Attachment 01 - Rigging Bldg 2735 PWS - 20241028.docx

DOCX document 38 KB Posted

Attached to
Construction Rigging and Material Handling Support Federal contract opportunity
Solicitation number
W519TC25QRIGG
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

This document contains a Performance Work Statement (PWS) for construction rigging and material handling support at Building 2735 of the Crane Army Ammunition Activity (Crane AAA) in Crane, Indiana. The contractor is required to disassemble, package, transport, and store concrete production equipment from the building, including a concrete pump, mixer, bag hoist, hopper, conveyors, silo, and drilling/tapping machines. The contractor must provide all labor, supervision, materials, tools, and equipment necessary to complete the work. The contractor has 10 days to perform the work and may subcontract if needed. The PWS outlines specific requirements for work requests, customer service reporting, normal and outside-of-normal service hours, environmental compliance, and security access.

The related federal contract opportunity is a solicitation (W519TC-25-Q-RIGG) issued by the Department of the Army Materiel Command Contracting Command Rock Island Arsenal for the required rigging and material handling services. This is a 100% small business set-aside under NAICS code 238290, with a one-year period of performance. The solicitation requires offerors to submit pricing at the CLIN level and indicates the Government intends to award on a lowest price technically acceptable basis.

View the file

Other files for this federal contract opportunity

Other files attached to Construction Rigging and Material Handling Support, newest first.
File Type Posted
Attachment 02 Pricing Sheet.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

28 Oct 2024

Construction Rigging and Material Handling Support Building 2735 At Crane Army Ammunition Activity General Description: To provide rigging, crane, and material handling support to demo the concrete round production equipment in Building 2735. In-house Maintenance lacks the specialized lifting fixtures, cranes, training, and manpower required to perform this work safely and in a timely manner. Specifically, the contractor is needed to perform the following:

- Travel to Crane Army Ammunition Activity, 300 Highway 361, Building 2735, Crane IN 47522.

- Disassemble the identified machinery and remove from the building
- Package for long term storage
- Load the packaged machinery pieces onto contractor supplied trailer
- Transport the packages to a storage location on base. Exact location TBD
- Unload trailer and place packages in the storage facility

Crane AAA will disconnect main utilities from all equipment prior to the contractor arrival onsite. Equipment to be demoed includes a concrete pump, mixer, bag hoist, hopper, supporting conveyors, concrete storage silo, and 4 drilling/tapping machines. See Appendix A for a list of specific equipment and model numbers.

1.0 Requirement: The contractor shall furnish all labor, supervision, materials, consumables, tools, and equipment to accomplish the work. All work shall be performed in accordance with the Standards referenced in paragraph 2 of this PWS. The contractor is responsible for the supervision of all employees engaged in executing the work effort as well as those who may be subcontracted to perform work.

1.1 Continuity of Work: The contractor shall commence work upon the issuance of a “work request” as provided in paragraph 3.1. The contractor shall diligently pursue the work effort during normal business hours. Postponing or interrupting work for a period exceeding 24 hours shall be for the purpose of obtaining replacement components, materials, or equipment. Work shall not be performed without a valid work request.

1.2 Execution: The contractor is responsible for analyzing the job to determine the proper procedures, tools, personnel, equipment, and materials needed to demo, package, and relocate the equipment used to produce concrete rounds in Building 2735. The contractor will be afforded 10 days to complete the work scope. If the contractor is unable to complete the needed work in this timeframe, or lacks the required technical expertise, the contractor may subcontract as needed to complete the work.

1.3 Tools, Equipment, and Materials The contractor shall furnish all tools, equipment, and materials necessary to perform the work. All tools and equipment shall be in good condition and pass all necessary inspections required for service. All OSHA required safety equipment and features must be installed and operational on all tools and equipment used to perform the work. Rigging devices shall meet OSHA 1926.251 requirements. Contractor shall inform the technical POC of any special, non-catalog fixtures or devices used for lifting and rigging prior to use. The contractor shall obtain COR approval for tool and material purchases that exceed $200.00 that will be charged to the job. All approvals shall be obtained in writing and shall be submitted with the associated Customer Service Report (see Section 3.3). Contractor shall have remote operation machinery skate capability.

2.0 Applicable Standards: The following two (2) standards (version in effect on date of solicitation issuance) shall be adhered to in the performance of work under this PWS:

U.S. Department of Labor Standards OSHA standards:

OSHA 1910 – General Industry OSHA 1926.251 – Rigging Equipment for Material Handling Requests for copies for the above standard can be made to:

Superintendent of Documents Government Printing Office Washington, DC 20402

3.0 Procedures: The procedures for performance under this contract are as follows:

3.1 Work Requests: The technical POC will issue Work Requests to the contractor via email; in the event e-mail is temporarily unavailable, the request will be made by telefax or by telephone. The request will contain an identification number, priority of request (urgent or routine), item to be removed/installed/relocated, and the nature of the service required.

3.2 Contractor Response Time: The contractor shall commence services within 10 business days of contract award.

3.3 Customer Service Report: The contractor shall prepare a separate Customer Service Report (CSR) for each Work Request received. The report shall contain the date(s) of service, contract number, work request number, description of work performed, materials provided and their costs, labor hours expended, and labor rate charged. The CSR shall separately identify normal labor hours, and outside of normal labor hours. The CSR shall reference and attach the Contracting Officer approval for all work hours outside of normal hours. The CSR shall also include actual invoices for all materials listed. The contractor shall provide the CSR, with associated backup, to the COR and Contracting Officer within 7 days of service completion.

3.4 Normal Service Hours: Services shall normally be performed between 7:00 am and 4:30 pm, Monday through Thursday, Eastern Time. Work scheduled outside these normal hours, as well as on holidays, shall be pre-approved by the Contracting Officer and shall not commence without said pre-approval.

3.5 Outside of Normal Service Hours Pre-Approval Process: The contractor shall obtain prior approval from the Contracting Officer for all service hours scheduled for outside the normal service hours (as delineated in Section 3.4). The contractor shall e-mail the request for outside of normal service hours to the Contracting Officer; the request shall include the Work Request identification number, date of proposed work, and estimated total labor hours. The contractor shall not engage in work outside of normal hours unless prior approval is obtained from the Contracting Officer. Contactor Officer approval documentation shall be submitted with the associated Customer Service Report for COR approval (see Section 3.3).

3.6 Acceptance: The COR shall indicate the Government’s acceptance of services under this contract by signing the Customer Service Report. The COR will retain one copy of the report and the contractor shall use his copy for purposes of invoicing the Government. The CSR shall be submitted with the invoice into the Wide Area Workflow (WAWF) system for billing purposes.

4.0 Place of Performance: The contractor shall perform the work on site at the Crane Army Ammunition Activity, Crane, Indiana, 47522.

5.0 Standard Language: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility, or area. Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

5.1 Screening Standards: Contractor and all associated sub‐contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC‐III) and Terrorist Screening Database (Army Directive 2014‐05/AR 190‐13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative); or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations. Contractor shall submit the following information to the COR no later than 10 days after contract award: name, address, and citizenship of each employee retained in performance of this contract. Contractor personnel must possess a valid driver’s license and proof of American citizenship prior to being admitted to the base. All personnel are subject to search of persons and vehicles at any time by the Government.

5.2 AT Level I training: All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I Awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 60 calendar days after completion of training by all employees and subcontractor personnel. AT level I Awareness training is available at the following website: http://jko.jten.mil. Comment by Bridget: Should there be a # here? Comment by Smith, Aaron D CIV USA AMC: updated Comment by Bridget: AT OPSEC document states "60 days" Comment by Smith, Aaron D CIV USA AMC: fixed

5.3 Access and General Protection/ Security Policies and Procedures:

5.3.1 Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

5.3.2 Contractor and all associated sub‐contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC‐III) and Terrorist Screening Database (Army Directive 2014‐05/AR 190‐13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative); or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

5.4 iWatch Training: The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award. Comment by Bridget: AT OPSEC document states "30 days" Comment by Smith, Aaron D CIV USA AMC: fixed Comment by Bridget: AT OPSEC document states "30 days" Comment by Smith, Aaron D CIV USA AMC: fixed

5.5 Badges: Identification badges issued by the Government shall be worn in such a manner as to be visible at all times while on base. The contractor shall ensure all identification badges are returned to the COR when no longer needed, and contractor shall account in writing for each missing badge as soon as they become aware of its absence.

5.6 Disclosure of Information: The contractor and their employees shall not disclose or cause to be disclosed any information concerning the operations and activities of CAAA and the Naval Surface Warfare Center, Crane. Disclosure of such information may subject the contractor or his agent to criminal liability under Title 18, Section 793 and 798 of the United States Code.

6.0 Environmental Requirements Comment by Bridget: Did the previous contract require Environmental Requirements? This info will be whatever is on the Environmental Cover Sheet. Comment by Smith, Aaron D CIV USA AMC: Changes made to reflect environmental check list

6.1 Compliance with Environmental Laws and Regulations: Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement, or Status-of-Forces Agreement. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR) and technical POC.

6.2 Competency Training for Contractor Personnel: Contractor shall not allow personnel to perform any activities and/or tasks on AMC installations without proper and adequate qualifications or job competency training. In the event of any identified noncompliance, the Contractor shall, if requested, provide proof of contract personnel training or qualification (individual name, training/qualification type, training/qualification certificate, and date of training/qualification) to perform those contract activities associated with the identified noncompliance.

6.3 Generation of Solid Waste: Contractor shall remove from the installation and dispose of all solid waste generated, which cannot be recycled to an approved and permitted off-post disposal facility.

6.3.1 Debris: Contractor shall make every effort to divert construction, demolition debris, and all other solid waste to comply with the Army Integrated Solid Waste Management Policy.

6.3.2 Recycling: Prior to removing any waste from the installation for disposal, the Contractor shall coordinate with the installation Qualified Recycling Program (QRP) Manager, DGR, technical POC and COR to arrange for recyclable materials to be removed and diverted from the waste stream.

6.3.3 Record Keeping: Submit in writing the quantities of waste removed and recycled to the DGR, technical POC and/or COR on a monthly basis. The submittal shall include the date of disposal/recycling, the disposal/recycling facility, the types of material disposed/recycled and the quantities of materials disposed/recycled by weight.

6.3.4 Reduction: The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.

6.3.5 Prevention: The Contractor shall make maximum effort to reduce and prevent waste.

6.4 Generation of Hazardous Waste: Contractor shall assign all hazardous waste management responsibilities to the appointed ECD. Contractor shall contact the DGR, technical POC, and/or COR to obtain technical assistance from the Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous waste storage and disposal requirements. Contractor shall properly profile all waste generated as part of this contract to determine if any waste is hazardous waste as defined by 40 CFR. Contractor shall accumulate hazardous waste prior to disposal shipment in a satellite accumulation point at or near the point of generation or in a less-than-90-day site, in accordance with Federal, State, Army, and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement or Status-of-Forces Agreement. The Contractor shall properly package the hazardous waste and complete the hazardous waste manifest, then take the manifest to DGR for approval and signature prior to removing any hazardous waste from the installation. Contractor shall contact DGR to obtain the installation’s hazardous waste EPA ID number for the hazardous waste manifest. The Contractor shall notify the DGR 24 hours prior to removing any hazardous waste from the installation. The contractor shall remove and dispose of manifested hazardous waste generated by contract activities from the installation, to an approved off-post permitted hazardous waste disposal facility. The DGR shall assist contractors with profiling their waste upon request.

6.5 Use of Hazardous Materials: Contractor shall assign all hazardous materials management responsibilities to the appointed ECD. Contractor shall contact the DGR, technical POC, and / or COR to obtain technical assistance from Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous material storage, issue, use, and disposal requirements. Contractor shall submit to the technical POC, COR and/or DGR a hazardous material inventory. The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed 180 consecutive days. The inventory list will contain the hazardous material type and maximum quantities of materials anticipated to be stored on-site. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. The Contractor shall maintain copies of Safety Data Sheets for all hazardous materials used and stored on-site during performance of the contract. Contractor shall not supply or deliver any hazardous materials or chemicals to an installation that are listed on EPA toxic chemical list without prior written approval from DGR, technical POC and/or COR.

6.6 Prevention of Spills: Contractor shall adopt the installation's Spill Prevention Control and Countermeasures Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. In case of a spill, the person in control of the spill site or their designated representative shall take appropriate action to protect workers and bystanders; contain the spill (if it can be done safely); secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department).

6.7 Universal Waste / e-Waste Management: Universal waste including but not limited to some mercury containing building products such florescent lamps, mercury vapor lamps, high pressure sodium lamps, CRTs, batteries, aerosol paint containers, electrical equipment containing PCBs, and consumed electronic devices, shall be managed in accordance with applicable environmental law and installation instructions.

6.8 Pollution Prevention / Hazardous Waste Minimization: Minimize the use of hazardous materials and the generation of hazardous waste. Consult with the Environmental Office for suggestions and to obtain a copy of the installation's pollution prevention/hazardous waste minimization plan for supporting waste minimization goals.

Attachment 1 – Equipment List

QTY
Equipment Name
Model Number
Manufacturer
Approximate Weight (lbs)
1
Concrete Pump
SP305E
Schwing
4320
4
Drilling/Tapping Machines
TCA 70
Jet
800
1
Bulk Bag Unloader Assembly
Type 6
Spiroflow
1200
1
Concrete Mixer Assembly
MP565/375
Sicoma
4000
1
Platform
1
Conveyor
1
Hopper
1
Silo 37’ x 8.5’
350
Zimmerman*
10,000

*Or similar with stationary non-drive through stand.

7.0 Performance Requirements Summary

Performance Objective
Performance Standard
Acceptable Quality Level
Monitoring Method

PWS Para 1.0 Requirement

The contractor shall furnish all labor, supervision, materials, consumables, tools, and equipment to accomplish the work. All work shall be performed in accordance with the Standards referenced in paragraph 2 of this PWS. The contractor is responsible for the supervision of all employees engaged in executing the work effort as well as those who may be subcontracted to perform work.
100% compliance with contract requirements.
Customer Feedback as requested or provided by technical POC.

PWS Para 1.1 Continuity of Work

The contractor shall commence work upon the issuance of a “work request” as provided in paragraph 3.1. The contractor shall diligently pursue the work effort during normal business hours. Postponing or interrupting work for a period exceeding 24 hours shall be for the purpose of obtaining replacement components, materials, or equipment. Work shall not be performed without a valid work request.
100% compliance with contract requirements
Customer Feedback as requested or provided by technical POC.

PWS Para 1.2 Execution

The contractor is responsible for analyzing the job to determine the proper procedures, tools, personnel, equipment, and materials needed to demo, install, or relocate the machinery in question. The contractor will be afforded a reasonable period of time to complete the work. If the contractor is unable to complete the needed work in a timely fashion, or lacks the required technical expertise, the contractor may subcontract as needed to complete the work.
100% compliance with contract requirements.
Customer Feedback as requested or provided by technical POC.

PWS Para 1.3 Tools, Equipment and Materials

The contractor shall furnish all tools. equipment and materials necessary to perform the work. All tools and equipment shall be in good conditions and pass all necessary inspections required. Rigging devices shall meet OSHA 1926.251 requirements. Contractor shall inform the technical POC of any special, non-catalog fixtures or devices used for lifting and rigging prior to use.
100% of the time, with no exceptions
Monitor contract expenditures by tracking invoice numbers, and dollar amounts for each work request

PWS Para 3.1 & 3.2 Work Requests Contractor Response Time

The technical POC will issue Work Requests to the contractor via email, telefax or by telephone. Upon issuance of contract, contractor shall commence service within 10 business days for routine work requests and 5 days for urgent work requests.
100% of the time, with no exceptions
Customer Feedback as requested or provided by technical POC.

PWS Para 3.3 Customer Service Report

The contractor shall prepare a separate Customer Service Report (CSR) for each Work Request received. The report shall contain the date(s) of service, contract number, work request number, description of work performed, parts and materials provided and their costs, labor hours expended and labor rate charged. The CSR shall separately identify normal labor hours, and outside of normal labor hours. The CSR shall also include actual invoices for all materials listed. The contractor shall provide the CSR, with associated backup, to the COR within 7 days of service completion.
100% of the time, with no exceptions
Customer Feedback as requested or provided by technical POC.

PWS Para 3.6 Acceptance

The COR shall indicate the Government’s acceptance of services under this contract by signing the Customer Service Report. The COR will retain one copy of the report and the contractor shall use his copy for purposes of invoicing the Government. The CSR shall be submitted with the invoice into the Wide Area Workflow (WAWF) system for billing purposes.
100% of the time, with no exceptions
Wide Area Workflow Notification to acceptor/COR