This is a Performance Work Statement (PWS) for the furnishing and installation of two powered vertical rolling steel doors at Fort Bliss, Texas, dated 28 May 2026.
The contractor shall remove the existing damaged bay doors from a Large Area Maintenance Shelter (LAMS) and install two new electrically powered vertical rolling steel doors measuring 14 feet by 14 feet. Door specifications include minimum 22-gauge galvanized steel construction in grey color, 110v outlet powered motor operation with interior push-button open/close controls, and compatibility with the existing door track system. All materials must be new and defect-free. Services encompass removal and off-site disposal of existing doors, furnishing all new doors, motors, controls, and hardware, installation utilizing the existing track system, electrical hookup to the existing generator-fed power source, installation of push-button controls, operational testing, and adjustment and alignment for proper operation. The contractor must provide a final service report certifying full operational status and compliance with performance standards, along with documentation of all installed components and warranty information.
The work shall be completed within forty-five (45) calendar days after contract award at Fort Bliss, Texas 79916, with all work coordinated through the Government Point of Contact during normal installation hours. Installation standards require doors to operate smoothly without binding, excessive noise, or defects; fully open and close utilizing the installed motor systems; properly respond to interior push-button controls; be securely mounted and aligned with the existing track system; exhibit no visible installation defects or damage; and be fully functional and safe for operation. The contractor shall provide a minimum 12-month warranty covering all furnished doors, motors, controls, parts, and installation workmanship. All contractor personnel must possess official identification to access the installation, and photography is prohibited without authorization. Security requirements include contractor coordination with the Government Point of Contact for access, prominent display of identification and company affiliation, and restriction to work areas only with prohibition on disclosure of installation, facility, schedule, or operational details to unauthorized third parties.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Pictures.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.0 Background
This requirement is to furnish and install two (2) powered vertical rolling steel doors for a fabricated facility located at Fort Bliss, Texas. The existing bay doors are damaged and no longer serviceable. The requirement includes removal and disposal of the existing bay doors and installation of new electrically powered rolling steel doors utilizing the existing door track system of the Large Area Maintenance Shelter (LAMS).
2.0 Scope of Work
The contractor shall furnish all personnel, equipment, tools, materials, supplies, supervision, administration, transportation, and labor necessary to remove, dispose of, furnish, and install two (2) vertical rolling steel doors at the location identified below.
Door Specifications:
• Quantity: Two (2)
• Type: Vertical Rolling Steel Doors
• Dimensions: 14 feet by 14 feet
• Material: Minimum 22-gauge galvanized steel
• Color: Grey
• Operation: 11 0v outlet powered motor operation
• Controls: Interior push-button open/close controls
• Warranty: Minimum 12-month warranty
• Compatibility: Doors shall be compatible with and fit the existing door track system
The contractor shall ensure all work is performed in accordance with manufacturer specifications, commercial standards, and applicable federal, state, and local regulations.
3.0 Description of Services
The contractor shall remove and dispose of the existing damaged doors and furnish and install two (2) new powered vertical rolling steel doors.
Services shall include:
• Removal of existing damaged doors and disposal of removed materials off-site
• Furnishing all new doors, motors, controls, hardware, and associated components
• Installation of new doors utilizing the existing track system
• Electrical hookup and operational connection to the existing generator-fed power source
• Installation of interior push-button controls for opening and closing