This is a Statement of Work (SOW) for construction services at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The project (668-23-101) requires the contractor to construct a new 4,000 gross square foot chiller plant with cooling towers on the roof adjacent to building 44's boiler plant. The scope encompasses site preparation, electrical routing for emergency and normal power from the existing loop, loop modifications, construction of the new building to house three chillers with roof-mounted cooling towers, installation of all electrical equipment, chillers, support systems (pumps, towers, water treatment), and connections to the existing chilled water loop. The contractor must also provide Building Management System (BMS) integration and controls for all new systems. The total project duration is 630 calendar days, with performance taking place at 4815 North Assembly Street, Spokane, Washington 99205.
Additional requirements include engaging a qualified manufacturer's representative to verify installation conformance, oversee system commissioning, and conduct complete test and balance (TAB) documentation for both the building air system and chillers. The contractor must perform operating tests in the presence of the Contracting Officer's Representative (COR), provide comprehensive commissioning documentation, and deliver demonstrations and training to VA personnel covering chiller settings, pump configurations, flow settings, and equipment balancing. Deliverables include as-built drawings and a detailed owner's manual with step-by-step operational instructions for all plant equipment as an integrated system, including electrical gear documentation. The contractor is responsible for all equipment and supplies, with final system acceptance requiring a complete controls and instrumentation validation and demonstration performed by the installer before the COR.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26026R0003_3.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project 668-23-101, Construct Chiller Plant and Cooling Towers Page 1 of 2
STATEMENT OF WORK FOR CONSTRUCTION SERVICES
Construct Chiller Plant and Cooling Towers Project No. 668-23-101
Mann-Grandstaff VA Medical Center Spokane, WA
March 19, 2026
Attachments to this document include the following. Contact the contracting officer if any items are missing.
• Drawings_668-23-101_Construct Chiller Plant and Cooling Tower
• Specs_668-23-101_Construct Chiller Plant and Cooling Tower
1. General Provide construction services to include labor, materials, tools, equipment, transportation, supervision, and other services necessary for “Project 668-23-101, Construct Chiller Plant and Cooling Towers” at the Mann-Grandstaff VA Medical Center, Spokane, Washington. Scope of work is indicated below. Total project duration shall be 630 calendar days.
2. Scope
2.1. In accordance with the provided project drawings and specifications this NRM-IM project will build a new 4000 gross square foot chiller plant with cooling towers located on the roof adjacent to building 44 boiler plant. The work will consist of site preparation, electrical routing of emergency and normal power from the existing loop, modification of the loop to maintain the loop architecture, construction of a new 4000 GSF building to house 3 new chillers with roof support for cooing towers, installation of all electrical equipment necessary for the new building and the associated equipment, installation of chillers and all chiller support systems to include pumps, towers, water treatment, emergency connections, and connection to existing chilled water loop. Provide BMS integration and controls for all new systems in accordance with the design.
2.2. The contractor shall provide a qualified manufacturer’s representative to check complete installation for conformance to manufacturer’s recommendation, to place the system into service, to make all adjustments required for full conformance to design and specified requirements and to perform all demonstrations and testing. This will include a full test and balance (TAB) for the building air system and the chillers with documentation provided of all equipment settings. This will apply to the electrical gear and the chiller systems.
2.3. An operating test shall be run in the presence of the Contracting Officer’s Representative (COR) and other station representatives as required by the COR.
2.4. The contractor shall provide all Commissioning documentation.
2.5. The contractor shall provide demonstrations and training to VA personnel. This will include all chiller settings, loop and tower pump settings, all building air conditioning chilled water flow settings, all building air conditioning steam flow settings, balancing of the 3 chillers and associated cooling towers.
2.6. The contractor shall verify all installation locations for space requirements of proposed equipment.
Project 668-23-101, Construct Chiller Plant and Cooling Towers Page 2 of 2
3. Deliverables:
Inspection documents, testing documents, manual and warranty documents as required by the specifications.
3.1. As-Built Drawings and Owner’s Manual.
3.1.1. The contractor shall deliver the as-built drawings and owner’s manual to the COR no later than at the time of beneficial occupancy.
3.1.1.1. The owner’s manual shall contain detailed step by step instructions for the operation of all plant equipment as a system. Manufacturers’ operation manuals are not sufficient as they do not pertain to how the equipment is operated as a system. The chiller plant automation will be very complex therefore, the manual shall explain all plant settings, their adjustable ranges, and the settings at time of beneficial occupancy.
3.1.1.2. The supporting electrical gear shall be supplied with the owner’s manual of similar detail to the chiller plant owner’s manual.
4. Performance Monitoring The COR will evaluate all work and testing performed for contract compliance. Items must be in a clean state and in a proper working condition and must be in a new condition.
5. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI).
The Contractor will not have access to any Government-Furnished Equipment. All equipment and supplies used under the terms of this contract will be the responsibility of the Contractor.
6. Inspection and Acceptance Criteria.
As part of final system acceptance, a systems demonstration is required. Prior to start of this demonstration, the contractor is to perform a complete validation of all aspects of the Controls and
Instrumentation System. System operation and calibration shall be demonstrated by the installer in the presence of the COR.
7. Place of Performance.
Mann- Grandstaff VA Medical Center, located at 4815 North Assembly Street, Spokane Washington
99205.
8. Period of Performance.
The Contractor has 630 calendar days to perform all described work; this includes all project close out documentation.