Attachment 01 - Statement of Work.pdf
PDF 672 KB Posted
- Attached to
- NDI Lab Pen Line Federal contract opportunity
- Solicitation number
- FA480325RS007
About this file
This Statement of Work (SOW) details an electrical infrastructure upgrade project at Shaw Air Force Base for the NDI Lab/Pen Line, with a project designation of VLSB 25-2502. The base bid (CLIN 0001) includes replacing circuit breakers, demolishing and installing new electrical wiring for a sub-panel, dryer equipment, and inspection equipment, and disconnecting and capping air connections. The work involves replacing a 150 AMP breaker at the main panel, installing 1/0 wiring to the sub-panel, replacing a 70 AMP breaker for the dryer, and installing #6 and #12 wire for dryer and inspection equipment respectively.
The contractor is required to follow multiple codes and standards, including UFC, UFGS, IBC, NEC, and others. A pre-construction meeting will be held at Shaw AFB to discuss project requirements. The contractor must minimize interference with base operations, coordinate utility outages, and ensure proper debris disposal, including providing electronic dump receipts to the government daily. The project includes a one-year warranty against workmanship defects, and the contractor must restore the facility to a professional appearance, cleaning both interior and exterior areas before returning the site to the government.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sources Sought Notice.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
NDI LAB / PEN LINE
13 Feb 2025
PROJECT: VLSB 25-2502
SCOPE OF WORK:
Remove existing wiring from panel to equipment and install new wiring to new equipment. Ensure wiring is code compliant for new equipment.
BASE BID (CLIN 0001):
• Replace circuit breaker at main panel that feeds sub-panel with 150 AMP breaker.
• Demo and install wiring from main panel to sub-panel with 1/0.
• Replace circuit breaker at sub panel for dryer with 70 AMP breaker.
• Demo and install wiring to new dryer equipment with #6 wire.
• Demo and install wiring to new inspection equipment with #12 wire.
• Disconnect air and cap connection to inspection machine.
GENERAL CONSTRUCTION NOTES:
The Contractor is responsible for protection of existing facilities equipment from damage during installation and testing operations.
WARRANTY:
Contractor shall furnish a minimum one-year warranty against defects in workmanship starting on the beneficial occupancy date.
Ensure that any demolition, utility cut and capping, and debris removal service performed at Shaw AFB, South Carolina in completed in such a manner that will restore a neat and professional appearance of base areas.
The facility/area shall be cleaned in its entirety, including exterior areas, before being returned the government.
GENERAL INFORMATION:
The contractor shall provide all management, tools, supplies, equipment, labor, and applicable licenses and permits necessary to complete the requirements within. All work shall be done in strict accordance with this Statement of Work and
Attachment 01
FA480325RS007
subject to the terms and conditions of the contract and in accordance with (UFC) Unified Facilities Criteria, Unified Facilities Guide Specifications (UFGS), the International Building Code (IBC), International plumbing code (IPC), South Carolina Department of Health and Environmental Control (SCDHEC), National Electrical Code (NEC), National Electrical Safety Code (NESC), National Fire Protection Association (NFPA), EPA 402-K-01-001 (2008), South Carolina Department of Transportation (SCDOT), South Carolina Department of Health and Environmental Control (SCDHEC) Shaw Air Force Base Design and Construction Standards, Change 2, 21 Aug 2018 and all other applicable codes.
A pre-construction meeting will be held at Shaw AFB to include the Contractor and Government representatives. The Government shall set up this meeting, to be held on Shaw AFB, with the Contractor and Government representatives, to discuss all remodel requirements, as well as any other construction issues the Contractor may have. All finishes shall be presented to the project inspector as one submittal for selection and approval prior to installation. All material that could be discontinued shall be on-site, i.e. carpet and tile prior to starting project so there will be no difference in color.
WORKING CONDITIONS:
The Contractor shall take all precautions to ensure that his operations are conducted in a manner as to minimally interfere with the normal operations of the base and the safety and convenience of the base personnel. The contractor shall coordinate utility outages with the Civil Engineering Squadron (CE) service call and the user.
DEBRIS HAULING AND DISPOSAL:
Contractor shall use an approved hauling route to prevent interference with base operations. In order to prevent problems with traffic, noise, wear and tear on roads, or other problems having the potential to adversely affect health, safety, or the environment, the government reserves the right to regulate routes, intervals, delivery points, and times for hauling.
All debris hauled by the contractor shall be enclosed to prevent leaking, spilling, or blowing. The Contractor shall ensure all debris or dirt is promptly removed from any transportation route if such debris is spilled, blown, or leaked from hauling equipment and vehicles. The contractor shall remove all dirt and mud caused by tracks of hauling equipment within one hour of notification by the Government. All demolition debris collected by the contractor shall be housed dumpsters and covered at all times and disposed of in an authorized landfill or transfer station. No disposal or burning is allowed on base. The contractor shall provide the government inspector with an electronic copy of each dump receipt on the following work day by 0800 with the daily report.
DAILY REPORTS:
The contractor shall provide the government with an electronic copy of each dump receipt along with the daily report by 0800 the following work day.
END OF STATEMENT OF WORK