Attachment 01 Statment of Work Grizzly Flats Utility Hook-up.docx
DOCX document 55 KB Posted
- Attached to
- 127EAS23Q0051 Utility Hook Up Grizzly Flats
- Solicitation number
- 127EAS23Q0051
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 127EAS23Q0051 Amendment 02.pdf | ||
| Attachment 04 Wage Determination.pdf | ||
| Attachment 02 General site map.pptx | PPTX presentation | |
| Sol_127EAS23Q0051.pdf | ||
| Attachment 05 Response to Evaluation Factors.docx | DOCX document | |
| Attachment 03 Fire Plan_Placerville District.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents
| Project | 3 |
| General Information | 3 |
| 1.0 Scope of Work | 3 |
| 2.0 Background | 3 |
| Contractor Requirements | 3 |
| 3.0 Technical Requirements / Tasks | 3 |
| 4.0 Government Furnished | 3 |
| 5.0 Deliverables / Schedule | 3 |
| 6.0 Travel | 4 |
| 7.0 Contractor’s Key Personnel | 4 |
| 8.0 Security Requirements | 4 |
| 9.0 Data Rights | 4 |
| 10.0 Section 508 – Electronic and Information Technology Standards | 4 |
| Attachment | 4 |
Project Grizzly Flats Utility Hook-up
General Information
1.0 Scope of Work
This goal of this project is to prepare the site at Grizzly Flats to accommodate temporary buildings. This will entail rough grading the locations for the buildings, tapping into the main waterline, surface lay domestic water to the building locations with the ability to attach to multiple buildings, establish a shore power hookup from the transformer, laying a rough base course to stabilize the roads and parking.
2.0 Background
The Grizzly Flats fire station was destroyed during the Caldor Fire in 2021. The decision was made to rebuild a new station at the location for fire suppression coverage but until it is completed there is a need for temporary facilities. A separate contract will be submitted for the buildings.
Contractor Requirements Comment by Espinoza, Rocio - FS, CA: Recommend including a site map labeling areas of work
3.0 Technical Requirements / Tasks
The site is located at 6775 String Canyon Road, Grizzly Flats and is owned by the US Forest Service. A drawing of the site will be attached. All locations to be field fit on-site. All power lines are buried, residential water line was destroyed
Div 31. Earthwork. The contractor shall clear and grub as needed where the buildings will be placed. The contractor shall perform grading as needed for the site to accommodate the temporary structures (unknown number at this time but plan for up to 3 27’x64’ buildings of a mobile home style). This will include placing up to 6000ft sq area of 6-inch compacted ¾ inch minus gravel surface for the buildings. Comment by Espinoza, Rocio - FS, CA: Provide minimum depth
Div 32. Exterior improvements. The contractor shall stabilize the road up to 300 ft using 4-in deep ¾ inch minus compacted gravel surface in the existing road prism. The contractor shall also place gravel for personal parking (10 cars) and fire module parking (I Type 3 engine with water tender).
Div 33. Utilities. There is currently a PGE transformer at the site and the water main is functional. The contractor shall install equipment such that the buildings (3) can hook up to the shore power. Any pole installed should have the capability to increase the number of lines to power up to 5 buildings. The contractor shall tap into the main waterline and install up to 300’ of domestic water line able to provide shore water for the 3 buildings and a separate 2 in connection with valves and fittings to be used to fill the apparatus. Water service line to meet specifications per the International Plumbing Code 2021 Section 600. Pipe to be installed at a minimum of 36” below the surface. Place gravel base and cover per IBC and IPC. Terminate at a standpipe to provide connections for trailers. It is expected that the contractor will provide all necessary valves, fittings, temporary electric equipment and materials needed.
4.0 Government Furnished
The contractor will be able to use the site for staging as needed. Work will be conducted M-F between 7:30 am and 5:00 pm but can be adjusted based on needs.
5.0 Deliverables / Schedule
The contractor will provide the following prior to construction:
Site Safety Plan Tentative project schedule List of key personnel as identified
During Construction the contractor will:
Attend weekly jobsite meetings (depending on the length of the installation)
At the close of the project the contractor will:
| Provide as-builts |
| Any warranty information |
6.0 Travel
No travel provided by the government
7.0 Contractor’s Key Personnel
Contractor will identify the following personnel (at a minimum):
Project Manager Site Supervisor Safety Manager
8.0 Security Requirements
There is currently no security on site.