be responsible for revising CAD drawings and producing a new engineering analysis to certify the towers. The government-furnished antennas have a unit acquisition cost of $7,944.05 each and will be provided in an "as-is" condition, with 548th CTS personnel present to inspect the property during installation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT STATEMENT OF WORK

MPU5 ANTENNA INSTALLATION AND TOWER CLIMB

548TH CTS FORT JOHNSON, LA

10 FEB 2025

PART I – GENERAL

1. PURPOSE

This Statement of Work (SOW) defines the scope of work to accomplish the installation of

MPU5 antennas on 4 permanent towers in the Fort Johnson training area. The contractor shall provide all labor, material, equipment, management, supervision, coordination, and transportation required to accomplish this work; the antennas will be provided (see Appendix A).

After new equipment is installed by Contractor, areas will be cleaned up to maintain a litter-free environment and present a neat and professional appearance. The work shall be performed in accordance with this SOW, accepted proposal, and all Federal, State, and local laws and regulations, codes and industry standards that may apply. Specific requirements are identified below:

1.2. WORK SCHEDULE

The Contractor shall complete the work outside of scheduled Joint Readiness Training Center exercises, contractor shall contact the 548th CTS to schedule the work. The Contractor shall work with the 548th CTS to ensure access to the towers 2 weeks prior to commencing work.

1.3. CLEAN-UP

All debris and rubbish not specified to become Government property resulting from the installation of antennas. Disposal will be in compliance with all applicable Federal, State, and local hauling and disposal regulations. Site clean-up shall occur daily.

1.4. SAFETY REQUIREMENTS

Safety requirement shall be the applicable sections of EM 385- 1-1, Oct 1992 and Occupational

Safety and Health Administration (OSHA) Regulations. The contractor shall ensure that any lifting devices or ladders meet any and all applicable safety standards.

1.5. PERIOD OF PERFORMANCE

Period of performance for installation/service work mentioned above shall not exceed 14 working days. Work shall begin at an agreed upon date by both parties after the contract has been awarded, at which point, the schedule and completion date will be determined.

1.6. WARRANTY

The contractor shall provide the Government with a one-year warranty on workmanship. The contractor shall provide any manufacturer’s warranty to the Government.

PART II – TECHNICAL

2. Fort Johnson Permanent Towers

2.1. TOWER AND ANTENNA LOCATIONS

The antennas shall be installed on towers in the Fort Johnson training area with the following specifications:

• Site 34/Mill Creek (31.08371285, -93.1409003); 3 antennas

• Site 15/Cemetery (31.09604115, -92.97745216); 3 antennas

• Site 32/Peason West (31.35177588, -93.32792486); 2 antennas

• Site 1/Peason East (31.35044917, -93.17181034); 1 antenna

2.2. TOWER INSTALLATION SPECIFICATIONS AND DELINEATION OF DUTIES

Contractor shall install antennas at approximately 250 ft above the base of towers oriented toward a central point, under the direction of 548th personnel. 548th will provide CAT 6 cable along with all necessary installation brackets. Contractor shall provide cable-ties or appropriate equipment to secure the CAT6 cable to the tower. The CAT6 cable will be routed into the structure below the tower, 548th personnel will connect the cables to a central power supply.

2.3 ENGINEERING STRUCUTRAL ANALYSIS

Contractor shall revise CAD drawings and produce a new engineering analysis to certify the towers. The 548th CTS will provide current CAD renderings for revision. Contractor is not required to update the engineering analysis of the structure at the base of the tower.

APPENDIX A: GOVERNMENT FURNISHED PROPERTY

1. The name, part number and description, manufacturer, and model number:

• S-Band Integrated Sector Antenna, WR-INT-ANT-01 12dBi Gain 120° Sector

Antenna, Persistent Systems, WR-INT-ANT-SYS-01

2. Quantity/unit of measure:

• 9 Each

3. Unit acquisition cost:

• $7,944.05 Each

4. Unique-item identifier or equivalent:

• N/A

5. The antennas will be furnished in an “as-is” condition and members from the 548th CTS will be onsite to inspect the property with the contractor.

File details come from the government source that posted it. Updated .