This pre-solicitation notice is for project DPW-20263-0J to repair the roof of building 4320 at Fort Wainwright, Alaska. The U.S. Army requires replacing the existing roof system down to the concrete deck with a fully-adhered EPDM membrane system. The estimated value is between $250,000 and $500,000. The solicitation will be issued as a 100% small business set-aside using sealed bidding procedures and award a firm fixed price contract. Interested small businesses are requested to provide company information by April 13, 2021 to the identified points of contact. The actual solicitation is expected within 180 days, with the bid due date contained therein. Prospective contractors must register in SAM prior to award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Repair/Replace B4320 Roof
DPW-20263-0J 24-MAR-2021
STATEMENT OF WORK
DPW-20263-0J / Bldg 4320
Repair/Replace Roof
24 MAR 2021
1. GENERAL:
1.1. Provide all materials, labor, and equipment to repair by replacement of roof system on
Building 4320 per this scope and the construction documents attached/enclosed. This project is intended to replace the existing roof system down to the concrete deck with a fully-adhered
EPDM membrane system. Contractor shall verify on site all dimensions, sizes, and quantities prior to submitting a proposal.
1.2. Contractor shall comply with any current Operational Order which modifies or restricts access to Fort Wainwright.
2. PROJECT REQUIREMENTS:
2.1. Refer to project drawings, specifications, and all contract documents and appendices.
2.2. Contractor shall take measures during construction to preserve and protect against damage all government and personal property. Property damaged during work shall be restored or replaced by contractor at no additional cost to Government. Contractor will ensure work site is secured daily after work for day is completed.
2.3. Work shall be completed in accordance with (IAW) all applicable, current codes, regulations, industry standards. In event of conflicting guidance the more stringent guidance will be followed; This includes but is not limited to: Applicable United Facilities Criteria (UFC), International Building Codes (IBC, IPC, IMC, IC), National Fire Protection Association
(NPA), American Standards Institute (ANSI), American Standards of Testing Materials
(ASTM), National Electrical Safety Code (NEC), Life Safety Code.
2.4. Contractor is responsible to repair all damaged finishes on the interior caused in the performance of their work.
2.5. DEMOLITION: Demolish, remove, and dispose of existing roof system down to the roof deck, including vapor barrier, insulation; and gravel, framed roof curbs, roof parapet, flashing/cap, abandoned bird nests in the work area, and features. The contractor shall protect the work area to prevent roof and roof drain leaks to the facility at all times. The contractor shall be fully responsible for repairs of damage created by such leaks in the facility during the entire construction period. All damaged or otherwise modified finishes must be repaired/terminated according to manufacturer’s/industry standards.
2.6. INDOOR AIR QUALITY: Contractor shall shut down HVAC equipment supplying outdoor air to building occupants during all contractor odor and dust generating activities. The contractor shall protect all HVAC equipment from work generated dust contamination.
2.7. NEW EPDM ROOF SYSTEM:
2.7.1. The roof system shall be designed to meet Underwriter’s label (UL) Class A fire rating per UL 790 and Factory Mutual (FM) Class 1A-90 fire/windstorm rating.
2.7.2. The roofing system shall be reinforced EPDM, single-ply fully-adhered roofing system, black in color and a minimum sheet thickness of 60 mil. A minimum of two layers of insulation shall be provided. Insulation layers, cover board, and roofing membrane shall be installed in accordance with roofing system manufacturer’s guidance, as required to meet wind uplift requirements. EPDM Membrane: 60 mils, ASTM D 4637 Type II, reinforced.
2.7.3. Slope of roof shall not be less than 1/4:12 (vertical units to horizontal units) as measured in the valleys.
2.7.4. Vapor Barrier:
2.7.4.1. Provide minimum 30 mil self-adhered vapor barrier to the deck in accordance with manufacturer’s installation guidelines. Gaps between horizontal and vertical surfaces shall be filled with code approved backup filler.
2.7.4.2. Vapor barrier shall extend up vertical surfaces a minimum of 8” and around all roof deck penetrations. Vertical vapor barrier shall be minimum 60 mil
EPDM self-adhered flashing material installed per manufacturer’s installation guidance.
2.7.5. Roof Insulation: The roof system insulation shall be Expanded Polystyrene EPS
ASTM C 578, Type II. Minimum compressive strength shall be 15 psi. Provide a minimum of 12” roof insulation over the entire roof deck vapor barrier, including at the lip of roof drains.
2.7.6. Insulation Cover Board: Install cover board over insulation. ½” Thick, Gypsum
Fiber Roof Cover Board, USG Securock Gypsum or equal. Must be a compatible material for selected roof system, minimum thickness, ½”.
2.7.7. Abandoned Penetrations: Any abandoned penetrations found shall be infilled in such a way that the infill can support a 50 psf load and a single 400 lb point load.
2.7.8. Roof Penetrations (DWV Vents, Ventilation Ducts, & Electrical Raceways):
Extend piping, ductwork, and raceways as required to accommodate new roof system thickness and achieve existing elevation above membrane. All piping and ductwork shall have new rigid insulation with aluminum jacket installed from the top of the roof deck above the vapor barrier and extending through the roof system to the bottom of the cap. Provide roof system manufacturer membrane flashings and seals for all piping and ductwork membrane penetrations.
2.7.9. Roof System Accessories: All existing roof penetrations including roof drains, DWV vents, ventilation ducts, and electrical raceways, shall be retained at existing locations.
All abandoned penetrations shall be infilled and covered over.
2.8. ROOF PARAPETS & CURBS:
2.8.1. Curb Extensions: Curbs for rooftop equipment, if present, shall be extended where required to meet equipment manufacturer’s requirements.
2.8.2. Parapet Walls: Demo old parapet walls and construct new parapet walls to provide a minimum 6” projection above top of insulation.
2.8.3. Membrane At Parapets: At all parapets, the EPDM membrane shall be fully adhered, extend up and over the wall, continue down the exterior of the wall, and terminate under the new flashing and cap, per the roof manufacturer’s installation guidance where feasible.
2.8.4. Metal Flashing & Cap: Provide galvanized, minimum 24 gauge, flashing and cap on parapet walls, curbs, and all other areas of existing flashing associated the roof system. Flashing shall be colored where exposed to exterior view. All finish colors shall be Government approved. Cap to cover to the bottom of the existing parapet cap. No exposed fasteners on the cap.
2.8.5. Metal Copings: Perlock 150 parapet wall coping or equal. Salient features must include a galvanized steel cleat. Minimum 6” internal splice plate with colors matching the cap. No exposed fasteners on the cap.
2.8.6. Roof Overflow Scuppers: Install two 16” wide roof scuppers that will install with the bottom elevation at 2” above roof drain. Scuppers will extend beyond the face of the exterior of the building a minimum of 12”. Scupper to be constructed of metal of a sufficient gage to extend the 12” overhang with oil canning or bending under load of snow or water. Material must be of factory painted sheet metal that is of the same color as the parapet cap. Contractor to locate scuppers as shown on drawings, over primary roof drains / splash blocks.
2.9. ROOF DRAINS & PIPING: Provide two new roof drains of as shown in attached sketch.
All roof drain piping to be 3” hubless cast iron, installed per the most recent version of the
International Plumbing Code. Roof drains shall be 15” diameter cast iron with a 3” diameter outlet. Drains will have a cast iron dome cover.
2.9.1. Roof Drain Piping Location Coordination: Roof drains must be installed in the general area shown in the attached drawings. Contractor may relocate slightly if needed to accommodate existing structural/mechanical and electrical items in the interior space. All such relocations shall be pre-approved by the Contracting Officer.
At the Workshop side there is a workbench where the pipe will go through wall.
Coordinate height that rain leader exits wall with workbench back shelf so there is no conflict. This may require adjusting height from the heights shown on drawings.
2.9.1.1. Piping Support: Piping shall be supported per International Plumbing
Code requirements on clevis hangers for horizontal runs (slope per IPC), and
Unistrut type supports on vertical runs.
2.9.2. Pipe Routing: The two roof drain leaders will be routed through the interior of the building and penetrate the building at an elevation between 18” and 24” above exterior grade.
2.9.3. Piping in Exposed Areas: All exposed vertical runs of drain piping shall have the insulation covered in 0.016” thick stucco embossed aluminum roll jacketing fastened with stainless steel banding (0.020" thick stainless steel composed of alloys T304 or
T316 with annealed temper) according to manufacturer’s recommended intervals.
2.9.4. Piping Through Wall: Through-the-wall gap shall be foamed (trimmed flush), and annular space covered on interior side with chromed escutcheon plate.
2.9.4.1. Contractor is responsible for repair/re-establishment of the vapor barrier at all new penetrations.
2.9.5. Exterior Spout: The rain leaders will finish on the exterior with a bronze spout;
2.9.5.1. Material: Cast Bronze Nozzle and Flange.
2.9.5.2. Body: Machined inside finish nozzle, slides over cast iron pipe, with set screws, and 4 securing holes on flange.
2.9.5.3. Outlet: No less than 5-5/8” effective dripline distance from flange to end of spout, with spout fitted tight to wall.
2.9.5.4. Basis-of-Design Product: Subject to compliance with requirements, provide Jay R Smith Mfg. Co. Figure Number 1771 or comparable product with equal or greater dripline distance.
2.9.6. Concrete Splash Blocks:
2.9.6.1. Provide 24”x36” concrete splash block of the dimensions and construction shown. The angled back is a critical feature that is not found on standard splash blocks. Fairbanks Precast & Rebar is a local source who is known to be able to produce these, though any reputable pre-caster also can.
2.9.6.2. Install two new splash blocks, one under each spout, up against building foundation. Splash blocks to be 24” x 36” precast, constructed according to the drawings, with backside clearance slope, and interior slope.
2.9.6.3. Secure splash block from slippage away from building by driving two
36”L #6 rebar in the ground at the bottom end, per splash block.
2.9.6.4. Grade and compact soil to slope away from building foundation prior to setting splash blocks.
2.10. ROOF DRAIN HEAT TRACE: Provide electric self-limiting 12-Watt armored-type heat trace at all downspouts. Heat trace shall be UL listed, self-crossing non-overheating type, and
IEEE-515 compliant. Work shall include providing of primary power circuit, ambient air-sensing thermostatic central heat trace controller, branch circuits, circuit ground-fault protection, elevated J-boxes, raceway, and supports, as required, for a complete functional system.
2.10.1. Self-Regulating Heat Trace: Basis of design, Raychem ICESTOP GM-2X, or equal, having the following salient features:
2.10.1.1. Capable of demonstrating a lifetime in excess of 25 years.
2.10.1.2. The system shall be complete with cold components, energy efficient controls and a 10-year product warranty.
2.10.1.3. The self-regulating heating cables shall have modified polyolefin electrical insulation (radiation cross-linked, to ensure long life expectancy), tinned copper braid and UV resistant, modified polyolefin over jacket with dimension marks for ease of installation.
2.10.1.4. The heating element in heating cable shall consists of a continuous core of conductive polymer extruded between two copper bus wires. As current flows through the core, the heating cable shall regulate its own heat output in response to ambient conditions.
2.10.1.5. Self-regulating feature, which eliminates hot spots, resulting in better temperature control.
2.10.2. Heat Trace Controller: Basis of design, Raychem EC-TS, or equal, having the following salient features:
2.10.2.1. Electronic pipe sensing thermostat for pipe freeze protection applications.
2.10.2.2. Suitable for use for controlling a single heat-tracing circuit or as a pilot to control a contactor switching multiple heat-tracing circuits.
2.10.2.3. The temperature set point can be visually checked through the clear lid, as can the LED indicators for alarm, power and heating cable status.
2.10.2.4. The stainless steel sensor thermostat suitable for applications that require an embedded sensor, with a set point range for the thermostat between 30°F and
110°F.
2.10.2.5. Operates at voltages between 100 to 277 Vac and switches current to 30
Amps.
2.10.3. Power to Heat Trace: Provide primary power circuit from building service panel to exterior ambient air-sensing central controllers.
2.10.3.1. Raceway: Interior mounted raceway shall be minimum EMT and painted to match adjacent surfaces when exposed to public view. RGS conduit with threaded fittings to be installed for all exterior applications. Conduit to be painted to match the section of the building that it is mounted to.
2.10.3.2. Branch Circuits: Provide branch circuits (to also include breakers) and raceway from controllers to heat trace J-boxes. Fixed outdoor electric deicing and snow-melting equipment to be considered a continuous load when sizing branch circuits, feeders, service conductors, and OCPDs.
2.10.3.3. Circuit Protection: Heat trace system circuits shall be protected by a 30-mA GFEPD.
2.10.3.4. Controls: Heat-tracing circuits shall be controlled by an ambient temperature sensing electronic temperature range adjustable thermostat configured with remote exterior mounted temperature sensor. Controller shall be located within conditioned mechanical space and accessible to maintenance personnel. Controller shall be used for single heat-tracing circuit control or as a pilot control of a contactor switching multiple heat-tracing circuits. Controller switch shall be SPST (normally open) type. System “ON” set-point shall be 35F
(adjustable). Heat trace system circuits shall be protected by a 30-mA GFEPD.
Heat-trace controller basis of design Raychem EC-TS, or equal. New conduit and boxes shall be painted to match existing exterior.
2.10.3.5. Labeling: Provide permanent labels to identify panel, and circuits, for disconnect on junction boxes and MDP. Label new circuits in the load center.
2.10.4. Routing Heat Trace: Drain leader downspout heat trace shall be looped through piping, from the exterior up into the drain spout, a minimum of 4-feet up into downspout with looped end at outlet tucked back into piping minimum 1-feet. Drain leader heat trace shall be powered from an exterior mounted weatherproof J-box. Heat trace wiring to exit weatherproof box through a waterproof gland seal meeting the
National Electrical Code for the application.
2.11. ITEM DELETED.
2.12. SITE COORDINATION:
2.12.1. Contractor is responsible for, in coordination with COR, moving work benches and other equipment out of the way as needed to perform their work, and moving it back in place when work is done.
2.12.2. Contractor is responsible for all supportive work (dismantling, reinstallation) necessary to the suspended ceiling for gaining access, and then for restoring it to its prior condition after work is done. Any T-bar or panels damaged by contractor shall be replaced at contractor’s expense.
2.13. Contractor Field Verify:
2.13.1. Existing Truss Slope: The building has no original as-built drawings. Field observations indicate the trusses are set to sheet drain from the north side of building to the south side. The actual measurements were not conclusive due to snow load.
Contractors must field verify prior to submitting bids, and submitting shop drawings, since the truss slope will affect roof insulation thicknesses and profiles and roof and parapet construction.
2.13.2. Contractor shall field verify all necessary building conditions and measurements prior to submitting bids, and submitting shop drawings.
3. SCHEDULE: Work shall commence no later than 10 days after receipt of Notice to Proceed
(NTP). All preconstruction requirements shall be completed NLT 15 days after NTP. Onsite construction may commence upon NTP, but shall start NLT 30 days after NTP. Construction shall be 100% complete no later than Period of Performance.
The Contractor’s Preliminary Schedule shall be submitted with the bid/proposal.
3.1. Notice To Proceed (NTP): The Contracting office shall issue NTP pending receipt of acceptable Bonding and Insurance documentation by the Contracting Office.
3.2. Period of Performance (POP): Pursuant to the Contractor’s schedule submitted at proposal, the project is expected to take 100 days from the start date to the end date. The Contractor’s proposed submitted schedule is subject to Government review and approval.
3.3. PROJECT SCHEDULE. Prepare for approval a Project Schedule, as specified herein. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.
3.3.1. Approved Project Schedule. Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the
Contractor submits the required schedule.
3.3.2. Schedule Status Reports. Provide a Schedule Status Report/Schedule Update on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government.
3.4. BASIS FOR PAYMENT AND COST LOADING. Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial, and subsequent schedule updates. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the
Schedule.
3.4.1. Activity Cost Loading. Activity cost loading must be reasonable and without front-end loading. Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.4.2. Withholdings / Payment Rejection. Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met. In the event the Contracting Officer directs schedule revisions, those revisions shall be included in subsequent Project Schedule revisions or updates.
3.5. PROJECT SCHEDULE DETAILED REQUIREMENTS. Critical Path Method - Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule.
3.5.1. Level of Detail Required. Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.5.2. Activity Durations. Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
3.5.3. Procurement Activities. The schedule must include activities associated with the submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 60 calendar days or material lead times that will negatively affect project parameters of an individual task order. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.5.4. Mandatory Tasks. Include the following activities/tasks in the initial project schedule and all updates:
a. Submission, review and acceptance of Preconstruction Submittals (individual activity for each).
b. Submission of specialized layout drawing (mechanical/electrical systems).
c. Long procurement activities
d. Submission and approval of as-built drawings.
e. Submission and approval of DD1354 data and installed equipment lists.
f. Contractor's pre-final inspection.
g. Correction of punch list from Contractor's punchout inspection.
h. Government's pre-final inspection.
i. Correction of punch list from Government's pre-final inspection.
j. Final inspection.
3.5.5. Percent Complete. With each update, update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete. To allow for proper schedule management, cost load the correction of punch list from government pre-final inspection activity(ies) not less than 1% of the total contract value which activity(ies) may be declared 100% complete upon completion and correction of all punch list work identified during pre-final inspection(s).
3.5.6. Remaining Duration. Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
3.5.7. Anticipated Adverse Weather. Reflect the number of anticipated adverse weather delays allocated to a weather sensitive activity in the activity's calendar.
a. The following schedule of monthly anticipated adverse weather delays is based on NOAA data and will constitute the baseline for anticipate adverse weather.
b. Time extensions may be granted under the DEFAULT contract clause if the weather at the site is more severe than the adverse weather anticipated for any given month and if the unusually severe weather can be shown to actually cause a delay to the completion of the project – that is cause impact/delay to activities on the critical path. The delay must be beyond the control and without fault or negligence of the contractor.
c. Monthly Anticipated Adverse Weather Delay Work Days Based on 5 Day
Work Week: Jan 22, Feb 20, Mar 14, Apr 0, May 0, Jun 0, Jul 4, Aug 3, Sep 4, Oct 1, Nov 20, Dec 22.
3.5.8. Early Completion Schedule and the Right to Finish Early. An Early Completion
Schedule is an Initial Project Schedule (IPS) indicating all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an early completion will be accepted without being fully resource- loaded (including crew sizes and manhours) and the Government agreeing the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.6. PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made. Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.6.1. Preliminary Project Schedule Submission. Preliminary Project Schedule shall be provided at time of solicitation of contract. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract as well as permitting activities, and other non-construction activities intended to occur within the first 30 calendar days. Schedule any construction activities planned for the first 30 calendar days after NTP.
3.6.2. Initial Project Schedule Submission. Submit the Initial Project Schedule for approval within 30 calendar days after NTP is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. The Initial Schedule shall be at a reasonable level of detail as determined by the Contracting Officer.
3.6.3. Periodic Schedule Updates. Update the Project Schedule on a regular basis, monthly at a minimum. Provide a draft Periodic Schedule Update for review at the schedule update meetings as prescribed in the paragraph PERIODIC SCHEDULE UPDATE
MEETINGS. These updates will enable the Government to assess Contractor's progress. If the Contractor fails or refuses to furnish the information and project schedule data, which in the judgement of the Contracting Officer or authorized representative is necessary for verifying the Contractor's progress, the Contractor shall be deemed not to have provided an estimate upon which progress payment may be made.
3.7. SUBMISSION REQUIREMENTS. Submit the following items for the Preliminary
Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:
3.7.1. Narrative Report. Provide a Narrative Report with the Preliminary, Initial, and each
Periodic Update of the project schedule, as the basis of the progress payment request.
The Narrative Report shall include: a description of activities along the two most critical paths where the total float is less than or equal to 20 work days, a description of current and anticipated problem areas or delaying factors and their impact, and an explanation of corrective actions taken or required to be taken. The narrative report is expected to communicate to the Government, the Contractor's thorough analysis of the schedule output and its plans to compensate for any problems, either current or potential, which are revealed through that analysis. Identify and explain why any activities, based on their calculated late dates, should have either started or finished during the update period but did not.
3.7.2. Approved Changes Verification. Include only those project schedule changes in the schedule submission that have been previously approved by the Contracting Officer.
3.7.3. Network Diagram. The Network Diagram is required for the Preliminary, Initial, and Periodic Updates. Depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:
3.7.4. Continuous Flow. Show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated earned value on the diagram.
3.7.5. Project Milestone Dates. Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.
3.7.6. Critical Path. Show all activities on the critical path. The critical path is defined as the longest path.
3.8. PERIODIC SCHEDULE UPDATE
Periodic Schedule Update Meetings. Conduct periodic schedule update meetings for the purposes of reviewing the Contractor's proposed out-of-sequence corrections, determining causes for delay, correcting logic, maintaining schedule accuracy, and determining earned value. The meeting and resultant approvable schedule update shall be a condition precedent to a formal submission of the update as described in SUBMISSION REQUIREMENTS and to the submission of an invoice for payment. The meeting will be a working interactive exchange which will allow the Government and the Contractor the opportunity to review the updated schedule on a real time and interactive basis. The Contractor's Project Manager/Superintendent shall attend the meeting with the Authorized Representative of the Contracting Officer.
3.9. REQUESTS FOR TIME EXTENSIONS. Provide a justification of delay to the Contracting
Officer in accordance with the contract provisions and clauses for approval within 10 days of a delay occurring. Also prepare a time impact analysis for each Government request for proposal (RFP) to justify time extensions.
3.9.1. Justification of Delay. The project schedule shall clearly display the Contractor has used, in full, all the float time available for the work involved with this request. The
Contracting Officer's determination as to the number of allowable days of contract extension shall be based upon the project schedule updates in effect for the time period in question, and other factual information. Actual delays found to be caused by the Contractor's own actions, which result in a calculated schedule delay, will not be a cause for an extension to the performance period, completion date, or any interim milestone date.
3.9.2. Submission Requirements Time Extension. Submit a justification for each request for a change in the contract completion date of less than 2 weeks based upon the most recent schedule update at the time of the NTP or constructive direction issued for the change. Such a request shall be in accordance with the requirements of other appropriate Contract Clauses and shall include, as a minimum:
a. A list of affected activities, with their associated project schedule activity number.
b. A brief explanation of the causes of the change.
c. An analysis of the overall impact of the changes proposed.
d. A sub-network of the affected area.
e. Identify activities impacted in each justification for change by a unique activity code contained in the required data file.
3.11.3 Additional Submission Requirements Time Extension. The Contracting Officer may request an interim update with revised activities for any requested time extension of over 2 weeks. Provide this disk within 4 days of the Contracting Officer's request.
3.10. FAILURE TO ACHIEVE PROGRESS. Should the progress fall behind the approved project schedule for reasons other than those that are excusable within the terms of the contract, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.
3.10.1. Artificially Improving Progress. Artificially improving progress by means such as, but not limited to, revising the schedule logic, modifying or adding constraints, shortening activity durations, or changing calendars in the project schedule is prohibited. Indicate assumptions made and the basis for any logic, constraint, duration, and calendar changes used in the creation of the recovery plan. Any additional resources, manpower, or daily and weekly work hour changes proposed in the recovery plan must be evident at the work site and documented in the daily report along with the Schedule Narrative Report.
3.10.2. Failure to Perform. Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and/or may result in corrective action directed by the Contracting
Officer and other contract provisions.
3.10.3. Recovery Schedule. Should the Contracting Officer find it necessary, submit a recovery schedule.
3.11. OWNERSHIP OF FLOAT. Float available in the schedule, at any time, shall not be considered for the exclusive use of either the Government or the Contractor.
3.12. Final Approved Schedule, provided by contractor, will be incorporated in the award.
3.13. Definable Features of Work (DFOW): Each DFOW is subject to a 3-phase control inspection conducted by the contractor's QC. At a minimum, the DFOW list shall include tasks as follows:
3.13.1. Demolition
3.13.2. Vapor Barrier
3.13.3. Parapet & Curbs
3.13.4. Parapet & Curb Insulation
3.13.5. Roof Insulation System
3.13.6. Roof Drainage System
3.13.7. EPDM Roofing System
3.13.8. Roof Flashing & Trim
3.13.9. Electric Heat-Trace
3.13.10. Concrete Splash Blocks
4. MEETINGS:
4.1. Preconstruction Conference
After award and Notice to Proceed (NTP) has been issued by the Contracting officer and prior to the start of any construction work the Government will schedule and conduct a preconstruction meeting. The Contractor's Project Manager and Quality Control Manager will attend this meeting. The Contractor is encouraged to have an officer of his company and representation from his sub-contractors at this conference. This meeting will be held at the location specified by the Government. Minutes of the meeting will be prepared by the
Contractor and submitted to the Government for review and approval. The minutes shall become a part of the contract file.
4.2. Start of Construction Work
If the Contractor has submitted all the preconstruction submittals required by contract
(Accident Prevention (Safety) Plan, Quality Control Plan, Environmental Protection Plan, Sampling and Analysis Plan, Storm Water Pollution Prevention Plan or Erosion and Sediment
Control Plan, Project Schedule and Submittal Register) for review prior to this meeting, these may be accepted into or accepted with comments at the Preconstruction Meeting.
Construction work shall not proceed until after this meeting has been held, the plans noted above have been accepted, and the Notice to Proceed has been received and acknowledged by the Contractor.
4.3. WEEKLY COORDINATION MEETINGS
The Contractor shall participate in weekly coordination meetings with the Contracting
Officer’s Representative and other Government representatives, as applicable. The Contractor shall be responsible for preparing the agenda in coordination with the Contracting Officer, distributing the agenda, conducting the meeting, preparing the meeting minutes, distributing the minutes, and tracking action items. The Contractor's superintendent and QC System
Manager shall attend each meeting. Typical topics shall consist of but not limited to the following: review of the previous week's activities and progress; forecast of the following 2 week's activities and progress; upcoming utility outage or street closure; status of shop drawing submittals and reviews; status of outstanding requests-for-information (RFI); status of pending modifications; anticipated modifications; proposed schedule changes; other concerns/and or issues.
4.4. OTHER MEETINGS
Construction Quality Control meetings and conferences are specified in follow on Sections about CONTRACTOR QUALITY CONTROL. Other meetings may be specified in various other sections. It shall be the contractor’s responsibility to review all contract documents and schedule and participate in all required meetings.
Government reserves the right to request additional meetings with contractor at any time during this contract that may not be specified in this or other sections of the contract..
5. OCCUPANCY:
5.1. The building included in the scope of this contract will be occupied. The contractor will schedule and perform work under this contract in such a manner as to allow the occupants of the building to continue their normal activities with the least amount of interference. The parking lots adjacent to the facility may be closed due to safety consideration during construction. The Contractor is responsible for securing the job site and keeping the public/occupants from entering into areas of danger.
6. SUBMITTALS:
6.1. Submittal Register: A preliminary submittal register is provided with solicitation. The submittal register provided by the Government contains the minimum submittals the
Government sees as necessary and may not be all inclusive. Contractor will be responsible, as part of Contractor Quality Control responsibilities to review the Government provided submittal register, the contract, statement of work, drawings, and all applicable specifications for this task order and NLT 10 work days after award, Contractor shall supplement the
Government provided submittal register with additional items required to be submitted as determined from the review.. The supplemented/augmented submittal register shall be submitted to the Government for review and shall be updated and adjusted as necessary throughout the period of performance.
6.2. General Summary (SUBMITTAL PROCEDURES AND SOFTWARE REQUIREMENTS):
Shop drawing and product data submittals shall be transmitted to the government in electronic
(PDF) format using ENG Form 4025. A copy of this form in PDF will be made available to the contractor from the Contracting Officer’s Representative (COR). Information and training on the process and flow for submittals will be provided by (COR) after award and prior to start of making submittals. The Contractor shall allow adequate time for government review of all submittal documents. Government review shall be 14 calendar days unless otherwise indicated in this contract.
6.3. Contractor shall submit a schedule of values (SOV) to be used for partial payments processing.
6.4. Submittals shall be accompanied by a completed ENG Form 4025-R; incomplete submittals will be rejected without action pending completion. Submittals shall be submitted directly to
Government Quality Assurance Representative (QA) with copy to Government Contracting
Officer’s Representative (COR) and Project Manager (PM). When directed, or as specified, the Contractor shall provide information and/or submit samples of equipment and materials that the Contractor contemplates incorporating in the work. All submittals shall be at the
Contractor’s expense. All items on 4025 submittal shall be restricted to a single contract technical section.
6.5. Closeout submittals: In addition to paper copies, all closeout submittals shall be submitted in searchable digital format on a single CD or DVD. If searchable documents are not available
(in the case of handwritten reports) scanned .pdf files will be acceptable. Contractor may choose to submit the digital submittal disc after the paper copies have been approved.
6.5.1. O&M Manuals: Provide O&M Manuals for Heat Trace System and its Components.
6.6. Job Progress Photos: Contractor shall provide the government with job progress photos, on a
CD at turnover, showing a complete depiction of job progress at all stages of the work.
6.7. As-Built Drawings: Contractor shall provide the government with as-built drawings at turnover, showing a complete depiction of the new roof, to include a description of all materials installed, thicknesses, slopes, and dimensions of key components.
6.7.1. Final as-built drawing set shall be submitted by the Contractor through the
Government Quality Assurance Representative. The contractor shall submit final as-built drawings through the Government Quality Assurance Representative to the Ft.
Wainwright DPW Plans Vault in Building 3013. As-built record drawings shall consist of one (1) disc containing the electronic file(s) in AutoCAD .dwg format, Release 2017 or earlier and in PDF format. AutoCAD files shall be purged, audited, and virus scanned prior to delivery. Files shall include all loaded and relevant external references, associated linetypes, fonts, blocks, plot style table (.ctb) file(s) image file(s), etc. AutoCAD files shall be ‘eTransmitted…’ or similar in order to gather all associated supporting files. AutoCAD drawings shall utilize the coordinate systems referenced in section 01 19 30 of this publication. Items shall be accompanied with a completed DD Form 250, and ENG DA Form 4025. Coordinate with Government
Contracting Officer’s Representative (COR) for proper completion of these forms. If questions arise pertaining to the Record As-built submittals, contact the DPW Plans
Vault staff.
6.7.2. To facilitate the conversion of final as-built drawing AutoCAD data into GIS data layer format, the final submittal shall include a separate folder directory containing electronic files in AutoCAD .dwg format, Release 2013. Each AutoCAD 2013 .dwg file shall contain a layer, or layers, of like content line work for new and modified civil site and utility feature changes made to the project site as a result of this contract
(facility footprints, utility installations and modifications, roads, parking areas, sidewalks, pads, fences, gates, etc.). For example, a single .dwg file shall contain only closed polylines representing new and/or modified sidewalk features within the project site. Each AutoCAD 2013 .dwg file of like content shall be named similarly to the layer name utilized in the final as-built drawing electronic files. Contractor shall coordinate with DPW GIS Coordinator (Craig Ostrom 361-4163) for more information.
The DPW Ft. Wainwright Plans Vault is located in Building 3013. The Plans Vault houses prior engineering project as-built data and hazardous material reports. Data may be requested by contacting the Plans Vault, Rich Gordon 361-6142 or Geoff
Shores 361-1778. A DPW Drawing Request Form may be obtained in the entryway of the Plans Vault and must be completed and submitted prior to any data being transmitted.
Contractor submitted AutoCAD data shall conform to current U.S. Army Engineer
Research and Development Center (ERDC) and Information Technology Laboratory
(ITL) standards to the maximum extent possible. Horizontal Coordinate data shall be
NAD 1983 StatePlane Alaska 3 FIPS 5003 in feet (WKID: 102633) and vertical coordinates in NAVD88 height (ftUS)(WKID: 6360).
6.7.3. Geographic Information System (GIS) Data - The contractor shall submit a File
Geodatabase (.gdb file format) containing geospatial data representing final as-built conditions of all civil site changes to the project area as a result of this contract. The
File Geodatabase schema shall follow the current U.S. Army template provided to the contractor by the Government or the contractor shall obtain the current U.S. Army template from the Spatial Data Standards for Facilities, Infrastructure and
Environment (SDSFIE) website (https://www.sdsfieonline.org).
The File Geodatabase submittal shall conform to the current U.S. Army Spatial Data
Standards for Facilities, Infrastructure and Environment (SDSFIE) and Installation
Geospatial Information and Services (IGI&S) Program Quality Assurance Plans
(QAP) to the maximum extent possible. Contractor shall not utilize the GIS shapefile format when exporting data from AutoCAD to ArcGIS. The File Geodatabase shall utilize the projected WGS 1984 UTM Zone 6N (WKID: 32606) horizontal coordinate system. Vertical coordinate system elevation values shall be stored in the File
Geodatabase Feature Class attribute table when applicable. Contractor shall coordinate the Geographic Transformation method and all other project related GIS subject matter with the DPW GIS Coordinator (Craig Ostrom 361-4163) for more information.
7. TRAFFIC CONTROL:
7.1. Contractor shall submit to the Government as a For Information Only (FIO) traffic control plans (if applicable) prepared by a certified traffic control supervisor meeting all MUTCD, Alaska Sign Design Specifications (ASDS), and Alaska Traffic Manual (ATM).
7.2. As part of the traffic control plan, Contractor shall provide at all times channelized pedestrian access, emergency access to adjacent buildings, residential access, and cross traffic, unless otherwise approved. Contractor will also need to provide business access during business hours.
7.3. Parking Area Closures: The contractor shall coordinate temporary closure of parking areas located between buildings with the Government. If the Contractor’s traffic control or work plan proposes temporary shutdown of parking lots adjacent to the work locations, the
Contractor shall as part of the traffic control plan/work plan identify alternative parking locations for displaced vehicles during closures and identify proposed detour routes. Parking area closures, including contractor notice of closure to Government, shall be indicated on the schedule. The contractor shall provide a minimum 7-days advance notice to the Government prior to closing parking areas. The contractor temporary closure barriers shall not restrict passage of Fire Department and other emergency vehicles.
https://www.sdsfieonline.org/
7.4. Contractor shall provide suitable for public distribution, road detour/closure plans, no less than one (1) week prior to planned road closures (if applicable).
7.5. Coordinate traffic control with other construction in the area.
7.6. Cover existing signs which conflict with construction signing.
7.7. Laydown Plan: Contractor shall identify and submit for Government approval Contractor’s proposed laydown area.
8. WARRANTY:
8.1. All work shall be covered under the 1-year warranty of construction required by contract.
Contractor shall provide Government with phone numbers and email addresses of primary and alternate Warranty POC’s for both regular work days/duty hours warranty calls and also primary and alternate Warranty POC’s for holiday/weekend/after normal duty hours warranty calls.
8.2. In addition to the 1-year warranty of construction, the contractor shall obtain / provide standard 10-year warranty, using the wind speed criteria for Fairbanks, Alaska, and attached specifications.
8.3. The contractor shall obtain / provide all extended warranties, greater than 1-year, that would normally be given in commercial practice and, upon final acceptance of the work (or before), provide a list to the Government of each extended warranted equipment item, feature of construction, or system. As applicable, the list shall include the status of delivery of all
Certificates of Warranty for extended warranty items, to include roof and heat trace. The list shall indicate the following:
Name of item.
Model and Serial Number.
Installed location.
Name and phone numbers of manufacturers or suppliers.
Names, addresses, and phone numbers of sources of spare parts.
Warranties and terms of warranty. Items with warranties extending beyond the one-year warranty shall be indicated with separate warranty expiration dates.
Start date and duration of warranty period.
Summary of maintenance procedures required to continue the warranty in force with cross-reference to specific pertinent operation and maintenance manuals as applicable.
8.4. At approximately four (4) and nine (9) months after acceptance the Government will conduct warranty inspections. The inspections will be scheduled by the Government Project Manager and conducted with the user, and, if possible, Contractor personnel attending. A list of warranty items existing at the time will be compiled and furnished to the Contractor for correction.
9. SAFETY:
9.1. Contractor shall use all appropriate safety equipment and apply sound safety practices.
Contractor shall fully comply with most current version of NFPA, OSHA, and Federal standards as applicable. Contractor shall obtain hot work permit from Fire Dept for welding, cutting, brazing. Soldering.
9.2. The contractor shall comply with 29 CFR part 1926, 29 CFR part 1910, all state and local occupational safety and health requirements, and the requirements of latest version of EM
385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual. A Site
Safety and Health Officer will not be required.
9.3. Prior to the start of work, the contractor shall submit for approval a site specific Site Safety and Health Plan (SSHP) also referred to elsewhere in this contract as an Accident Prevention
Plan (APP). The plan shall be developed by a qualified person and be signed by a competent person and a representative of the prime contractor’s project management team. The plan shall meet the minimum basic outline requirements contained in EM 385-1-1, Appendix A.
The plan shall be job-specific and shall include work to be performed by subcontractors and measures to be taken by the contractor to control hazards associated with materials, services, or equipment provided by suppliers. The accident prevention plan shall include procedures for frequent safety inspections, conducted by competent persons, of the work sites, material, and equipment to ensure compliance with the plan and other referenced standards. Unless otherwise approved, Quality Control personnel or Superintendent shall conduct and document daily safety inspections.
9.3.1. Due to the limited scope of this project, the Contractor may submit to the Government for approval, an abbreviated APP. The abbreviated APP shall meet the requirements set forth in EM 385-1-1 and follow the format outlined in Form A-01 of EM 385-1-1.
10. ENVIRONMENTAL PROTECTION:
10.1. All work shall be completed in accordance with applicable environmental laws, regulations, and latest version of IMFW-PWE document Environmental Requirements for Construction, Demolition and Renovation Projects. The document identifies the requirements for
Contractors handling of wastewater, backflow prevention, hazardous waste and hazardous material, solid waste, spill reporting, air quality, fuel storage, natural resources, and cultural resources. A copy of this document is provided as an Attachment.
10.2. The Contractor will be required to obtain a dig permit for this project.