This file is an extensive technical specification for a hurricane hardening construction project at the VA Caribbean Healthcare System's Generator Farm in San Juan, Puerto Rico. The project (Number 672-20-105) involves comprehensive electrical system upgrades and infrastructure improvements, with detailed specifications covering multiple technical divisions including HVAC, electrical, plumbing, and architectural components.
The technical specification provides comprehensive design and installation requirements for various systems, including electrical distribution equipment (automatic transfer switches, motor control centers, panelboards), generator support infrastructure, HVAC components, and associated electrical and mechanical systems. The document specifies strict requirements for equipment quality, installation standards, testing protocols, and performance expectations, with a focus on resilience and functionality in hurricane-prone environments. Key technical elements include seismic restraint considerations, comprehensive grounding and bonding specifications, detailed requirements for electrical equipment enclosures, and specific guidelines for installation, testing, and commissioning of all system components.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Provide Hurricane Hardening at Generator Farm San Juan VA Medical Center
San Juan, Puerto Rico June 9, 2025
Specifications Volume II
Bid Documents Submittal Project Number: 672-20-105
2025.06.09 16:04:54-04'00'
Date:
2025.06.09
16:18:27-04'00'
2025.06.09 16:23:50-04'00'
(THIS PAGE LEFT INTENTIONALLY BLANK)
San Juan VA Medical Center 05-01-21
00 01 10 - 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 05-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 03-19 01 45 35.1 Schedule of Special Inspections 01 45 35.2 Statement of Special Inspections 01 57 19 Environmental Controls 01-21 01 74 19 Construction Waste Management 01-21 01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
Not Required
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
Not Required
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18 05 21 00 Steel Joist Framing 11-18 05 31 00 Steel Decking 01-21 05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
00 01 10 - 2
07 21 13 Thermal Insulation 01-21 07 22 00 Roof and Deck Insulation 01-21 07 40 00 Roofing and Siding Panels 01-21 07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21 08 41 13 Aluminum-Framed Entrances and Frames 01-21 08 44 13 Glazed Aluminum Curtain Walls 04-20 08 71 00 Door Hardware 01-21 08 80 00 Glazing 01-21 08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 29 00 Gypsum Board 04-20 09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 11 – EQUIPMENT
Not Required
DIVISION 12 – FURNISHINGS
Not Required
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components 01-14
DIVISION 14 – CONVEYING EQUIPEMENT
Not Required
DIVISION 21 - FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20 22 05 23 General Duty Valves for Plumbing Piping 09-20 22 08 00 Commissioning of Plumbing Systems 11-16
00 01 10 - 3
22 14 00 Facility Storm Drainage 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 02-20 23 05 12 General Motor Requirements for HVAC and Steam Generation
Equipment 02-20
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
02-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 02-20 23 09 23 Direct-Digital Control System for HVAC 09-11 23 10 00 Facility Fuel Systems 04-20 23 21 13 Hydronic Piping 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 37 00 Air Outlets and Inlets 02-20 23 73 00 Indoor Central-Station Air-Handling Units 03-20
DIVISION 25 – INTEGRATED AUTOMATION
Not Required
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 24 16 Panelboards 01-18 26 24 19 Motor Control Centers 01-18 26 27 26 Wiring Devices 01-18 26 29 11 Motor Controllers 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 36 23 Automatic Transfer Switches 01-17 26 51 00 Interior Lighting 01-18 26 56 00 Exterior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
Not Required
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
00 01 10 - 4
31 20 00 Earthwork 08-23 31 63 33 Micropiles
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 16 Asphalt Paving
DIVISION 33 – UTILITIES
On Drawings
DIVISION 34 – TRANSPORTATION
Not Required
DIVISION 48 – Electrical Power Generation
Not Required
Hazardous Material ASSESSMENT
Hazardous Material Assessment Building 29 Generator 05-21
San Juan VA Medical Center 05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
DRAWING NO. TITLE
GENERAL
GI001 COVER SHEET
GI002 LEGENDS, ABBREVIATIONS, AND NOTES
GI003 PHASING PLAN
LIFE SAFETY
LS101 LIFE SAFETY PLAN
CIVIL
VF-101 VA GENERATOR FARM AS-BUILT SURVEY PLAN
C-101 NEW 12” DIAMETER SANITARY SEWER PIPE RELOCATION PLAN
C-102 NEW STORM SEWER PLAN
CU-103 SANITARY SEWER PROFILE AND DETAILS
CU-104 STORM SEWER POLYDRAIN PLAN AND DETAILS
CU-105 STORM SEWER DETAILS PLAN
STRUCTURAL
S001 STRUCTURAL NOTES
S002 STRUCTURAL NOTES
SD101 STRUCTURAL PLATFORM DEMOLITION PLANS
S101 FOUNDATION PLAN
S102 CATWALK FRAMING PLAN
S103 ROOF FRAMING PLAN
S104 STAIR TOWER FRAMING PLANS
S105 LOW PLATFORM FRAMING PLAN
S201 BRACE ELEVATIONS
S202 BRACE ELEVATIONS
S203 BRACE ELEVATIONS
S204 BRACE ELEVATIONS
S205 BRACE ELEVATIONS
S206 FRAMING ELEVATIONS
S207 FRAMING ELEVATIONS
S208 FRAMING ELEVATIONS
00 01 15 - 2
S209 FRAMING ELEVATIONS
S210 FRAMING ELEVATIONS
S301 CONCRETE DETAILS
S302 CONCRETE DETAILS
S303 CONCRETE DETAILS
S304 CONCRETE DETAILS
S501 STEEL DETAILS
S502 STEEL DETAILS
S503 STEEL DETAILS
S504 STEEL DETAILS
S505 STEEL DETAILS
S506 STEEL DETAILS
ARCHITECTURAL
AD101 UPPER AND LOWER DEMOLITION FLOOR PLAN
AD121 ROOF DEMO PLAN
AE101 UPPER AND LOWER LEVEL FLOOR PLAN
AE102 PLATFORM PLAN
AE111-A FIRST FLOOR REFLECTED CEILING PLAN – AT CANOPY LEVEL
AE111-B FIRST FLOOR REFLECTED CEILING PLAN – AT PLATFORM LEVEL
AE111-C FIRST FLOOR REFLECTED CEILING PLAN – ABOVE PLATFORM
AE121 UPPER ROOF PLAN
AE201 EXTERIOR ELEVATIONS
AE301 BUILDING SECTION
AE302 BUILDING SECTIONS
AE303 BUILDING SECTIONS
AE351 WALL SECTIONS
AE352 WALL SECTIONS
AE353 WALL SECTIONS
AE354 WALL SECTIONS
AE355 WALL SECTIONS
AE501 FRAMING DETAILS
AE502 ENLARGED STAIR PLAN AND DETAILS
AE511 PLAN AND SECTION DETAILS
AE512 PLAN AND SECTION DETAILS
AE601 WINDOW, DOOR AND FRAME TYPES, SCHEDULES, AND DETAILS
AE701 SIGNAGE PLAN
AE702 SIGNAGE TYPES
00 01 15 - 3
AE703 SIGNAGE TYPES
AE704 SIGNAGE TYPES
FIRE PROTECTION
F-001 FIRE PROTECTION LEGEND
FA101 FIRST FLOOR FIRE ALARM PLAN - AT CANOPY
FA102 PLATFORM FIRE ALARM PLAN – AT PLATFORM
FX101 FIRST FLOOR SPRINKLER PLAN – BELOW CANOPY
FX102 FIRST FLOOR SPRIKLER PLAN – BELOW PLATFORM
FX103 FIRST FLOOR SPRIKLER PLAN – BELOW ROOF
PLUMBING
P-001 PLUMBING LEGEND, GENERAL NOTES, AND SCHEDULES
PD101 DEMOLITION FLOOR PLAN
PP101 NEW WORK FLOOR PLAN
P-501 DETAILS
P-701 RISER
MECHANICAL
M-001 MECHANICAL LEGEND AND SCHEDULES
MD101 FIRST FLOOR PLAN - DEMOLITION
MH101 FIRST FLOOR PLAN
MH102 ROOF PLAN
MP101 FIRST FLOOR PLAN
M-301 SECTION
M-501 DETAILS
M-801 CONTROLS
ELECTRICAL
E-001 ELECTRICAL LEGEND
EL101 FIRST FLOOR – LIGHTING
EL102 PLATFORM LIGHTING PLAN
EP101 FIRST FLOOR – POWER
EP102 PLATFORM POWER PLAN
EP103 ROOF PLAN – POWER
EP104 PARTIAL BUILDING PLAN - POWER
EP501 ELECTRICAL DETAILS
EP601 POWER RISER AND SCHEDULES
00 01 15 - 4
- - - E N D - - -
Provide Hurricane Hardening at Generator Farm 01-01-23
22 05 11 - 1
SECTION 22 05 11
COMMON WORK RESULTS FOR PLUMBING
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section will apply to all sections of Division
22.
B. Definitions:
1. Exposed: Piping and equipment exposed to view in finished rooms.
2. Exterior: Piping and equipment exposed to weather be it temperature, humidity, precipitation, wind or solar radiation.
C. Abbreviations/Acronyms:
1. ABS: Acrylonitrile Butadiene Styrene
2. AC: Alternating Current
3. ACR: Air Conditioning and Refrigeration
4. A/E: Architect/Engineer
5. AFF: Above Finish Floor
6. AFG: Above Finish Grade
7. AI: Analog Input
8. AISI: American Iron and Steel Institute
9. AO: Analog Output
10. ASHRAE: American Society of Heating Refrigeration, Air Conditioning
Engineers
11. ASJ: All Service Jacket
12. ASME: American Society of Mechanical Engineers
13. ASPE: American Society of Plumbing Engineers
14. AWG: American Wire Gauge
15. BACnet: Building Automation and Control Network
16. BAg: Silver-Copper-Zinc Brazing Alloy
17. BAS: Building Automation System
18. BCuP: Silver-Copper-Phosphorus Brazing Alloy
19. bhp: Brake Horsepower
20. Btu: British Thermal Unit
21. Btu/h: British Thermal Unit per Hour
22. BSG: Borosilicate Glass Pipe
23. C: Celsius
24. CA: Compressed Air
25. CD: Compact Disk
22 05 11 - 2
26. CDA: Copper Development Association
27. CGA: Compressed Gas Association
28. CFM: Cubic Feet per Minute
29. CI: Cast Iron
30. CLR: Color
31. CO: Contracting Officer
32. COR: Contracting Officer’s Representative
33. CPVC: Chlorinated Polyvinyl Chloride
34. CR: Chloroprene
35. CRS: Corrosion Resistant Steel
36. CWP: Cold Working Pressure
37. CxA: Commissioning Agent
38. dB: Decibels
39. db(A): Decibels (A weighted)
40. DCW: Domestic Cold Water
41. DDC: Direct Digital Control
42. DFU: Drainage Fixture Units
43. DHW: Domestic Hot Water
44. DHWR: Domestic Hot Water Return
45. DHWS: Domestic How Water Supply
46. DI: Digital Input
47. DI: Deionized Water
48. DISS: Diameter Index Safety System
49. DN: Diameter Nominal
50. DO: Digital Output
51. DOE: Department of Energy
52. DVD: Digital Video Disc
53. DWG: Drawing
54. DWH: Domestic Water Heater
55. DWS: Domestic Water Supply
56. DWV: Drainage, Waste and Vent
57. ECC: Engineering Control Center
58. EL: Elevation
59. EMCS: Energy Monitoring and Control System
60. EPA: Environmental Protection Agency
61. EPACT: Energy Policy Act
62. EPDM: Ethylene Propylene Diene Monomer
63. EPT: Ethylene Propylene Terpolymer
22 05 11 - 3
64. ETO: Ethylene Oxide
65. F: Fahrenheit
66. FAR: Federal Acquisition Regulations
67. FD: Floor Drain
68. FDC: Fire Department (Hose) Connection
69. FED: Federal
70. FG: Fiberglass
71. FNPT: Female National Pipe Thread
72. FOR: Fuel Oil Return
73. FOS: Fuel Oil Supply
74. FOV: Fuel Oil Vent
75. FPM: Fluoroelastomer Polymer
76. FSK: Foil-Scrim-Kraft Facing
77. FSS: VA Construction & Facilities Management, Facility Standards
Service
78. FU: Fixture Units
79. GAL: Gallon
80. GCO: Grade Cleanouts
81. GPD: Gallons per Day
82. GPH: Gallons per Hour
83. GPM: Gallons per Minute
84. HDPE: High Density Polyethylene
85. HEFP: Healthcare Environment and Facilities Program (replacement for
OCAMES)
86. HEX: Heat Exchanger
87. Hg: Mercury
88. HOA: Hands-Off-Automatic
89. HP: Horsepower
90. HVE: High Volume Evacuation
91. Hz: Hertz
92. ID: Inside Diameter
93. IE: Invert Elevation
94. INV: Invert
95. IPC: International Plumbing Code
96. IPS: Iron Pipe Size
97. IW: Indirect Waste
98. IWH: Instantaneous Water Heater
99. Kg: Kilogram
22 05 11 - 4
100. kPa: Kilopascal
101. KW: Kilowatt
102. KWH: Kilowatt Hour
103. lb: Pound
104. lbs/hr: Pounds per Hour
105. LNG: Liquid Natural Gas
106. L/min: Liters per Minute
107. LOX: Liquid Oxygen
108. L/s: Liters per Second
109. m: Meter
110. MA: Medical Air
111. MAWP: Maximum Allowable Working Pressure
112. MAX: Maximum
113. MBH: 1000 Btu per Hour
114. MED: Medical
115. MER: Mechanical Equipment Room
116. MFG: Manufacturer
117. mg: Milligram
118. mg/L: Milligrams per Liter
119. ml: Milliliter
120. mm: Millimeter
121. MIN: Minimum
122. MV: Medical Vacuum
123. N2: Nitrogen
124. N20: Nitrogen Oxide
125. NC: Normally Closed
126. NF: Oil Free Dry (Nitrogen)
127. NG: Natural Gas
128. NIC: Not in Contract
129. NO: Normally Open
130. NOM: Nominal
131. NPTF: National Pipe Thread Female
132. NPS: Nominal Pipe Size
133. NPT: Nominal Pipe Thread
134. NTS: Not to Scale
135. O2: Oxygen
136. OC: On Center
137. OD: Outside Diameter
22 05 11 - 5
138. OSD: Open Sight Drain
139. OS&Y: Outside Stem and Yoke
140. PA: Pascal
141. PBPU: Prefabricated Bedside Patient Units
142. PD: Pressure Drop or Difference
143. PDI: Plumbing and Drainage Institute
144. PH: Power of Hydrogen
145. PID: Proportional-Integral-Differential
146. PLC: Programmable Logic Controllers
147. PP: Polypropylene
148. ppb: Parts per Billion
149. ppm: Parts per Million
150. PSI: Pounds per Square Inch
151. PSIA: Pounds per Square Inch Atmosphere
152. PSIG: Pounds per Square Inch Gauge
153. PTFE: Polytetrafluoroethylene
154. PVC: Polyvinyl Chloride
155. PVDF: Polyvinylidene Fluoride
156. RAD: Radians
157. RO: Reverse Osmosis
158. RPM: Revolutions Per Minute
159. RTD: Resistance Temperature Detectors
160. RTRP: Reinforced Thermosetting Resin Pipe
161. SAN: Sanitary Sewer
162. SCFM: Standard Cubic Feet per Minute
163. SDI: Silt Density Index
164. SMACNA: Sheet Metal and Air Conditioning Contractors National
Association
165. SPEC: Specification
166. SPS: Sterile Processing Services
167. SQFT/SF: Square Feet
168. SS: Stainless Steel
169. STD: Standard
170. SUS: Saybolt Universal Second
171. SWP: Steam Working Pressure
172. TD: Temperature Difference
173. TDH: Total Dynamic Head
174. TEFC: Totally Enclosed Fan-Cooled
22 05 11 - 6
175. TEMP: Temperature
176. TFE: Tetrafluoroethylene
177. THERM: 100,000 Btu
178. THHN: Thermoplastic High-Heat Resistant Nylon Coated Wire
179. THWN: Thermoplastic Heat & Water Resistant Nylon Coated Wire
180. TIL: Technical Information Library http//www.cfm.va.gov/til/indes.asp
181. T/P: Temperature and Pressure
182. TYP: Typical
183. USDA: U.S. Department of Agriculture
184. V: Vent
185. V: Volt
186. VA: Veterans Administration
187. VA CFM: VA Construction & Facilities Management
188. VA CFM CSS: VA Construction & Facilities Management, Consulting Support Service
189. VAC: Vacuum
190. VAC: Voltage in Alternating Current
191. VAMC: Veterans Administration Medical Center
192. VHA OCAMES: This has been replaced by HEFP.
193. VSD: Variable Speed Drive
194. VTR: Vent through Roof
195. W: Waste
196. WAGD: Waste Anesthesia Gas Disposal
197. WC: Water Closet
198. WG: Water Gauge
199. WOG: Water, Oil, Gas
200. WPD: Water Pressure Drop
201. WSFU: Water Supply Fixture Units
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
C. Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT.
D. Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.
E. Section 03 30 00, CAST-IN-PLACE CONCRETE: Concrete and Grout.
F. Section 05 31 00, STEEL DECKING: Building Components for Attachment of Hangers.
22 05 11 - 7
G. Section 05 50 00, METAL FABRICATIONS.
H. Section 07 84 00, FIRESTOPPING.
I. Section 07 92 00, JOINT SEALANTS.
J. Section 09 91 00, PAINTING.
K. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS.
L. Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.
M. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
N. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
O. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.
1.3 APPLICABLE PUBLICATIONS
A. The publications listed below will form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only. Where conflicts occur these specifications and the VHA standard will govern.
B. American Society of Mechanical Engineers (ASME):
B31.1-2013..............Power Piping
ASME Boiler and Pressure Vessel Code -
BPVC Section IX-2019.... Welding, Brazing, and Fusing Qualifications
C. American Society for Testing and Materials (ASTM):
A36/A36M-2019...........Standard Specification for Carbon Structural
Steel
A575-96(2013)e1.........Standard Specification for Steel Bars, Carbon, Merchant Quality, M-Grades
E84-2013a...............Standard Test Method for Surface Burning
Characteristics of Building Materials
E119-2012a..............Standard Test Methods for Fire Tests of
Building Construction and Materials
D. International Code Council, (ICC):
IBC-2018................International Building Code
IPC-2018................International Plumbing Code
E. Manufacturers Standardization Society (MSS) of the Valve and Fittings
Industry, Inc:
SP-58-2018..............Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application and
Installation
F. Military Specifications (MIL):
22 05 11 - 8
P-21035B................Paint High Zinc Dust Content, Galvanizing
Repair (Metric)
G. National Electrical Manufacturers Association (NEMA):
MG 1-2016...............Motors and Generators
H. National Fire Protection Association (NFPA):
51B-2019................Standard for Fire Prevention During Welding, Cutting and Other Hot Work
54-2018.................National Fuel Gas Code
70-2020.................National Electrical Code (NEC)
99-2018.................Healthcare Facilities Code
I. NSF International (NSF):
5-2019..................Water Heaters, Hot Water Supply Boilers, and
Heat Recovery Equipment
14-2019.................Plastic Piping System Components and Related
Materials
61-2019.................Drinking Water System Components – Health
Effects
372-2016................Drinking Water System Components – Lead Content
J. Department of Veterans Affairs (VA):
PG-18-102014(R18).......Plumbing Design Manual
PG-18-13-2017(R18)......Barrier Free Design Guide
1.4 SUBMITTALS
A. Submittals, including number of required copies, will be submitted in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and
SAMPLES.
B. Information and material submitted under this section will be marked
"SUBMITTED UNDER SECTION 22 05 11, COMMON WORK RESULTS FOR PLUMBING",
with applicable paragraph identification.
C. If the project is phased, contractors will submit complete phasing plan/schedule with manpower levels prior to commencing work. The phasing plan will be detailed enough to provide milestones in the process that can be verified.
D. Contractor will make all necessary field measurements and investigations to assure that the equipment and assemblies will meet contract requirements, and all equipment that requires regular maintenance, calibration, etc are accessable from the floor or permanent work platform. It is the Contractor’s responsibility to ensure all submittals meet the VA specifications and requirements and
22 05 11 - 9 it is assumed by the VA that all submittals do meet the VA specifications unless the Contractor has requested a variance in writing and approved by COR prior to the submittal. If at any time during the project it is found that any item does not meet the VA specifications and there was no variance approval the Contractor will correct at no additional cost or time to the Government even if a submittal was approved.
E. If equipment is submitted which differs in arrangement from that shown, provide documentation proving equivalent performance, design standards and drawings that show the rearrangement of all associated systems.
Additionally, any impacts on ancillary equipment or services such as foundations, piping, and electrical will be the Contractor’s responsibility to design, supply, and install at no additional cost or time to the Government. VA approval will be given only if all features of the equipment and associated systems, including accessibility, are equivalent to that required by the contract.
F. Prior to submitting shop drawings for approval, Contractor will certify in writing that manufacturers of all major items of equipment have each reviewed drawings and specifications, and have jointly coordinated and properly integrated their equipment and controls to provide a complete and efficient installation.
G. Submittals and shop drawings for interdependent items, containing applicable descriptive information, will be furnished together and complete in a group. Coordinate and properly integrate materials and equipment in each group to provide a completely compatible and efficient installation. Final review and approvals will be made only by groups.
H. Manufacturer's Literature and Data including: Manufacturer’s literature will be submitted under the pertinent section rather than under this section.
1. Electric motor data and variable speed drive data will be submitted with the driven equipment.
2. Equipment and materials identification.
3. Firestopping materials.
4. Hangers, inserts, supports and bracing. Provide load calculations for variable spring and constant support hangers.
5. Wall, floor, and ceiling plates.
I. Coordination/Shop Drawings:
22 05 11 - 10
1. Submit complete consolidated and coordinated shop drawings for all new systems, and for existing systems that are in the same areas.
2. The coordination/shop drawings will include plan views, elevations and sections of all systems and will be on a scale of not less than
1:32 (3/8-inch equal to 1 foot). Clearly identify and dimension the proposed locations of the principal items of equipment. The drawings will clearly show locations and adequate clearance for all equipment, piping, valves, control panels and other items. Show the access means for all items requiring access for operations and maintenance. Provide detailed coordination/shop drawings of all piping and duct systems. The drawings should include all lockout/tagout points for all energy/hazard sources for each piece of equipment. Coordinate lockout/tagout procedures and practices with local VA requirements.
3. Do not install equipment foundations, equipment or piping until coordination/shop drawings have been approved.
4. In addition, for plumbing systems, provide details of the following:
a. Mechanical equipment rooms.
b. Hangers, inserts, supports, and bracing.
c. Pipe sleeves.
J. Plumbing Maintenance Data and Operating Instructions:
1. Maintenance and operating manuals in accordance with Section 01 00
00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment.
2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide:
a. Include complete list indicating all components of the systems.
b. Include complete diagrams of the internal wiring for each item of equipment.
c. Diagrams will have their terminals identified to facilitate installation, operation and maintenance.
3. Provide a listing of recommended replacement parts for keeping in stock supply, including sources of supply, for equipment. Include in the listing belts for equipment: Belt manufacturer, model number, size and style, and distinguished whether of multiple belt sets.
K. Provide copies of approved plumbing equipment submittals to the TAB and
Commissioning Subcontractor.
22 05 11 - 11
L. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22
08 00 COMMISSIONING OF PLUMBING SYSTEMS.
M. Submit training plans, trainer qualifications and instructor qualifications in accordance with the requirements of Section 22 08 00
COMMISSIONING OF PLUMBING SYSTEMS.
1.5 QUALITY ASSURANCE
A. Mechanical, electrical, and associated systems will be safe, reliable, efficient, durable, easily and safely operable and maintainable, easily and safely accessible, and in compliance with applicable codes as specified. The systems will be comprised of high quality institutional-class and industrial-class products of manufacturers that are experienced specialists in the required product lines. All construction firms and personnel will be experienced and qualified specialists in industrial and institutional plumbing.
B. Products Criteria:
1. Standard Products: Material and equipment will be the standard products of a manufacturer regularly engaged in the manufacture, supply and servicing of the specified products for at least 5 years.
However, digital electronics devices, software and systems such as controls, instruments, computer work station, will be the current generation of technology and basic design that has a proven satisfactory service record of at least 5 years.
2. Equipment Service: There will be permanent service organizations, authorized and trained by manufacturers of the equipment supplied, located within 160 km (100 miles) of the project. These organizations will come to the site and provide acceptable service to restore operations within 4 hours of receipt of notification by phone, e-mail or fax in event of an emergency, such as the shut-down of equipment; or within 24 hours in a non-emergency. Names, mail and e-mail addresses and phone numbers of service organizations providing service under these conditions for (as applicable to the project): fuel oil systems for generators, pumps, compressors, water heaters, critical instrumentation, computer workstation and programming will be submitted for project record and inserted into the operations and maintenance manual.
22 05 11 - 12
3. All items furnished will be free from defects that would adversely affect the performance, maintainability and appearance of individual components and overall assembly.
4. The products and execution of work specified in Division 22 will conform to the referenced codes and standards as required by the specifications. Local codes and amendments enforced by the local code official will be enforced, if required by local authorities such as the natural gas supplier. If the local codes are more stringent, then the local code will apply. Any conflicts will be brought to the attention of the Contracting Officers Representative
(COR).
5. Multiple Units: When two or more units of materials or equipment of the same type or class are required, these units will be of the same manufacturer and model number, or if different models are required they will be of the same manufacturer and identical to the greatest extent possible (i.e., same model series).
6. Assembled Units: Performance and warranty of all components that make up an assembled unit will be the responsibility of the manufacturer of the completed assembly.
7. Nameplates: Nameplate bearing manufacturer's name or identifiable trademark will be securely affixed in a conspicuous place on equipment, or name or trademark cast integrally with equipment, stamped or otherwise permanently marked on each item of equipment.
8. Asbestos products or equipment or materials containing asbestos is prohibited.
9. Bio-Based Materials: For products designated by the USDA’s bio-based
Bio-Preferred Program, provide products that meet or exceed USDA recommendations for bio-based content, so long as products meet all performance requirements in this specifications section. For more information regarding the product categories covered by the
Bio-Preferred Program, visit http://www.biopreferred.gov.
C. Welding: Before any welding is performed, Contractor will submit a certificate certifying that welders comply with the following requirements:
1. Qualify welding processes and operators for piping according to ASME BPVC, Section IX, "Welding and Brazing Qualifications". Provide proof of current certification to CO.
http://www.biopreferred.gov/
22 05 11 - 13
2. Comply with provisions of ASME B31 series "Code for Pressure
Piping".
3. Certify that each welder and welding operator has passed American Welding Society (AWS) qualification tests for the welding processes involved, and that certification is current.
4. All welds will be stamped according to the provisions of the AWS or
ASME as required herein and by the association code.
D. Manufacturer's Recommendations: Where installation procedures or any part thereof are required to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations will be furnished to the COR prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.
E. Execution (Installation, Construction) Quality:
1. All items will be applied and installed in accordance with manufacturer's written instructions. Conflicts between the manufacturer's instructions and the contract documents will be referred to the COR for resolution. Printed copies or electronic files of manufacturer’s installation instructions will be provided to the COR at least 10 working days prior to commencing installation of any item.
2. All items that require access, such as for operating, cleaning, servicing, maintenance, and calibration, will be easily and safely accessible by persons standing at floor level, or standing on permanent platforms, without the use of portable ladders. Examples of these items include but are not limited to: all types of valves, filters and strainers, transmitters, and control devices. Prior to commencing installation work, refer conflicts between this requirement and contract documents to COR for resolution. Failure of the Contractor to resolve or call attention to any discrepancies or deficiencies to the COR will result in the Contractor correcting at no additional cost or time to the Government.
3. Complete layout drawings will be required by Paragraph, SUBMITTALS.
Construction work will not start on any system until the layout drawings have been approved by VA.
22 05 11 - 14
4. Installer Qualifications: Installer will be licensed and will provide evidence of the successful completion of at least five projects of equal or greater size and complexity. Provide tradesmen skilled in the appropriate trade.
5. Workmanship/craftsmanship will be of the highest quality and standards. The VA reserves the right to reject any work based on poor quality of workmanship this work will be removed and done again at no additional cost or time to the Government.
F. Upon request by Government, provide lists of previous installations for selected items of equipment. Include contact persons who will serve as references, with current telephone numbers and e-mail addresses.
G. Guaranty: Warranty of Construction, FAR clause 52.246-21.
H. Plumbing Systems: IPC, International Plumbing Code. Unless otherwise required herein, perform plumbing work in accordance with the latest version of the IPC. For IPC codes referenced in the contract documents, advisory provisions will be considered mandatory, the word “should” will be interpreted as “will”. Reference to the “code official” or
“owner” will be interpreted to mean the COR.
I. Cleanliness of Piping and Equipment Systems:
1. Care will be exercised in the storage and handling of equipment and piping material to be incorporated in the work. Debris arising from cutting, threading and welding of piping will be removed.
2. Piping systems will be flushed, blown or pigged as necessary to deliver clean systems.
3. The interior of all tanks will be cleaned prior to delivery and beneficial use by the Government. All piping will be tested in accordance with the specifications and the International Plumbing
Code (IPC). All filters, strainers, fixture faucets will be flushed of debris prior to final acceptance.
4. Contractor will be fully responsible for all costs, damage, and delay arising from failure to provide clean systems.
1.6 DELIVERY, STORAGE AND HANDLING
A. Protection of Equipment:
1. Equipment and material placed on the job site will remain in the custody of the Contractor until phased acceptance, whether or not the Government has reimbursed the Contractor for the equipment and material. The Contractor is solely responsible for the protection of such equipment and material against any damage or theft.
22 05 11 - 15
2. Damaged equipment will be replaced with an identical unit as determined and directed by the COR. Such replacement will be at no additional cost or additional time to the Government.
3. Interiors of new equipment and piping systems will be protected against entry of foreign matter. Both inside and outside will be cleaned before painting or placing equipment in operation.
4. Existing equipment and piping being worked on by the Contractor will be under the custody and responsibility of the Contractor and will be protected as required for new work.
5. Protect plastic piping and tanks from ultraviolet light (sunlight) while in pre-construction. Plastic piping and tanks will not be installed exposed to sunlight without metal jacketing to block ultraviolet rays.
1.7 AS-BUILT DOCUMENTATION
A. Submit manufacturer’s literature and data updated to include submittal review comments and any equipment substitutions.
B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions will be in electronic version on CD or DVD inserted into a three─ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation will be included in the operation and maintenance manual. The operations and maintenance manual will include troubleshooting techniques and procedures for emergency situations.
Notes on all special systems or devices will be included. A List of recommended spare parts (manufacturer, model number, and quantity) will be furnished. Information explaining any special knowledge or tools the owner will be required to employ will be inserted into the As-Built documentation.
C. The installing Contractor will maintain as-built drawings of each completed phase for verification; and, will provide the complete set at the time of final systems certification testing. Should the installing
Contractor engage the testing company to provide as-built or any portion thereof, it will not be deemed a conflict of interest or breach of the ‘third party testing company’ requirement. Provide record drawings as follows for each type:
22 05 11 - 16
1. Red-lined, hand-marked drawings are to be provided, with one paper copy and a scanned PDF version of the hand-marked drawings provided on CD or DVD.
2. As-built drawings are to be provided, with a copy of them in three-dimensional Building Information Modeling (BIM) software version
Revit 2023 provided on CD or DVD.
D. The as-built drawings will indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc.
Coordinate lockout/tagout procedures and practices with local VA requirements.
E. Certification documentation will be provided to COR 21 working days prior to submitting the request for final inspection. The documentation will include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results will contain written sequence of test procedure with written test results annotated at each step along with the expected outcome or setpoint. The results will include all readings, including but not limited to data on device
(make, model and performance characteristics_), normal pressures, switch ranges, trip points, amp readings, and calibration data to include equipment serial numbers or individual identifications, etc.
1.8 JOB CONDITIONS – WORK IN EXISTING BUILDING
A. Building Operation: Government employees will be continuously operating and managing all facilities, including temporary facilities that serve the VAMC.
B. Maintenance of Service: Schedule all work to permit continuous service as required by the VAMC.
C. Steam and Condensate Service Interruptions: Limited steam and condensate service interruptions, as required for interconnections of new and existing systems, will be permitted by the COR during periods when the demands are not critical to the operation of the VAMC. These non-critical periods are limited to between 8 pm and 5 am in the appropriate off-season (if applicable). Provide at least 10 working days advance notice to the COR. The request will include a detailed plan on the proposed shutdown and the intended work to be done along with manpower levels. All equipment and materials must be onsite and
22 05 11 - 17 verified with plan 14 calendar days prior to the shutdown or it will need to be rescheduled.
D. Phasing of Work: Comply with all requirements shown on contract documents. Contractor will submit a complete detailed phasing plan/schedule with manpower levels prior to commencing work. The phasing plan will be detailed enough to provide milestones in the process that can be verified.
E. Building Working Environment: Maintain the architectural and structural integrity of the building and the working environment at all times.
Maintain the interior of building at 18 degrees C (65 degrees F) minimum. Limit the opening of doors, windows, or other access openings to brief periods as necessary for rigging purposes. Storm water or ground water leakage is prohibited. Provide daily clean-up of construction and demolition debris on all floor surfaces and on all equipment being operated by VA. Maintain all egress routes and safety systems/devices.
F. Acceptance of Work for Government Operation: As new equipment, systems and facilities are made available for operation and these items are deemed of beneficial use to the Government, inspections and tests will be performed. Based on the inspections, a list of contract deficiencies will be issued to the Contractor. After correction of deficiencies as necessary for beneficial use, the Contracting Officer will process necessary acceptance and the equipment will then be under the control and operation of Government personnel.
G. Temporary Facilities: Refer to Paragraph, TEMPORARY PIPING AND EQUIPMENT in this section.
PART 2 - PRODUCTS
2.1 MATERIALS FOR VARIOUS SERVICES
A. Non-pressure PVC pipe will contain a minimum of 25 percent recycled content. Steel pipe will contain a minimum of 25 percent recycled content.
B. Plastic pipe, fittings and solvent cement will meet NSF 14 and will bear the NSF seal “NSF-PW”. Polypropylene pipe and fittings will comply with NSF 14 and NSF 61. Solder or flux containing lead will not be used with copper pipe.
C. Material or equipment containing a weighted average of greater than
0.25 percent lead will not be used in any potable water system intended
22 05 11 - 18 for human consumption and will be certified in accordance with NSF 61 or NSF 372.
D. In-line devices such as water meters, building valves, check valves, stops, valves, fittings, tanks, and backflow preventers will comply with NSF 61 and NSF 372.
E. End point devices such as drinking fountains, lavatory faucets, kitchen and bar faucets, ice makers supply stops, and end-point control valves used to dispense drinking water must meet requirements of NSF 61 and
NSF 372.
2.2 FACTORY-ASSEMBLED PRODUCTS
A. Standardization of components will be maximized to reduce spare part requirements.
B. Manufacturers of equipment assemblies that include components made by others will assume complete responsibility for final assembled unit.
1. All components of an assembled unit need not be products of same manufacturer.
2. Constituent parts that are alike will be products of a single manufacturer.
3. Components will be compatible with each other and with the total assembly for intended service.
4. Contractor will guarantee performance of assemblies of components and will repair or replace elements of the assemblies as required to deliver specified performance of the complete assembly at no additional cost or time to the Government.
C. Components of equipment will bear manufacturer's name and trademark, model number, serial number and performance data on a name plate securely affixed in a conspicuous place, or cast integral with, stamped or otherwise permanently marked upon the components of the equipment.
D. Major items of equipment, which serve the same function, will be the same make and model.
2.3 COMPATIBILITY OF RELATED EQUIPMENT
A. Equipment and materials installed will be compatible in all respects with other items being furnished and with existing items so that the result will be a complete and fully operational system that conforms to contract requirements.
2.4 SAFETY GUARDS
A. Pump shafts and couplings will be fully guarded by a sheet steel guard, covering coupling and shaft but not bearings. Material will be minimum
22 05 11 - 19
16-gauge sheet steel; ends will be braked and drilled and attached to pump base with minimum of four 8 mm (1/4 inch) bolts. Reinforce guard as necessary to prevent side play forcing guard onto couplings.
B. B. All Equipment will have moving parts protected from personal injury.
2.5 LIFTING ATTACHMENTS
A. Equipment will be provided with suitable lifting attachments to enable equipment to be lifted in its normal position. Lifting attachments will withstand any handling conditions that might be encountered, without bending or distortion of shape, such as rapid lowering and braking of load.
2.6 ELECTRIC MOTORS, MOTOR CONTROL, CONTROL WIRING
A. All material and equipment furnished and installation methods used will conform to the requirements of Section 26 29 11, MOTOR CONTROLLERS;
and, Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES. All electrical wiring, conduit, and devices necessary for the proper connection, protection and operation of the systems will be provided. Premium efficient motors will be provided. Unless otherwise specified for a particular application, electric motors will have the following requirements.
B. Special Requirements:
1. Where motor power requirements of equipment furnished deviate from power shown on plans, provide electrical service designed under the requirements of NFPA 70 at no additional cost or time to the
Government.
2. Assemblies of motors, starters, and controls and interlocks on factory assembled and wired devices will be in accordance with the requirements of this specification.
3. Wire and cable materials specified in the electrical division of the specifications will be modified as follows:
a. Wiring material located where temperatures can exceed 71° C (160°
F) will be stranded copper with Teflon FEP insulation with jacket. This includes wiring on the boilers and water heaters.
b. Other wiring at boilers and water heaters, and to control panels, will be NFPA 70 designation THWN.
c. Shielded conductors or wiring in separate conduits for all instrumentation and control systems will be provided where recommended by manufacturer of equipment.
22 05 11 - 20
4. Motor sizes will be selected so that the motors do not operate into the service factor at maximum required loads on the driven equipment. Motors on pumps will be sized for non-overloading at all points on the pump performance curves.
5. Motors utilized with variable frequency drives will be rated “inverter-ready” per NEMA Standard, MG1.
C. Motor Efficiency and Power Factor: All motors, when specified as “high efficiency or Premium Efficiency” by the project specifications on driven equipment, will conform to efficiency and power factor requirements, with no consideration of annual service hours. Motor manufacturers generally define these efficiency requirements as “NEMA premium efficient” and the requirements generally exceed those of the
Energy Policy Act (EPACT), revised 2005. Motors not specified as “high efficiency or premium efficient” will comply with EPACT.
D. Single-phase Motors: Capacitor-start type for hard starting applications. Motors for centrifugal pumps may be split phase or permanent split capacitor (PSC).
E. Poly-phase Motors: NEMA Design B, Squirrel cage, induction type. Each two-speed motor will have two separate windings. A time delay (20 seconds minimum) relay will be provided for switching from high to low speed.
F. Rating: Rating will be continuous duty at 100 percent capacity in an ambient temperature of 40° C (104° F); minimum horsepower as shown on drawings; maximum horsepower in normal operation will not exceed nameplate rating without service factor.
G. Insulation Resistance: Not less than one-half meg-ohm between stator conductors and frame will be measured at the time of final inspection.
2.7 VARIABLE SPEED MOTOR CONTROLLERS
A. Refer to Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS and Section 26 29 11, MOTOR CONTROLLERS for specifications.
B. The combination of controller and motor will be provided by the respective pump manufacturer and will be rated for 100 percent output performance. Multiple units of the same class of equipment, i.e. pumps, will be product of a single manufacturer.
C. Motors will be premium efficient type, “invertor duty”, and be approved by the motor controller manufacturer. The controller-motor combination will be guaranteed to provide full motor nameplate horsepower in
22 05 11 - 21 variable frequency operation. Both driving and driven motor sheaves will be fixed pitch.
D. Controller will not add any current or voltage transients to the input AC power distribution system, DDC controls, sensitive medical equipment, etc., nor will be affected from other devices on the AC power system.
2.8 EQUIPMENT AND MATERIALS IDENTIFICATION
A. Use symbols, nomenclature and equipment numbers specified, shown in the drawings, or shown in the maintenance manuals. Coordinate equipment and valve identification with local VAMC shops. In addition, provide bar code identification nameplate for all equipment which will allow the equipment identification code to be scanned into the system for maintenance and inventory tracking. Identification for piping is specified in Section 09 91 00, PAINTING.
B. Interior (Indoor) Equipment: Engraved nameplates, with letters not less than 7 mm (3/16 inch) high of brass with black-filled letters, or rigid black plastic with white letters specified in Section 09 91 00, PAINTING will be permanently fastened to the equipment. Unit components such as water heaters, tanks, coils, filters, etc. will be identified.
C. Exterior (Outdoor) Equipment: Brass nameplates, with engraved black filled letters, not less than 7 mm (3/16 inch) high riveted or bolted to the equipment.
D. Control Items: All temperature, pressure, and controllers will be labeled and the component’s function identified. Identify and label each item as they appear on the control diagrams.
E. Valve Tags and Lists:
1. Plumbing: All valves will be provided with valve tags and listed on a valve list (Fixture stops not included).
2. Valve tags: Engraved black filled numbers and letters not less than
15 mm (1/2 inch) high for number designation, and not less than 8 mm
(1/4 inch) for service designation on 19-gauge, 40 mm (1-1/2 inches) round brass disc, attached with brass "S" hook or brass chain.
3. Valve lists: Valve lists will be created using a word processing program and printed on plastic coated cards. The plastic-coated valve list card(s) sized 215 mm (8-1/2 inches) by 275 mm (11 inches) will show valve tag number, valve function and area of control for each service or system. The valve list will be in a punched 3-ring binder notebook. An additional copy of the valve list will be
22 05 11 - 22 mounted in picture frames for mounting to a wall. COR will instruct
Contractor where frames will be mounted.
4. A detailed plan for each floor of the building indicating the location and valve number for each valve will be provided in the
3-ring binder notebook. Each valve location will be identified with a color-coded sticker or thumb tack in ceiling or access door.
2.9 FIRESTOPPING
A. Section 07 84 00, FIRESTOPPING specifies an effective barrier against the spread of fire, smoke and gases where penetrations occur for piping.
2.10 GALVANIZED REPAIR COMPOUND
A. Mil. Spec. DOD-P-21035B, paint.
2.11 PIPE AND EQUIPMENT SUPPORTS AND RESTRAINTS
A. In lieu of the paragraph which follows, suspended equipment support and restraints may be designed and installed in accordance with the
International Building Code (IBC) and Section 13 05 41, SEISMIC
RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS. Submittals based on the International Building Code (IBC) and Section 13 05 41, SEISMIC
RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS requirements, or the following paragraphs of this Section will be stamped and signed by a professional engineer registered in the state where the project is located. The Support system of suspended equipment over 227 kg (500 pounds) will be submitted for approval of the COR in all cases. See the above specifications for lateral force design requirements.
B. Type Numbers Specified: For materials, design, manufacture, selection, application, and installation refer to MSS SP-58. Refer to Section 05
50 00, METAL FABRICATIONS, for miscellaneous metal support materials and prime coat painting.
C. For Attachment to Concrete Construction:
1. Concrete insert: Type 18, MSS SP-58.
2. Self-drilling expansion shields and machine bolt expansion anchors:
Permitted in concrete not less than 100 mm (4 inches) thick when approved by the COR for each job condition.
3. Power-driven fasteners: Permitted in existing concrete or masonry not less than 100 mm (4 inches) thick when approved by the COR for each job condition.
D. For Attachment to Steel Construction: MSS SP-58.
1. Welded attachment: Type 22.
22 05 11 - 23
2. Beam clamps: Types 20, 21, 28 or 29. Type 23 C-clamp may be used for individual copper tubing up to 23 mm (7/8 inch) outside diameter.
E. Attachment to Metal Pan or Deck: As required for materials specified in Section 05 31 00, STEEL DECKING.
F. For Attachment to Wood Construction: Wood screws or lag bolts.
G. Hanger Rods: Hot-rolled steel, ASTM A36/A36M or ASTM A575 for allowable load listed in MSS SP-58. For piping, provide adjustment means for controlling level or slope. Types 13 or 15 turn-buckles will provide 40 mm (1-1/2 inches) minimum of adjustment and incorporate locknuts.
All-thread rods are acceptable.
H. Multiple (Trapeze) Hangers: Galvanized, cold formed, lipped steel channel horizontal member, not less than 43 mm by 43 mm (1-5/8 inches by 1-5/8 inches), 2.7 mm (No. 12 gauge), designed to accept special spring held, hardened steel nuts.
1. Allowable hanger load: Manufacturers rating less 91kg (200 pounds).
2. Guide individual pipes on the horizontal member of every other trapeze hanger with 8 mm (1/4 inch) U-bolt fabricated from steel rod.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .