This document outlines the statement of work for solicitation number 127EAW23R0064 issued by the Department of Agriculture Forest Service. The solicitation requires replacement of the septic system at the Santa Barbara District Office, including pumping the existing tank, removing and disposing of the old tank and distribution lines, installing a new 1,500 gallon septic tank and 125 linear feet of distribution piping, repairing asphalt, and providing as-built drawings. The period of performance is 14 calendar days with work to begin within 10 days of notice to proceed. Bidders must hold a valid C-36 Plumbing Contractor license from California and comply with Davis-Bacon prevailing wage requirements and Buy American provisions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 Statement Of Work
Santa Barbara District Office Septic System Replacement
1 - Scope of Contract The Los Padres National Forest is seeking a qualified and licensed contractor for the replacement of the septic tank and distribution lines for the Santa Barbara District Office located at 3505 Paradise Road, Santa Barbara, CA 93105. The existing septic system was recently inspected and determined that the septic tank interior baffle wall had deteriorated and can no longer promote the separation of solids from liquid. Therefore, failure in the baffle wall is causing solids to enter the drain lines and into the drain field – there are no reports of drain field failure. As a result, sewage is being pumped periodically from the septic tank, to address health and safety concerns, while allowing the continuous use of the district office.
Contract work will address the issue at Santa Barbara District Office by replacing the old septic tank with a new 1,500-gallon low profile septic tank. Work is also to include:
• Pumping of existing 1,000-gallon septic tank.
• Removal and disposal of existing septic tank and contents.*
• Removal and disposal of existing drain line from the district office over to the leach field tie-in.*
• Provide and install new 1,500-gallon plastic low profile septic tank.
• Provide and install two manhole extension collars with manhole lids. Manhole extension collars should be (24-36 inches) based on the depth that the septic tank is buried. Manhole covers shall extend about 4 inches above finished ground grade.
• Provide and install approximately 125 linear feet of distribution ABS piping. Replace distribution piping from the district office to the septic tank and from septic tank over to the tie-in for the drain field.
Distribution piping should be placed in approximately the same location as the existing distribution line that is to be removed.**
• Provide 6 inches of fill material for trench bedding for distribution line. (3’x125’x6”). Also provide 12 inches of bedding material for septic tank placement (approximate dimensions 58” x 157” x 12”).
• Saw cut asphalt and dispose of waste (approximately 3 feet wide by 30 feet in length).**
• Replace removed asphalt for parking lot (3’x30’x4”).**
At the close-out of the contract, the contractor shall provide the Government with a set of as-built drawings showing all components of the new septic system.
The Contractor shall provide all labor, materials, and equipment to complete the contract as shown on the drawings and included in the specifications. The contractor is responsible for securing all permits, fees and requirements from state and local county offices.
Contract Line Item
Supplies/Services
0001 Mobilization 0002 Pumping Services - requires contractor to schedule a pumping service call for the existing 1,000 gallon septic tank.
0003 Removal of Old Septic Tank *- removal and disposal of existing septic tank and contents.
See Sheet Number C-02
0004 Installation of New Septic Tank - purchasing and installation of new 1,500 gallon plastic low profile septic tank. Work is also to include the installation of (2) manhole covers and lids.
See Sheet Number C-02, D-01 and Specification Section 221353 – Facility Septic Tanks
0005 Old Distribution Lines * - requires contractor to remove and dispose of old distribution lines.
0006 New Distribution Lines **- contractor shall provide and install new distribution lines which should be placed in approximately the same location as the existing distribution lines that are to be removed.
See Sheet Number C-02, D-01 and Specification Section 221319 – Sanitary Waste Piping Specialties
0007 Old Asphalt * - saw cutting, removal and disposal of existing asphalt for distribution line placement.
See Sheet Number C-02
0008 New Asphalt **- purchase and install new asphalt for parking lot repair.
See Sheet Number C-02, D-01 and Specification Section 321226 – Asphalt Paving
0009 Fill Material **- fill material needed for bedding.
See Sheet Number C-02
* Since space is limited at the site, contract work will require the removal and disposal of existing septic system components. The following items will need to be removed and disposed of in accordance with all Local, State, and Federal regulations and laws governing such disposal. A manifest of waste will need to be provided to the COR for contract closeout.
**Quantities are estimated quantities based on where the technician believes the distribution line is located and estimated dimensions for septic tank. Pay items will be for actual quantities used or removed for the project.
2 - Project Location Santa Barbara District Office: 3505 Paradise Road. Santa Barbara, CA 93105.
From Solvang, CA travel east on CA-246E/Mission Road for approximately 4.9 miles. Keep right to continue toward CA-154 E. Continue traveling down CA-154 E for approximately 13.2 miles. Turn left onto Paradise Road and continue down this path for approximately 4.5 miles. The destination will be on the left-hand side of the road.
3 – Time of Performance The period of performance is 14 calendar days .
Contractor must begin work within 10 days of the effective date of the Notice to Proceed.
4 – Site Visit A self-guided site visit is encouraged for the contractor to do between the hours of 8:00AM – 5:00PM Monday through Friday.
5 – Disclosure of the Magnitude The price range of this project is between $25,000 and $100,000.
6 - Restrictions on Work
1. In accordance with the fire plan, included in attachments.
2. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
3. No work on holidays without prior written approval of the Contracting Officer.
7 - Worker's Compensation Insurance The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.
8 – Special Conditions Affecting Work
a. Work Hours. Work hours are from 8:00AM to 5:00PM Monday through Friday. Weekend or holiday work is not allowed at any time during construction without written approval from the Contracting Officer.
b. Safety, Emergency Communications and Evacuation. Contractor shall be responsible for the safety of the Contractor’s employees, Subcontractor’s employees, Government employees associated with the project, and any visitors to the site both Government and private. The Contractor shall submit a project safety plan to the Contracting Officer for review prior to commencement of work. The project safety plan shall comply with the appropriate California OSHA and Federal OSHA rules and regulations and must include a medical evacuation and emergency communications plan.
c. Highway Permits. Contractor shall be responsible for securing any overload or over width limit permits required for the transport of materials or equipment to the project site. The Contractor shall be responsible for conducting a thorough reconnaissance of all routes leading to the site.
d. Security. The Contractor shall be responsible for his own equipment and materials supplied to the site. All equipment not equipped with a key lock system shall be secured in such a manner as to make it inoperable to the average person at the end of each working day. All hand tools and other equipment shall be secured at the end of each working day. On Fridays all construction debris, trash, and refuse shall be properly stored in dumpsters or trash bins or removed from the site. The Contractor shall not hold the Government liable for any theft or vandalism inflicted on his equipment and materials.
e. Fire Prevention. The Contractor shall comply with the Fire Plan included in the Contract.
f. Protection of Resources. Contractor shall thoroughly clean all equipment prior to delivery to the project site to remove weeds, mud, grease and oil buildup from the tires, wheels, tracks, engines and engine compartments, and other surfaces. Spills of petroleum products and other hazardous substances shall be reported, contained, and removed in accordance with all applicable Local, State and Federal laws and regulations. Inspection of equipment is required prior to off-loading.
g. Site Inspection: Prospective bidders are strongly encouraged to inspect the project site prior to the bid reply date. In no event shall the failure to inspect site conditions constitute grounds for a claim after contract award.
h. Questions: Prospective bidders desiring an explanation of the solicitation, drawings, specifications, etc.
must submit requests in writing to the Contracting Officer. Oral explanations or instructions given will not be binding.
i. Business Operations: Contractor’s work shall not interfere with business operations of Forest Service roads.
9 – Project Site Cleanup Project site cleanup includes the daily removal and proper disposal of all trash, debris, and residue of National Forest Land. All spills of petroleum products including leak spots from parked vehicles shall be removed and properly disposed of according to all Local, State, and Federal regulations and laws governing such disposal.
The Contractor is required to dispose of all construction debris and removed equipment off of Forest Service lands in accordance with Federal, State, and local requirements. The Contractor is required to furnish dumpsters or other trash receptacles and to empty such containers either as they become full or weekly, whichever is more frequent. The Contractor shall not place materials of any kind into private or Government trash bins or dumpsters.
10 – Contractor Qualifications and Licenses Contractor and/or subcontractor must possess a valid license to perform the applicable contract work issued by the State of California. Contractor must possess a current and valid C-36, “Plumbing Contractor” license issued by the State of California to perform the applicable contract work. Proof of certification shall be provided to Government attached to the bid proposal reply.
11 – Prevailing Wage This contract is subject to Davis-Bacon Act prevailing wage requirements.
12 – Buy America Act This contract is subject to the Buy American Act.
13 – Warranty Contractor shall warranty all equipment, material, design, and/or workmanship for a period of not less than 1 year from the final date of acceptance. See FAR Clause 52.246-21. All manufacturers’ equipment warranty information shall be submitted to the Contracting Officer prior to project completion. See Specifications for additional Warranty requirements specific to this project.
14 – Maps, Drawings and Specifications Maps -Included with Drawings Drawings -Project Drawings have been attached.
Specifications -Project Specifications These specifications are attached to this solicitation.
The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
| Attachment 1 Statement Of Work |
| Santa Barbara District Office Septic System Replacement |
| 1 - Scope of Contract |
| 2 - Project Location |
| 3 – Time of Performance |
| 4 – Site Visit |
| 5 – Disclosure of the Magnitude |
| 6 - Restrictions on Work |
| 7 - Worker's Compensation Insurance |
| 8 – Special Conditions Affecting Work |
| 9 – Project Site Cleanup |
| 10 – Contractor Qualifications and Licenses |
| 11 – Prevailing Wage |
| 12 – Buy America Act |
| 13 – Warranty |
| 14 – Maps, Drawings and Specifications |
File details come from the government source that posted it. Updated .