This document is a DRAFT Statement of Objectives (SOO) for a Flash X-Ray System project. The objective is to replace the existing Flash X-Ray System at the Arnold Engineering Development Complex (AEDC) Hypervelocity Aeroballistics Ranges Facilities on Arnold Air Force Base, Tennessee.
The contract shall define the work to be performed, project milestones, data deliverables, and data rights. The contractor shall develop and maintain a quality program and provide all necessary data, hardware, software, drawings, parts list, and training to support the Flash X-Ray System project. The government seeks to allow maximum flexibility for the contractor to manage the project schedule, performance, risks, subcontracts, and data to complete the project and satisfy the user's performance requirements. The related federal contract opportunity is a Sources Sought notice to determine the availability and capability of small and large businesses to meet this requirement, with a NAICS code of 334517 and PSC of 6635.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - DRAFT Performance Parameters.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives (SOO)
Flash X-Ray System Project
1.0 Project Objective: Replace existing Flash X‐Ray System currently housed in the Arnold Engineering
Development Complex (AEDC) Hypervelocity Aeroballistics Ranges Facilities located on Arnold Air
Force Base (AFB), Tennessee (TN) with a new Flash X-Ray System in accordance with (IAW) SOO
Attachment 1 – Performance Parameters.
2.0 Contract Objectives: The contract shall define, at a minimum, the following:
2.1 Work to be performed: Specific, performance‐based, quantitative terms of the work to‐be‐ done, in the form of a Statement of Work (SOW), to satisfy the Flash X-Ray System Project
IAW SOO Attachment 1 – Performance Parameters, Sections 2.0 and 3.0.
2.2 Project Milestones: Planned, significant events scheduled to occur at specific times in the
Flash X-Ray System Project (throughout a time period not to exceed 12 months) IAW
SOO Attachment 1 – Performance Parameters, Section 1.0.
2.3 Data Deliverables: Tangible or intangible data items produced as a result of the work performed, and their anticipated delivery date, method of delivery, format, and quantity. At a minimum, data deliverables shall include the data items listed in SOO Attachment 1 –
Performance Parameters, Section 4.0.
2.4 Data Rights: The following DFARS Clauses shall be included in the contract to address data rights.
• 252.227‐7014, Rights in Noncommercial Computer Software and Noncommercial
Computer Software Documentation
• 252.227‐7016, Rights in Bid or Proposal Information
• 252.227‐7019, Validation of Asserted Restrictions—Computer Software
• 252.227‐7037, Validation of Restrictive Markings on Technical Data
3.0 Quality Control Plan: Development and maintenance of a quality program to ensure the Flash X-
Ray System Project is made IAW the contractor‐developed Statement of Work (SOW).
Development and implementation of procedures to meet project milestones. Development and implementation of procedures to ensure appropriate corrective action is taken to meet project milestones.
4.0 Logistics Objective: Development and delivery of all data such as hardware and software, drawings, parts list, and training necessary to support the Flash X-Ray System Project.
5.0 Program Management Objective: Allow maximum flexibility to innovatively manage the project schedule, performance, risks, subcontracts (if applicable), and data to complete the Flash X-Ray
System Project so that it satisfies the user’s performance requirements IAW SOO Attachment 1 –
Performance Parameters. Clear government visibility into the project schedule, performance, and risks shall be maintained.