This document is a Statement of Work (SOW) for the repair, testing, and evaluation of two PATS-70A power board assemblies manufactured by Marvin Test Solutions. The SOW is part of a federal contract opportunity with Solicitation Number FA8222-24-Q-PATS for the repair of A-10 PATS 70 Power Boards.
The key details of the SOW are as follows: The contractor is required to repair the power boards in accordance with the manufacturer's specifications and procedures, provide a certificate of compliance, and deliver the repaired boards within 15 weeks after receipt of order and delivery of government-furnished equipment. The contractor is also responsible for all packaging and shipping costs. The repair work will be overseen by the PATS-70A team and the Procuring Contracting Officer, and the contractor must notify them of any management issues. The contractor will provide a 90-day warranty on the repaired power boards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 3.xlsx | XLSX spreadsheet | |
| Attachment 2.pdf | ||
| FA8222-24-Q-PATS Solicitation-Synopsis.docx | DOCX document | |
| 11906 Justifications Redacted_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
Portable Automated Test Set (PATS) Power Board Repair Prepared By:
Gregory Hernandez 309th Software Engineering Group (309 SWEG) Hill Air Force Base, Utah 84056
27 February 2024
1. SCOPE
The PATS-70A team of the 516th Software Engineering Squadron (516 SWES), a component of 309 SWEG, has been tasked with designing and producing automatic test systems to replace aging legacy test equipment. These test systems are used to perform troubleshooting and maintenance functions on the A-10 and E-3 aircraft on the flight line and backshop. These systems include avionics, weapons, radar, and flight planning. 516 SWES designed the PATS-70A Tester and is responsible for the sustainment of them for the Air Force.
This Statement of Work (SOW) defines contractor tasks and requirements for repair, testing and evaluation, certification, and delivery of two PATS-70A power board assemblies, manufactured by Marvin Test Solutions (MTS). Power board repair will be performed in accordance with (IAW) manufacturer specification and procedures.
2. SPECIAL CONSIDERATIONS
2.1. Program and Engineering Management
All contractor tasks and requirements covered by this document shall be coordinated with the PATS-70A team. Overall responsibility and approval of any changes to the contract or attachments resides with the Procuring Contracting Officer (PCO). If technical changes are required, they shall be communicated to the PCO, and updated documents will be provided in order to modify the contract for inclusion.
2.2. Contract Management
Overall responsibility and approval reside with the PCO. No conversation, recommendation, or direction, whether given directly or implied by Government personnel or representatives, that will affect the scope, schedule, or price of the program covered by this SOW, shall be acted upon by the contractor unless specifically directed in writing by the PCO.
2.3. Other Requested Deliverables
In addition to the repaired power boards, the below Contract Data Requirements List (CDRL) shall also be delivered as part of the contract.
2.3.1. The vendor shall provide a Certificate of Compliance 10 days after completion of testing and evaluation in accordance with (IAW) Data Item Description (DID) DI-MISC-81356A as described in CDRL A001.
3. GOVERNMENT FURNISHED EQUIPEMENT/INFORMATION
3.1. Government Furnished Equipment
The following parts will be furnished to the contractor to repair:
· 1 each, MTS-207 Power Board, Serial Number (SN) – 105
· 1 each, MTS-207 Power Board, Serial Number (SN) – 109
4. CONTRACTOR TASKING AND REQUIREMENTS
The contractor shall accomplish the following tasks and requirements during the repair, test, evaluation, and delivery of the two power boards listed above. Power board repair will be performed IAW manufacturer specification and procedures as follows:
| Line Item |
| Description |
| Manufacturer |
| Part Number |
| Quantity |
| Unit of Measure |
| 0001 |
| Test & Evaluation for MTS-207 Power Board |
| Marvin Test Solutions |
| 4100-100-00 (Test & Evaluation) |
| 2 |
| Each |
| 0002 |
| Minor Incremental Repair Services for Test Equipment |
| Marvin Test Solutions |
| Incremental-Repair-Services-I |
| 4 |
| Each |
Note: Each unit servicing will include these items:
Qty 1, PN 4100-100-00 (Test & Evaluation) Qty 2, PN Incremental-Repair-Services-I
4.1. Contractor Management
The contractor shall plan, direct, coordinate, monitor, evaluate, and control contractor tasks specified in this statement of work. The contractor shall notify the PATS-70A team and the PCO, by email, of management problems requiring Government action.
4.2. Performance Requirements
Performance requirements are IAW manufacturer’s repair, testing and evaluation procedures. A certificate of compliance will be provided (see paragraph 2.3 of the SOW).
4.3. Delivery Schedule
The minimum delivery schedule (advance delivery is acceptable) shall be as follows:
· 15 weeks IAW with manufacturer lead time.
| DELIVERY # |
| CLIN # |
| DESCRIPTION |
| QUANTITY |
| DELIVERY |
| 1 |
| 0001 |
| Test & Evaluation for MTS-207 Power Board |
| 2 |
| 15 weeks after receipt of order (ARO) and delivery of GFE |
| 1 |
| 0002 |
| Minor Incremental Repair Services for Test Equipment |
| 4 |
| 15 weeks after receipt of order (ARO) and delivery of GFE |
| 2 |
| 0003 |
| Certificate of Compliance (CDRL A001) |
| 2 |
| 10 days after completion of testing and evaluation. |
4.3.1 The Contractor is responsible for all shipping costs associated with FOB Destination.
4.4. Packaging and Shipping
4.4.1. The Contractor shall ensure all parts are packaged separately to prevent damage to part features and finishes during shipment.
4.4.2. The Contractor shall ensure all parts are properly identified and shipped per the instructions provided in the contract (i.e., CLINs, Ship to DoDAAC and delivery instructions.)
4.4.3. The Contract will have the following addresses:
DoDAAC: F2DCCF Attn: Michael Hardy Alt: Jason Fogarty 7278 4th St BLDG 100 Bay O Hill AFB, UT 84056
5. WARRANTY AND PRODUCT REPAIR
Vendor shall provide a warranty covering defects in workmanship for a period of 90 days from the time of delivery in accordance with FAR 52.246-18.
6. GENERAL INFORMATION
6.1. General Security Requirements
6.1.1. All requests for information shall be forwarded to the PATS-70A team and the PCO.
6.2. Item Unique Identification and Valuation
6.2.1 The items provided under the terms of this contract shall be subject to DFARS 252.211-7003, Item Unique Identification and Valuation.
6.3. All units produced and ordered through this contract are the property of the U.S. Government.
APPENDIX A
Summary of CDRLs
| Item |
| Title |
| Subtitle |
| Data Item Description |
| SOW Para Reference |
| Delivery |
| A001 |
| Certificate of Compliance |
| N/A |
| DI-MISC-81356A |
| 2.3 |
| 10 Days after Date of Test Completion (DATC) |
File details come from the government source that posted it. Updated .