Attachment_1_-_Draft_SOW_SLV-CB_Concrete_Work_1.docx

DOCX document 1 MB Posted

Attached to
SLV-CB Shop Floor (Concrete Work) Federal contract opportunity
Solicitation number
140R4026Q0058
Issued by
Department of the Interior Bureau of Reclamation

About this file

This is a Statement of Work (SOW) for concrete repair and replacement services at the San Luis Valley-Closed Basin (SLV-CB) Shop Floor facility managed by the Bureau of Reclamation's Upper Colorado Region, Alamosa Field Division. The requirement involves removing and replacing damaged concrete features that have shifted or heaved, with the contractor responsible for all demolition and concrete work, furnishing all equipment and materials, and performing required testing. The work is classified under Product Service Code Z2EB (Repair or Alteration of Maintenance Buildings) and NAICS code 238110 (Poured Concrete Foundation and Structure Contractors).

This is a Total Small Business Set-aside acquisition at or below the simplified acquisition threshold, with quotations to be solicited directly from suppliers rather than posted on SAM. Award will be made to the responsible offeror offering the best value based on evaluation of three factors: technical capability, past performance, and price. Contract award is anticipated to begin on or about August 1, 2026. One or more items are subject to Free Trade Agreements. The point of contact is Ronda Lucero at ronda_lucero@ios.doi.gov. Prospective offerors will have access to technical information necessary for quote preparation through the SOW and a scheduled site visit.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SLV Concrete Work

Statement of Work

1.0 - Introduction The Bureau of Reclamation, Upper Colorado Region, Albuquerque Area Office, Alamosa Field Division (Reclamation) is looking to remove and replace damaged concrete features that have shifted or heaved. Contractor shall perform all demolition and concrete work, furnish all equipment and materials and perform required testing.

1.1 - Abbreviations, Definitions, and Acronyms The Bureau of Reclamation commonly used definitions are listed below:

AFD - Alamosa Field Division

BOR -Bureau of Reclamation CO -Contracting Officer
COR -Contracting Officer’s Representative CS -Contracting Specialist
MDT -Mountain Daylight Time
OGR -Onsite Government Representative RSN -Required Submittal Number
SEMS -Sustainability and Environmental Management System (BOR)

1.2 - North American Industry Classification System (NAICS) The NAICS for this work is 238110.

1.3 - Location and Hours of Operations The Reclamation’s facility is located at 10900 Highway 160 East, Alamosa, Colorado 81101 in Alamosa County at Latitude 37º 28’ 22.3” and Longitude 105º 50’ 32.1”. Alamosa Field Division facility is approximately 1.7 miles northeast of downtown Alamosa, Colorado on US Highway 160. Reclamation’s standard business hours are Monday through Friday from 07:30 AM to 4:00 PM MDT except Federal Holidays. Reclamation is a smoke, drug, and alcohol-free facility.

1.3.1 - Facility Access and Deliveries Contractor shall inform the CO and COR a minimum of 5 working days prior to mobilizing personnel, equipment, and materials/supplies to the project site. In addition, if the Contractor would like to have delivery of materials and/or supplies direct shipped to the project site, the Contractor shall notify Ms. Susan Storm and COR a minimum of 3 working days (seventy-two hours) prior to the delivery of materials/supplies. The Contractor shall communicate with Susan the following:

SLV Concrete Work

· Provide a detail list of items to be shipped and arrive at the Alamosa Field Division (AFD)

· Provide the shipping company’s name and related information

· Provide estimated day and time the items are to arrive at AFD Ms. Susan Storm contact information is as follows:

Susan Storm, Facility Manager Bureau of Reclamation Alamosa Field Division 10900 US Highway 160 Alamosa, Colorado 81101

(719) 589-1810 SStorm@usbr.gov Contractor shall check and maintain all equipment stored at the AFD shall be protected from weather, humidity, temperature variations, dirt, and dust, and/or other contaminants.

1.4 – Site Visit The Government (Reclamation) highly recommends perspective Offerors to complete a site visit for a complete understanding of the project objectives and scope.

**A site visit is to be determined.

1.5 - Government Furnished Materials Government shall provide, if available, design data if requested by the Contractor for the purpose of fulfilling the requirements of these specifications.

2.0 - General

2.1 – Background The east concrete slab of the shop floor has shifted to the point of creating hazardous walkway. The slab has a vault with stairs that is designed to function as a mechanic service walkway. This vault has shifted to the point it may affect stability. The outside walkways have deteriorated due to insufficient drainage and water damage. There is also a section that has heaved outside the main door which limits the door from opening fully.

2.2 – Purpose The east foundation slab in the shop has lifted and cracked around the concrete vault/vehicle maintenance pit in the middle of the slab. It appears that freeze-thaw from moisture under the slab is the cause of the lifting. The issue at the shop slab appears to be indicative of a wider drainage issue in the area of the Alamosa shop building. The Alamosa office and shop building area appears to be at a lower elevation than the surrounding land, which causes runoff to flow to and pond at various spots on the property.

2.3 - Scope The concrete slab on the east side of the Alamosa shop building needs to be removed and replaced. The concrete slab covers approximately 800-ft2. The walls of the vault in the middle of the slab shall be removed a minimum of 18-inches below the bottom of the new concrete slab. The vault shall be filled with engineered fill material and compacted in 6-inch lift to a 95% dry density. ½-inch fibre expansion joint shall be placed between new concrete placements and the existing concrete. Concrete joints shall be filled with self-leveling polyurethane sealant. The vault dimensions are 26.25 ft. long x 3.4 ft. wide x 5.2 ft. deep (464 ft3). Also recommended is to improve the overall drainage scheme of the paved areas around the shop building. This will include removing the drain at the disused wash bay and paving it over so that runoff flows away from high traffic areas where it could otherwise freeze over and become a hazard. There are existing drains in the gravel parking lot area that the new drainage scheme can flow to. The heaving area outside the north entrance of the shop will need to be removed and replaced. The perimeter sidewalks will need to be repaired or replaced along with deteriorating sidewalk aprons.

The following Photographs are provided for as reference only.

1. Shop Slab

1a.

Shows vault location in east bay of shop. The vault dimensions are 26.25 long x 3.4” inches wide x 5.2” deep, (464 ft3).

1b.

Shows settling and damage around vault, separation between edge of vault and the slab.

1c.

Looking from the left slab towards the right slab, showing the separation between the two slabs.

2. Wash Bay 2a.

Water accumulated at the disused wash bay.

3. Walkway near north door of shop

3a.

Shows the cement walkway with heaving near the door to the shop. The shop door will only open to ~45 degrees due to raised area.

Dimensions of area to be replaced are ~8 ft. by 13.5 ft. (110 ft2).

3b.

Shows damaged walkway with heaving near the door to the shop.

4. Perimeter sidewalk

4a.

Shows perimeter walkway with crumbling aprons and damage.

Section of east perimeter sidewalk requiring apron replacement is ~150 ft in length.

4b.

Shows section of perimeter walkway with heaving area near main office building.

Area ~30 ft x 5 ft (150 ft2)

2.4 – Submittals The contractor shall submit the following for Government review and approval:

· Prepare in English.

· Measurement Units: US Customary Units.

· Label with contract number and title including Required Submittal Number (RSN).

· Provide a unique transmittal tracking number for each submittal.

· Required certifications shall be performed by a registered professional.

· Manufacturer’s certifications shall be signed by authorized representative.

· Product data that represents more than one items shall be highlighted to show model, size, features, optional, etc. to be supplied under these specifications.

· Review of submittals:

· Time required: The Government will require a minimum of 21 calendar days to review and/or approve each submittal or resubmittal, unless otherwise specified.

· Excess Time: Should the Government require additional time for review, the Contracting Officer may extend the contract completion date to allow completion of work. Time extension will be to the extent that the excess review time caused delay to contract completion.

· Submit the following for Government review and approval:

· Submittal Types:

· A – Action requiring Government approval

· I – Informational requires Government review and written receipt

· Submit electronic copies for review and approval to Susan Storm at sstorm@usbr.gov.

Submittal Table

RSN

S1 Required Submittal and Description Project Schedule (Original) and (Revisions) include key elements such as mobilization, demolition, installation, punch list items, and substantial completion Due Date or Delivery Time Within 14 days after contract award provide (Original) schedule. Submit (Revised) schedule(s) if any dates change more than 5 working days Type

A

S2
Submit site specific Contractor’s Safety Plan and Job Hazard Analysis (JHAs)
A minimum of 7 Days prior to mobilization
A

S3

Submit methods and practices for removing and disposal of existing concrete including safety plan for preventing accidental access.
Within 7 days prior to performance of work activities/tasks

A

S4
Submit list of recycled equipment, materials, supplies used per SEMS.
Within 7 days prior to performance of work activities/tasks
I
S5
Submit installation methods, practices, and layout plan for new concrete/structures.
Within 7 days prior to performance of work activities/tasks
A

S6

Submit the concrete mix design that includes test results of the minimum specified compressive strength.
Within 7 days prior to performance of work activities/tasks A minimum of 21 days prior to sending final invoice

A

S7
Submit As-Built drawings for changes in 34” x 22” standard bond paper and AutoCAD electronic formats.
A minimum of 21 days prior to sending final invoice

A

Reclamation’s Sustainability and Environmental Management System (SEMS) requires that construction contract(s) use recycled materials as defined by EPA’s Green Procurement Program for Recovered Materials. For questions on whether the product counts as "EPA-designated" or what the required recycled content is, refer to product descriptions on EPA's website at https://archive.epa.gov/epawaste/conserve/smm/wastewise/web/html/buyman.html.

3.0 - Reference Standards These standards are part of the specifications:

· American Concrete Institute (ACI) 318

· ASTM International – ASTM C94, ASTM C150/C150M, ASTM C618, ASTM C989/C989M

· International Existing Building Code

· NFPA 70, National Electric Code (NEC) 2023

Reclamation Safety and Health Standards (RSHS):

· RSHS-2014 Section 3 - Contractor Requirements

· RSHS-2014 Section 8 - Personal Protective Equipment (PPE)

· RSHS-2014 Appendix C - Electrical Grounding

4.0 - General Requirements Contractor and Government personnel shall interact and communicate with professionalism and respect throughout the contract processes. The Contractor shall use good housekeeping practices and cleanup all work areas at completion of a workday. All discarded materials, debris, and trash shall be contained and removed from the project site at a minimum weekly and disposed of according to local requirements. Contractor shall remove all equipment and materials not required to meet the requirements of this specifications within 48 hours from the construction site.

Contractor is responsible for the security of all equipment and materials on site. In addition, all material shipments, transportation, and storage are the responsibility of the Contractor.

Unless arrangements are made with the AFD Manager to provide access for shipments to be delivered.

All design work and equipment selection shall be in accordance with the Department of the Interior's Guiding Principles for Existing Buildings.

Qualifications: Contractors, subcontractors, manufacturers, and suppliers shall have minimum of three years of experience in concrete construction.

Any changes to or addition of wiring, conduits, and connectors shall be according to NEC 2023, performed by a state licensed electrician and approved by BOR electrician.

All installations shall provide for a neat and acceptable appearance.

Contactor, Subcontractors, and Reclamation shall participate in project meetings as required to develop, track, and maintain project schedules.

The Contractor shall consult with Reclamation to address impacts to existing utilities prior to removal and/or construction.

4.1 – East Bay of Shop Building Prepare area for concrete accordance with these specifications, standards, and industry best practices. The following is a short, bulleted list of activities:

· Concrete removed shall be recycled or disposed of accordingly to local requirements off site

· Remove original slab and vault area.

· The walls of the vault in the middle of the slab shall be removed a minimum of 18-inches below the bottom of the new concrete slab.

· The vault shall be filled with engineered fill material and compacted in 6-inch lift to a 95% dry density.

· The new concrete slab shall be a minimum of 8 inches thick. The concrete shall have a 28-day compressive strength of 4,000 psi.

· The concrete shall be steel reinforced with #5 rebar, spaced 12 inches OC each way. The reinforcement shall be 3 inches from the bottom of the slab. The steel reinforcement shall have tensile strength of 60 ksi.

· One half inch fibre expansion joints shall be placed between new concrete placements and the existing concrete.

· Concrete joints shall be filled with self-leveling polyurethane sealant.

4.1.1 - Existing Site Conditions

The Contractor shall prior to ordering supplies verify the following existing site requirements:

· Government furnished drawings are for “Reference Only” and all plans are approximations.

· Offeror shall document existing features:

· If required, include recommendations requiring changes, upgrades, or other related improvements to support new concrete features.

· Offeror can submit changes and/or modifications to the existing footprint to the Government for review and written approval of such changes/modification.

4.2 – Outdoor Wash Bay Prepare area for concrete accordance with these specifications, standards, and industry best practices. The following is a short, bulleted list of activities:

· Concrete removed shall be recycled or disposed of accordingly to local requirements off site.

· Remove original slab and remove filled in drain to prevent water infiltration.

· Grade shall provide for drainage away from the building or to proper drains. The wash bay slab shall slope a minimum of one quarter inch per foot away from the building.

· The new concrete slab shall be a minimum of 8 inches thick. Concrete shall have a 28-day compressive strength of 4,000 psi.

· The concrete shall be steel reinforced with #5 rebar, is spaced 12 inches OC each way. The reinforcement shall be 3 inches from the bottom of the slab. The steel reinforcement shall have a minimum tensile strength of 60ksi.

· One half inch fibre expansion joints shall be placed between new concrete placements and the existing concrete.

· Concrete joints shall be filled with self-leveling polyurethane sealant.

· Contractor shall specify how cold weather placements will be handled.

4.3 – Walkway Prepare area for concrete accordance with these specifications, standards, and industry best practices. The following is a short, bulleted list of activities:

· Concrete removed shall be recycled or disposed of accordingly to local requirements off site.

· Remove original slab.

· Grade shall provide for drainage away from the buildings.

· Pour new slab.

· One half inch fibre expansion joints shall be placed between new concrete placements and the existing concrete.

· Concrete joints shall be filled with self-leveling polyurethane sealant.

· Contractor shall specify how cold weather placements will be handled.

4.4 – Perimeter Sidewalks Prepare area for concrete accordance with these specifications, standards, and industry best practices. The following is a short, bulleted list of activities:

· Concrete removed shall be recycled or disposed of accordingly to local requirements off site.

· Remove original deteriorated aprons and damaged sections of sidewalk.

· Construct new aprons and repair/replace walkways.

· One half inch fibre expansion joints shall be placed between new concrete placements and the existing concrete.

· Concrete joints shall be filled with self-leveling polyurethane sealant.

· Contractor shall specify how cold weather placements will be handled.

5.0 – As-Built Drawings The following bullets describes the requirements for providing As-Built drawings for this project:

· Drawing shall indicate location of existing piping or electrical service, grade, and drainage.

· Drawing shall indicate location of grade and dimensions of concrete features at each state of work.

· Drawing shall include section and elevation views as required.

· Submit final electronic files for As-Built drawings by approved format such as CD, DVD, or thumb-drive, web base applications.

If required by the Offeror, the Government can supply electronic AutoCAD format template.

6.0 – Security and Safety This section describes the security and safety requirements for this Reclamation facility. The following sub-sections provide additional details for various considerations on this effort.

6.1 - Security The contractor shall not access any sensitive areas without escort from Reclamation personnel.

6.1.1 – Facility Security Agreement The contractor shall sign a Facility Security Agreement which outlines the Contractor’s and the Government’s responsibilities in the following areas:

· Drafting, coordinating Government reviews, finalizing, and maintaining the Facility Security Agreement

· Standard Procedures for accessing sensitive or restrictive areas

· Contractor security supervision

· Contractor’s accountability in training and managing personnel that will be accessing sensitive or restrictive areas

· Accountability of issued Identification

· Emergency protection

· Protection of government resources

6.2 - Safety Contractor and its subcontractors shall comply and incorporate into their safety and health programs/plans the following safety requirements:

· Occupational Safety and Health Administration (OSHA) Part 1926 Construction.

· Reclamation Safety and Health Standards (RSHS) which can be found at the following website: https://www.usbr.gov/ssle/safety/RSHS/rshs.html.

The contractor and its subcontractors (if applicable) shall promptly report all facts regarding accidents, near miss(es), emergencies, and/or mishaps involving Government property damage or injury to Government personnel and to cooperate in any resulting safety investigation.

The contractor shall notify the Contracting Officer’s Representative and Contracting Officer by one of the following methods: in person, by telephone, and/or by email within four (4) hours of all incidents. Reclamation’s personnel will notify Reclamation’s Safety and Health office. The contractor shall immediately secure the incident area and any damaged property. If requested by Reclamation Safety and Health office, the Contractor shall submit all pertinent maintenance and training records for equipment or personnel involved in the safety incident(s). If the Government investigates the safety incident, the contractor and the subcontractors shall cooperate fully and assist the Government personnel with the investigation.

7.0 – Provided to Offeror

7.1 – Point of Contact The following key Government personnel are:

Contract Specialist: Ronda Lucero (UC-871) Bureau of Reclamation 555 Broadway NE, Suite 100 Albuquerque, NM 87101-2352 Phone No.: (801) 524-3691 Email: ronda_lucero@ios.doi.gov

Contracting Officer: Mary B. Maestas (ALB-865) Bureau of Reclamation 555 Broadway NE, Suite 100 Albuquerque, NM 87101-2352 Phone No.: (505) 462-3581 Email: mary_maestas@ios.doi.gov

Contracting Officer’s Representative: Susan Storm, Facility Manager (AFD-400) Bureau of Reclamation 10900 US HWY 160 E Alamosa, Colorado 81101 Phone No.: (719) 589-1810 Email: sstorm@usbr.gov

Technical Representative: Susan Storm, Facility Manager (AFD-400) Bureau of Reclamation 10900 US HWY 160 E Alamosa, Colorado 81101 Phone No.: (719) 589-1810 Email: sstorm@usbr.gov

7.2 – Government provided Utilities The Government will make available electricity and water for construction activities. The use of water closet(s) will be at the discretion of the AFD Manager. If use of the water closet (bathroom) is not available, the Contractor shall provide a portable toilet for its employees use.