This sources sought notice seeks capabilities statements from interested parties for fire sprinkler and fire alarm maintenance, inspection, and testing services at the Moncrief Army Health Clinic at Fort Jackson, South Carolina. The services include maintenance and testing of fire sprinklers, fire pumps, standpipes, wet and dry pipe systems, fire alarm panels, and associated devices. Capabilities statements are requested by September 23, 2022 and should address the organization's experience, technical skills, management approach, and ability to self-perform at least 50% of the work. The requirement may be set aside for small businesses. The period of performance is one base year plus four option years, with an anticipated award date of December 2022. The contract type is expected to be firm fixed price.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - A-G PRS Deliverables 20220913.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FIRE SPRINKLER, FIRE ALARM SYSTEM MAINTENANCE, INSPECTION, AND TESTING SERVICES
MONCRIEF ARMY HEALTH CLINIC (MAHC)
Fort Jackson, SC
Part 1
General Information
1. GENERAL: This is a non-personal services contract to provide Fire Sprinkler, Fire Alarm System
Maintenance, Inspection, and Testing Services at the Moncrief Army Health Clinic (MAHC), Fort
Jackson, SC. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.1 Description of Services/Introduction: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform Fire Sprinkler, Fire Alarm System Maintenance, Inspection, and Testing Services as defined in this Performance Work Statement except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract as well as those applicable standards listed in NFPA, OSHA and EM 385 1-1.
1.2 Background: This requirement is for the MAHC to retain maintenance, inspection, and testing services for the Fire Sprinkler, Fire Alarm System and associated equipment. All scheduled and preventative maintenance required by the original equipment manufacturers, the attached checklists of this Performance Work Statement (PWS) and applicable codes shall be performed on the specified equipment. The qualified contractor workforce is responsible for being present and completing the Fire
Sprinkler, Fire Alarm System tests as outlined in Attachment A-G of this PWS for the MAHC.
1.3 Objectives: To retain sprinkler maintenance, inspection, and testing services for the MAHC.
1.4 Scope: The Contractor shall provide Fire Sprinkler, Fire Alarm maintenance, inspection, and testing service in accordance with this PWS. Contractor shall provide both scheduled and emergency service to
Moncrief Army Health Clinic's (Ten buildings shown on attachment “A”) Fire Sprinkler, Fire Alarm
System (FSS), (FAS) as described within this PWS. The Contractor shall provide service to the sprinkler piping, fire pump, associated equipment, and Fire Sprinkler, Fire Alarm System (FSS), (FAS) and do so in a manner which meets or exceeds all NFPA codes and regulatory requirements and manufacturer's requirements.
Attachment “A” includes ten specified buildings that requires testing.
Attachment “B” has a list that includes, but is not limited to, the specified fire alarm and fire sprinkler devices that requires testing.
Attachment “C” includes sample of fire pump test.
Attachment “D” includes sample of quarterly flow and tamper worksheet for building 4500.
Attachment “E” includes sample of 5-year standpipe testing.
Attachment “F” includes testing protocols for outlying buildings.
Attachment “G” includes the fire protection impairment program.
1.5 Period of Performance: Base year plus four 12-month option periods.
1.6 General Information
1.6.1 Quality Control: Not applicable
1.6.2 Quality Assurance: The Government shall evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the
Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.6.3 Recognized Holidays: The Contractor will not be required to perform services on Federal Holidays.
New Year’s Day Labor Day
Martin Luther King Jr.’s Birthday Columbus Day
President’s Day Veteran’s Day
Memorial Day Thanksgiving Day
Independence Day Christmas Day
1.6.4 Hours of Operation: The contractor is responsible for conducting business, between the hours of
0730-1530 Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate and qualified workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons.
1.6.5 Place of Performance: The work performed under this contract will be performed at Moncrief Army
Health Clinic, Fort Jackson, SC 29207.
1.6.6 Type of Contract: The Government will award a firm fixed price contract.
1.6.7 Security Requirements: See section 5.16.2
1.6.7.1 Physical Security: See section 5.15.2
1.6.7.2 Key Control: See section 5.15.6
1.6.7.3 Lock Combinations: Not applicable
1.6.8 Special Qualifications: Not applicable
1.6.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with
Federal Acquisition Regulation Subpart 42.5. The Contracting Officer, Contracting Officers
Representative (COR), and other Government personnel, as appropriate, may meet periodically with the
Contractor to review the Contractor's performance. At these meetings, the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.6.10 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The
COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance:
maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of
Government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The
COR is not authorized to change any of the terms and conditions of the resulting order.
1.6.11 Key Personnel: The Contractor shall provide at least two points of contact within the company to interface with the COR on issues concerning sprinkler maintenance, inspection, and testing service.
Names, business address, phone numbers and hours of operation are the minimum information requirement. The Contractor shall also provide an afterhours name and telephone for emergency contact.
Contractor shall provide a point of contact information for 24 hours a day/ 7 days a week emergency service.
1.6.12 Identification of Contractor Employees: All Contractor personnel attending meetings, answering
Government telephones, and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.6.13 Contractor Travel: Not applicable
1.6.14 Other Direct Costs: Not applicable
1.6.15 Data Rights: Not applicable
1.6.16 Organizational Conflict of Interest: Contractor and sub-Contractor personnel performing work under this contract may receive, have access to, or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications, or work statements, etc.) or perform evaluation services which may create a current or subsequent
Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the
Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.6.17 Phase In /Phase Out Period: Not applicable
1.6.18 Installation Access
Based on recent guidance from the Secretary of the Army and COS Army, Senior Commanders and supporting garrison leadership are not authorized to grant unescorted installation access without the required identity proofing and vetting using the National Crime Information Center Interstate
Identification Index (NCIC-III).
Civilian personnel requesting access must have a valid reason to be on the federal installation, be sponsored by a DOD Civilian/military card holder, and be favorably vetted against the FBI's database.
Once these conditions have been met, we will issue credentials in the form of either a pass or DOD identification card from the DBIDS System that we currently have in place. (Defense Biometric
Identification System).
Personnel not affiliated with DOD and/or not vetted against NCIC-III or for a short term visit, must be escorted while on the installation.
National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening
Database (TSDB) Criteria for Denial.
Army Senior Commanders will, in the absence of an approved waiver, deny non-cleared individuals unescorted access to the installation based on the results of the NCIC-III and TSDB checks that contain credible derogatory information indicating that the individual may present a threat to the good order, discipline, or health and safety on the installation. Such derogatory information includes, but is not limited to, the following:
1. The NCIC-III contains criminal arrest information about the individual that causes the senior commander to determine that the individual presents a potential threat to the good order, discipline, or health and safety on the installation.
2. The installation is unable to verify the individuals claimed identity based on the reasonable belief that the individual has submitted fraudulent information concerning his or her identity in the attempt to gain access.
3. The individual has a current arrest warrant in NCIC, regardless of the offense or violation.
4. The individual is currently barred from entry or access to a federal installation or facility.
5. The individual has been convicted of crimes encompassing sexual assault, armed robbery, rape, child molestation, production or possession of child pornography, trafficking humans, drug possession with the intent to sell or drug distribution.
6. The individual has a U.S. conviction for espionage, sabotage, treason, terrorism or murder.
7. The individual is a registered sex offender.
8. The individual has a felony conviction within the last 10 years, regardless of the offense or violation.
9. The individual has been convicted of a felony firearms or explosives violation.
10. The individual has engaged in acts or activities designed to overthrow the U.S. Government by force.
11. The individual is identified in the TSDB as known to be or suspected of being a terrorist or belonging to an organization with known links to terrorism or support of terrorist activity. When this capability becomes available to DOD, installation access control personnel will strictly follow the Federal Bureau of
Investigations published engagement protocols.
*Only Government officials whom the senior commander designates will perform fitness determinations.
Designations will be in writing by duty position and codified in local guidance.
DBIDS information required to issue passes/cards.
Stateside license, Personal data Ht/Wt/, Who the sponsor is, finger print/photo.
Before issuing ID cards to new employees or contractors, the standard requires agencies to conduct a background investigation of employees and contractors "who require long-term access to federally controlled facilities and/or information systems." This investigation would include agency initiation of the
National Agency Check with Written Inquiries (NACI) or a similar type of national security investigation.
In the event credentials are issued without a completed NACI, the ID must be electronically distinguishable from those issued to individuals for whom the investigation has been completed. The
Contractor is responsible for meeting Antiterrorism/Operations Security Requirements. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete all mandatory training to include Antiterrorism (AT) and
Operations Security (OPSEC) training required by government employees and directed by the command.
The contractor and all associated subcontractors’ employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures
(provided by the Government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation
Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the
Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
The COR is the Point of Contact for all required OPSEC and iWatch training requirements identified in the contract.
See Technical Exhibit 4 for the Fort Jackson Vetting Policy/Documents.
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. DEFINITIONS:
2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the Contracting Officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS.
When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8. QUALITY ASSURANCE. The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of Contractor performance.
2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.
2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with
2.1.12. WORK WEEK. Monday through Friday, unless specified otherwise.
2.2. ACRONYMS:
ACOR Alternate Contracting Officer's Representative
AFARS Army Federal Acquisition Regulation Supplement
AR Army Regulation
CCE Contracting Center of Excellence
CFR Code of Federal Regulations
CONUS Continental United States (excludes Alaska and Hawaii)
COR Contracting Officer Representative
COTR Contracting Officer's Technical Representative
COTS Commercial-Off-the-Shelf
CMS Central Material Service
DA Department of the Army
DD250 Department of Defense Form 250 (Receiving Report)
DD254 Department of Defense Contract Security Requirement List
DFARS Defense Federal Acquisition Regulation Supplement
DMDC Defense Manpower Data Center
DOD Department of Defense
EMD Electro Motive Diesel
EPSS Emergency Power Supply System
FAR Federal Acquisition Regulation
HIPAA Health Insurance Portability and Accountability Act of 1996
KO Contracting Officer
MAHC Moncrief Army Health Clinic
OCI Organizational Conflict of Interest
OCONUS Outside Continental United States (includes Alaska and Hawaii)
ODC Other Direct Costs
OR Operating Room
PIPO Phase In/Phase Out
POC Point of Contact
PRS Performance Requirements Summary
PWS Performance Work Statement
QA Quality Assurance
QAP Quality Assurance Program
QASP Quality Assurance Surveillance Plan
QC Quality Control
QCP Quality Control Program
TE Technical Exhibit
VHP Very High performance diesel
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1. Services: Not applicable
3.2 Facilities: Not applicable
3.3 Utilities: Not applicable
3.4 Equipment: Not applicable
3.5 Materials: Not applicable
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1 General: The Contractor shall furnish all supplies, equipment, and services required to perform work under this contract that are not listed under Section 3 of this PWS.
4.2 Secret Clearance: Not applicable
4.3. Materials: The Contractor shall provide all materials and supplies necessary to accomplish all tasks required by the contract.
4.4. Equipment: The Contractor shall provide all equipment necessary to accomplish all tasks required by
PART 5
SPECIFIC TASKS
5. Specific Tasks:
5.1. Basic Services: The Contractor shall provide sprinkler maintenance, inspection, and testing service for the MAHC. The Contractor shall provide both scheduled and emergency service to MAHC’s Fire
Sprinkler, Fire Alarm System (FSS), (FAS) as described within this PWS. Service to the specified equipment, including its associated equipment, shall meet or exceed all applicable regulatory and manufacturer's requirements.
In addition, the Contractor is responsible for the performance of monthly Fire (FSS), (FAS) tests as outlined in Attachments A-G and IAW all applicable NFPA codes and regulations for the equipment listed below, including their ancillary components, parts, and devices, etc. In conjunction with completing the specified service IAW applicable NFPA rules and regulations; Below is a partial list of the equipment in building 4500. The attached eight checklists of this PWS shall be modified and utilized for the testing of the specified equipment. Any modifications of the eight checklists shall be approved by the
Engineering Department. All applicable Fire Alarm and Sprinkler systems, including ancillary devices and equipment, found in the specified buildings shall be tested in accordance with NFPA 72 (2013
Edition), NFPA 25 (2014 Edition) and NFPA 101 (2015 Edition).
Equipment Description:
• 1ea. Fire Pump 1000 GPM
• 1ea. Jockey Pump
• 2ea. Fire Department Connections (FDC)
• 4ea. Dry Valve Systems
• 6ea. Stand pipes
• 32ea. Wet Pipe Systems
• 2ea. Post Indicator Valves (PIV)
• 2ea. Backflow Devices
• 2ea. Monaco XMTR Relay
• 110ea. Points on the Quarterly flow and tamper work sheet
• 1ea Pressure Relief Clay Valve
• 45ea Hose valve/connection
5.2 Attachments A-G are required checklists to be used during performance of the contract. Official copies of attachments A-G will be provided by the government and must remain at (MAHC). The requirements listed on the sheets shall be performed in accordance with the monthly schedule. As noted on the sheets, additional maintenance either needed or required shall be performed by the Contractor. The
Contractor shall make available to the site inspectors any records requested or old parts replaced. The
Government reserves the right to supply all parts and materials. The Contractor shall also, at the request of the Government, provide parts, material, and additional services and to the Clinic’s Fire Sprinkler, Fire
Alarm system and promptly provide an invoice to the Government.
5.3 The Contractor shall make available to the site inspectors any new parts requested.
5.4 The Contractor is responsible for having a representative at the Fire alarm panel to perform the quarterly operational test. This test is normally done at 7:30 hours on the fifteenth of each month plus or minus ten days at building 4500. Engineering shall approve applicable schedules for outbuildings. The clinic reserves the right to change the normal test time and date, and will notify the Contractor at least one week prior to exercising this option. Due to the nature of the environment the clinic may be required to make “last minute” changes to the schedule to avoid unnecessary risks to patients and staff. In the event of a “last-minute” schedule change, the Contractor will be notified as soon as possible. The government shall, under no circumstances, incur fees or charges from the Contractor for “Last minute” scheduling changes.
5.5 The Contractor shall be responsible for emergency calls that the government staff is unable to respond to.
5.6 The Contractor is responsible for responding to all facility calls for non-scheduled service. Non-scheduled service shall be broken into the categories of routine, urgent and emergency. Routine service calls shall require an on-site response within 5 business days of receiving the trouble call (excluding all federal holidays). The on-site response time for urgent repairs shall be within 4 hours of receiving the trouble call. The on-site response time for emergency calls (total equipment failure) shall be within 1 hour of receiving the trouble call. The Contractor is responsible for responding to all service calls. All bids for this contract must include a firm and binding hourly rate for each of the three type calls, routine, urgent, and emergency.
5.7 The Contractor shall have an office and warehousing facilities with adequate parts, tools, and equipment to be used to maintain the equipment located within 60 miles of Fort Jackson installation. The contractor shall provide a statement which allows the Government access to Contractors facilities for inspection purposes for the purposes of ensuring that the entity has the capability of successfully executing the contract.
5.8 The annual preventative maintenance for the automatic transfer switches shall be performed by an authorized ASCO service center. The switch testing is not part of this PWS but the fire pump test shall be tested during the June generator test. The generator test is normally done at 17:00 hours on the first
Thursday of each month.
5.9 It is the responsibility of the Contractor to ensure that all calls are received (i.e. A 24 hour answering service or other appropriate method is required).
5.10 The Contractor shall be responsible for the proper disposal of all waste generated during the performance of this contract. All waste shall be disposed of in accordance with the South Carolina
Hazardous Waste Management Regulations, as regulated by the South Carolina Department of Health and
Environmental Control. The Contractor shall provide the Government with all trace documentation of the waste disposal, upon request.
5.11 The Contractor shall supply the clinic with Safety Data Sheets (SDS) on all applicable substances brought on site.
5.13 REPORTS
5.13.1 All submissions and records shall be made to the project site inspectors with the guidelines listed above. Doug Driggers, Howard Dowd and Wendell Fralix, of the clinic staff shall act as co-inspectors on this project, and shall receive copies of all submittals and monitor in process work.
5.13.2 Test documentation gathered at time of service will be turned over to the site inspectors. A review for correctness and to insure work orders are generated for any deficiencies will be done with the contractor present.
5.14 ADDITIONAL SERVICES TO BE PERFORMED:
5.14.1 Submission of a work plan is required prior to beginning the project. The work plan submitted will specifically detail the techniques to be employed to accomplish the assigned work and detail the phasing and scheduling of work, as coordinated with clinic staff, in order to minimize impact on normal clinic operations. Any additional services performed by the contractor shall be completed IAW applicable safety codes and regulations as described in EM 385 section 1-1. A copy of EM 385-1-1 is available upon request.
5.14.2 Contractor shall immediately report any hazardous condition discovered, whether within the scope of this project or not.
5.15. SITE SECURITY AND SAFETY:
5.15.1 The Contractor will be required to attend a pre-contract meeting and safety training approximately
2 weeks prior to the start of work. The Contractor will need to provide a signed copy of our pre-construction safety agreement at this meeting. A copy of the pre-construction safety agreement is available in electronic Word format upon request.
5.15.2 Site security and safety shall be in accordance with Fort Jackson and MEDDAC regulations.
Contractor shall be responsible for all activity, security, and safety inside the project area(s). Adherence to
Infection Control, Hazardous Communication (SDS), Hot Work, Lockout Tag-out, Life Safety, OSHA, NFPA, & JCAHO protocols is required and shall be enforced. This facility strictly adheres to and enforces safety requirement as outlined in EM385-1-1. As such the contractor, will be required to comply with all applicable regulations listed EM385-1-1. As the Authority Having Jurisdiction (AHJ) at MAHC and all of its outlying buildings, the Hospital Safety Officer shall have final approval authority of the
APP, AAPP and any and all sub plans that pertain or relate to therein. The Contractor will also be responsible for providing two man teams “buddy system” when performing work in areas designated as buddy spaces.
5.15.3 Any work that will create dust or in any way contaminate the air circulated within the clinic shall be performed in such a way as to comply with all rules and regulations concerning Infection Control. All equipment, desks, computers, etc. in the immediate area shall be covered to protect them from contamination that may occur during any dust or debris creating activity. The Contractor shall be required to cover all equipment in the area during any drilling of sheetrock, plaster, concrete or concrete products and a HEPA vacuum shall be utilized during this process.
5.15.4 The Contractor shall acquire a smoke/fire wall permit prior to any work in or through an existing smoke/fire wall in the facility and a ceiling tile permit for any ceiling tile that will be disturbed. All fire wall and smoke wall penetrations shall be sealed per UL specifications using the Hilti® System and provide proof of current training from a Qualified Hilti® field representative. This training is available free of charge by Hilti®, phone number 1-800-897-8000. Hilti® products and systems are available online http://www.us.hilti.com/holus/modules/home/home_main.jsp. The Contractor shall replace any ceiling tiles damaged during work with new matching tiles
5.15.5 Contractors will be required to wear visitor badges and sign in and out while working in the building.
The Contractor shall notify one of the personnel listed in paragraph 5.14.1 each day prior to beginning work.
5.15.6 Many areas of the clinic and other medical and support buildings on Fort Jackson require a controlled key for access. We have several security levels and lock combinations with an overall master key that utilizes the Best seven pin lock system in most locations. If this contract requires a controlled key(s) to be issued for access to those areas, the Contractor will be responsible for secure control and prompt return of the required key(s). If this key(s) is lost, the Contractor will be financially responsible for the replacement cost of any secure locks and accompanying keys that have been compromised. The replacement cost may be substantial because our Engineering lock system currently has over 200 lock cylinders and over 300 keys in place.
5.15.7 Please be advised that due to present fluctuating security levels, delays beyond our control may be encountered. The Government shall not be billed for cost increases due to raised security levels.
5.16 ENVIRONMENTAL AND HAZARDOUS MATERIALS HANDLING.
5.16.1 Ft. Jackson is subject to EPCRA reporting requirements. Therefore, any hazardous substance brought on the post must be identified and properly characterized to ensure they are tracked for reporting purposes.
5.16.2 The contractor shall provide a means to supply and transport hazardous materials (HAZMAT) in support of HAZMART operations. The contractor shall store, control, maintain, transport, and sustain
HAZMAT operations IAW regulatory requirements.
5.16.3 Any hazardous materials furnished under this contract shall comply with applicable OSHA laws and regulations. (See Clause 52.223-3- Hazardous Material Identification and Material Safety Data and
252.223-7001 - Hazard Warning Labels elsewhere in this solicitation.)
5.16.3.1 The Contractor shall provide copies of SDS data sheets for all products to the COR.
5.17.1 The Contractor and Contractor representative shall handle, transport, store, and dispose of all waste materials generated by any work performed under this contract in accordance with all applicable Federal, State, Local, or Installation laws, ordinances, regulations, court orders, or other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978; the Federal
Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (16
U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET
SEQ); the Solid Waste Disposal Act, as amended (16 U.S.C. Sec 469, ET SEQ); Emergency Planning and
Community Right-to-Know Act (42 U.S.C. 11011, ET.SEC.). In case of a conflict among these laws and regulations, the most stringent law or regulation shall apply. Any Hazardous Wastes requiring a manifest must be turned in to the DPW-Classification Unit for proper disposition. Should the Government be held liable for any noncompliance, neglect or improper actions resulting from the Contractor or the
Contractor’s representative removal or disposal of hazardous waste, the Contractor shall reimburse the
Government for all such liability. The Contractor is absolved of any liability for prior contamination of the site should it be identified.
5.17.2 The U.S. Environmental Protection Agency website
(http://www.epa.gov/wastes/conserve/tools/cpg/about.htm) has the latest product list and specific recycled content requirements for each product. For additional information contact Tameria Warren, ENV, at (803)
751-9505.
5.17.3 The contractor must be compliant with the Fort Jackson Spill Prevention Control and
Countermeasures Plan (SPCCP).
5.17.3.1 The Contractor is responsible for hazardous substance spill prevention, training, clean up, and reporting, and must comply with the Fort Jackson Spill Response Plan (page l5 of the HSMP). The Fort
Jackson Hazardous
Substance Management Plan (HSMP), dated January 201 1, may be used for guidance. The HSMP is located at http://wwwjackson.army.miVsites/garrisorVdocs/442. For additional information contact
Heather Thomas. ENV. At 75l-4231.
5.17.3.2 In the event of fuel or potentially hazardous material spillage by the Contractor and/or the
Contractor’s representative, the Contractor shall be responsible for its containment, clean up, and related disposal costs. The Contractor shall immediately notify the Fire/Emergency services dispatcher and take appropriate actions to correct and prevent future occurrences. The Contractor shall have sufficient spill supplies available on-site to contain any spillage. If any federal, state, or local agency assesses any monetary fines, penalties, or assessments related to the Contractor and/or the Contractor’s representative handling, release, storage, generation, or disposal of hazardous materials, toxic substances or any other regulated substance the Contractor shall indemnify and hold harmless the Government its agents, and employees from every claim or liability, including attorney fees and court costs.
5.17.4 Fort Jackson has implemented a Sustainability Management System (SMS) to proactively deal with environmental impacts of its processes, activities, and services while supporting mission requirements and building community relationships. All persons working on, for, or on behalf of Fort
Jackson must be aware of the SMS policy (acronym 'PALMS), which is to promote continual improvement, always be in compliance, look to prevent pollution, manage sustainable programs, and sustain natural and cultural resources. Contractors and their subcontractors must receive SMS General
Awareness Training and ensure that all goods and services do not deviate from the installation's SMS
Policy, objectives, and targets. For SMS training or additional information contact the SMS Coordinator at (803) 751-9505.
5.18 OCCUPATIONAL SAFETY AND HEALTH: The Contractor shall comply with the Occupational
Safety and Health Act (OSHA) as well as applicable Army Corp of Engineers EM 385 1-1 rules and regulations. The Contractor shall be responsible for ensuring adherence to all applicable Installation, State of South Carolina, and Federal rules and regulations.
5.18.1 The Contractor shall carry general liability and worker’s compensation as indicated by the FAR
52.228-5 (Insurance Work on a Government Installation) and hereby agrees to provide and maintain insurance during the entire contract period for the below stated minimum types and amounts specified elsewhere in the contract.
5.19 WORK ON A GOVERNMENT INSTALLATION: The work site is on a military installation;
therefore, the Contractor shall comply with all applicable rules and regulations including, but not limited to those specified in the contract. See Technical Exhibit 3 for the Fort Jackson Vetting Policy
5.20 NATIONAL ENVIRONMENTAL POLICY ACT: The Contractor is advised that the National
Environmental Policy Act (NEPA) requires the consideration of the environmental impact before any federal action may be taken. The Army's procedure for complying with NEPA is set forth in Army
Regulation 200-2. The Contractor agrees that it has or will review the applicable environmental documentation required before performance of this contract, and it has or will notify the Contracting
Officer in writing prior to proceeding with performance if it is not satisfied with the sufficiency of the documentation. The Contractor further agrees that it will provide any necessary documentation required by NEPA and AR 200-2 in the event a change is proposed to be made to this contract.
5.21 Contractor Manpower Reporting (CMR):
The contractor will report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Department of the Army via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil, and then click on “Department of the Army CMRA” or the icon of the DoD organization that is receiving or benefitting from the contracted services.
Reporting inputs will be for the labor executed during the period of performance during each Government
FY, which runs from October 1 through September 30. While inputs may be reported any time during the
FY, all data shall be reported no later than October of each calendar year, beginning with 2013.
Contractors may direct questions to the help desk by clicking on “Send an email” which is located under the Help Resources ribbon on the right side of the login page of the applicable Service/Component’s CMR website at http://www.ecmra.mil. As part of its submission.
PART 6
APPLICABLE PUBLICATIONS
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures below:
6.2 All regulations, manuals, and pamphlets (PAMs) can be accessed at http://www.army.mil/usapa/.
6.3 Unless otherwise specified by the Contracting Officer, the Contractor shall be required to perform in accordance with the most current editions of the following regulatory and procedural guidelines:
6.4 Regulations, Manuals, PAMs and Other
Publications. Number Regulations, Manuals, PAMS and Other
Publications
Mandatory/
Advisory AR 25-1 Army Knowledge Management and
Information Technology, dated 12/04/2008
Advisory
AR 25-400-2 The Army Records Information
Management System (ARIMS), dated
10/02/2007
Advisory
AR 190-13 The Army Physical Security Program, dated 02/25/2011
Advisory
AR 190-51 Security of Unclassified Army Property
(Sensitive and Nonsensitive), dated
09/30/1993
Mandatory
AR 200-1 Environmental Protection and
Enhancement, dated 12/13/2007
Advisory
AR 210-7 Commercial Solicitation on Army
Installations, dated 10/18/2007
Mandatory
FJ Supplement 1 to AR 210-7 Commercial Solicitation on Army
Installations, dated 06/01/2005
Mandatory
AR 380 SERIES Army Information Security Program
Regulations
Mandatory
AR 380-5 Department of the Army Information
Security Program dated 09/29/2000
Mandatory
AR 380-67 Personnel Security Program, dated
9/09/1988 (RAR 01, 8/4/2011)
Mandatory
AR 385-10 The Army Safety Program, dated
8/23/2007 (RAR 004, 2/25/2010)
Mandatory
DA PAM 385-40 Accident Reporting and Records, dated
03/06/2009 (RAR dated 02/25/2010)
Mandatory
AR 420-1 Army Facilities Management, dated
02/12/2008 (RAR 002, 8/24/2012)
Mandatory
FJ Reg.420-90 Fire Protection and Protection Services, dated 06/01/2005
Mandatory
AR 600-8-1 Army Casualty Program, dated 4/30/2007 Mandatory
AR 735-5 Policies And Procedures For Property
Accountability, dated 02/28/2005
Advisory
DA PAM 25-30 Consolidated Index of Army Publications
& Blank Forms (online)
Advisory
DA PAM 200-1 Environmental Protection and
Enhancement, dated 01/17/2002
Mandatory
DA PAM 385-10 Army Safety Program, dated 05/23/2008
(RAR 003, 01/19/2010)
Mandatory
DOD 4500.9-R Defense Transportation Regulation (DTR) Mandatory
DOD 5500.7-R Joint Ethics Regulation (JER), Ch 2, dated
03/25/1996 http://www.dod.gov/dodgc/defense_ethics/ ethics_regulation/
Mandatory
DODI 4715.4 Pollution Prevention, dated 06/28/1996 Mandatory
EM 385-1-1 Safety And Health Requirement Manual, dated 11/3/2003
Mandatory
EO 12873 Federal Acquisition, Recycling, and Waste
Prevention
Mandatory