This document outlines deliverables required under a federal contract for rock supply with the Missouri River Project Office of the Department of the Army Corps of Engineers Engineering District Omaha. Key deliverables include preliminary existing test results for conditional approval of the first 5,000 tons of stone due 5 days after contract award. Complete initial sampling and testing results are due 45 days after award. Sampling and testing results for any new stone sources must be submitted 21 days prior to scheduled delivery. Weight bills printed or signed must accompany each truckload delivered. Initial stone delivery onto government-owned barges must occur no later than 10 days after acceptance of preliminary results, with a contractor representative onboard barges and tow boats no later than 3 days after notice.