Attachment 01 Project Specifications.pdf

PDF 185 KB Posted

Attached to
Cooling Tower Maintenance
Solicitation number
12045320Q0012
Issued by

View the file

Other files

File Type Posted
Attachment 00 Schedule of Items.doc DOC document
12045320Q0012 Solicitation.pdf PDF
Attachment 02 Maintenance Guide.pdf PDF
Attachment 03 Drawings.pdf PDF
Attachment 04 Project Photos.docx DOCX document
Attachment 05 Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12045320Qxxxx Corvallis Forestry Sciences Laboratory

Cooling Tower Maintenance

TABLE OF CONTENTS

SECTION 00 00 50 - PROJECT DESCRIPTION

SECTION 00 01 00 - MEASUREMENT AND PAYMENT

SECTION 00 11 00 - WORK RESTRICTIONS

SECTION 01 33 30 - SUBMITTALS

SECTION 01 40 00 - QUALITY REQUIREMENTS

Cooling Tower Maintenance

SECTION 00 00 50

PROJECT DESCRIPTION

PART I - GENERAL

1.01 PROJECT DESCRIPTION

A. Renovation of Corvallis Lab’s Cooling Tower B. The Contractor shall remove all “drift eliminators” air inlet louvers and the wet deck medium and dispose of according to Oregon State law.

C. The Contractor shall remove all corroded/damaged interal accessories from the cold-water basin, such as the water strainers and supports.

D. The Contractor shall clean all surfaces per Baltimore Aircoil (BAC) manufacture maintenance/mechanical specifications.

E. The Contractor shall reassemble the internal accessories in the pan of the tower (per manufacture’s guidelines). Insuring proper fluid (cooling medium) circulation (throughout wet deck), in accordance with manufacturere’s specifications.

F. The Contractor shall install the original air-inlet louvers at the air-inlet faces of the towers.

G. The Contractor shall run the cooling system and observe for proper operation, sealing of work and overall completeness of the service project.

1.02 RELATED WORK

A. As needed, pressure wash the interior of each cell to remove all corroded, loose debris and knock off mineralized scale. Contractor shall clean all surfaces to be recoated.

B. Contractor shall grind down the interior of the pan as needed to make a bondable surface for the epoxy to be able to adhere with the metal substrate. The preperation and epoxy coating in the cold water pan shall be up to the top of the over-flow outlet of the lower cold water pan; with coating around the vertical sides of the pan up to his horizontal line defined by the top of the “step wall”.

C. Contractor shall seal all metal panel seams and any pin holes detected with manufacture approved sealer material. Install pultruded FRP with sealers or metal overlays and screws (if the surface of the cooling tower has sheet metal that is rusted through the contractor shall remove the damaged sheet metal and replace with a new 12 gauge galvanized sheet metal and screw the replacement material to the surface of the cooling tower). Allow all sealed areas to cure properly (per manufacturers specifications) before proceeding to the coating phase.

D. Contractor shall apply a two-part epoxy material to the entire floor and walls of the cooling tower (e.g. Panseal, elastomeric/rubber base to all perpared surfaces). Lay in FRP or similar approved material mesh into the first coat of epoxy on the horizontal surfaces of the cold water basin for extra protection.

1. Color Schedule – As per original product or a shade blend of orginal color.

2. Epoxy shall be applied in accordance with the applicable specification and/or manufacturer's instructions.

3. Epoxy and finishing materials shall be free from skins, lumps, or any foreign matter, and kept well stirred while being applied.

4. All work shall be protected against spatters, stains or soiling, and each type of finish shall be protected against similar defacement by other finish and shall be left clean.

5. Each coat of epoxy shall be evenly worked out and allowed to dry before any subsequent coat is applied or rubbing done.

6. The finish work shall be free from runs and sags, defective brushing, and/or clogging of lines or angles

E. Touch Up - At the completion of other branches of the work, all painted surfaces and finished work shall be touched up and restored where damaged or defaced, and the entire work left free from blemished.

Cooling Tower Maintenance

PART II - PRODUCTS

2.01 N/A

PART III - EXECUTION

3.01 UTILITIES

A. Utilities, (electricity and water) will be available for contractor's use, limited to reasonable use for the service project. It shall be the contractor's responsibility to maintain water and electrical needed to maintain safe conditions.

3.02.1 BUILDING ENVIRONMENT

A. Contractor shall maintain a clean, dust free office environment throughout the progress of work.

3.02.2 WORK NOT INCLUDED

A. N/A.

3.04 ALL OTHER PRODUCTS AND EXECUTION

A. Work shall be in accordance with the drawings and the service project specifications.

END OF SECTION 00 00 50

SECTION 00 01 00

MEASUREMENT AND PAYMENT

PART I - GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.

B. When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any pay item, suffixes will be added to the item number to differentiate between items to be bid.

1.02 DETERMINATION OF QUANTITIES

A. The following methods of measurement are used to determine contract quantities for payment:

1. For individual service project items, longitudinal and lateral measurements for area computations will be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, geotextiles, netting, erosion control blankets, and sodding will be along slope lines.

2. Structures will be measured according to neat lines SHOWN ON THE DRAWINGS or as altered by the Engineer in writing to fit field conditions.

Cooling Tower Maintenance

3. For items that are measured by the linear foot, measurements will be made parallel to the base or foundation upon which the structures are placed

4. For standard manufactured items, such as fence, wire, plates, rolled shapes, pipe conduits, etc., identified by gauge, weight, section dimensions, etc., such identification shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances will be accepted.

1.03 UNITS OF MEASUREMENT

A. Payment will be by units defined and determined according to U.S. Standard measure as follows:

1. Acre – Make longitudinal and transverse measurements for area computations horizontally.

2. Cubic Yard - A measurement computed by one of the following methods:

Material in the Delivery Vehicle - The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

3. Cubic Yard Mile - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material 1 mile.

4. Each - One complete unit, which may consist of one or more parts.

5. Gallon – The quantity may be measured by any of the following methods:

a. Measured volume container.

b. Metered volume. Use an approved metering system.

c. Commercially packaged volumes.

6. Measured volume container.

7. Metered volume. Use an approved metering system.

8. Commercially packaged volumes.

9. Hour – Measurement will be for the actual number of hours ordered and performed by the Contractor.

10. Linear Foot – Measure from end to end, parallel to the base or foundation being measured, or horizontal.

11. Mile – Measure horizontal along the centerline of each roadway, approach road.

12. Pound – If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.

13. Square Foot – A plane parallel to the surface being measured or horizontal.

14. Square Yard – A plane parallel to the surface being measured or horizontal.

15. Ton - Short ton consisting of 2,000 pounds.

16. Ton Mile - A combination of linear and weight measurement meaning the movement of 1 ton of material 1 mile.

17. Lump Sum – One complete unit.

1.04 METHODS OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:

1. Designed Quantities (DQ) - These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the service project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the Contracting Officer.

b. As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities that cause a pay item to change by 15 percent or more.

Cooling Tower Maintenance

c. As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by 15 percent or more.

The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

2. Actual Quantities (AQ) - These quantities are determined from measurements of completed work.

3. Vehicle Quantities (VQ) - Quantities measured or weighed in hauling vehicles.

4. Lump Sum Quantities (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.

PART II - PRODUCTS (Not Applicable)

PART III - EXECUTION (Not Applicable)

END OF SECTION 00 01 00

SECTION 00 11 00

WORK RESTRICTIONS

PART I - GENERAL

1.01 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.

1. Limits: Confine the projects operations within cooling tower gated area and adjacent staging areas.

2. Government Occupancy: Allow for Government occupancy of site and use by the public.

B. Work will be performed between the hours of 8:00 A.M. and 4:30 P.M. Monday through Friday except Government Holidays.

C. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Occupants, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

D. Use of Existing Building:

1. Bathroom facilities (as needed) sign-in with admin staff.

2. Maintain existing building in a weathertight condition throughout the service project period.

3. Repair all damages caused by the service project operations.

4. Areas requiring roof access; protect the roof structure from damage

5. Protect building and its occupants during the service project period.

1.02 OCCUPANCY REQUIREMENTS

A. Full Government Occupancy: Government will occupy site and existing the building during entire the service project period. Cooperate with Government during the project operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government operations.

Cooling Tower Maintenance

PART II - PRODUCTS (Not Used)

PART III - EXECUTION (Not Used)

END OF SECTION 00 11 00

SECTION 01 33 30

SUBMITTALS

PART I - GENERAL

1.01 SCOPE

A. This section covers the contractor's responsibility relating to all submittals that relate to the service project scope of work.

1.02 Measurement and Payment

A. No separate measurement and/or payment will be made for this section.

PART II - PRODUCTS (Not Applicable)

PART III - EXECUTION

3.01 All Submittals

A. It will be the Contractor's responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work which involves the submittal.

Contractor shall allow 10 calendar days for processing of submittals by the Government.

3.02 Manufacturer's (Epoxy) Literature

A. Submit one copy to the Contracting Officer Representative for the approval process on the items required herein. Literature which is not marked or otherwise designated to show the exact model and size that the contractor proposes to use will be returned by the Contracting Officer “without action." Circle or check items to be used on submittals. Highlighter pens may print black or not at all when copied and should not be used.

B. Information must be adequate to determine compliance with specifications.

C. Submittals and drawings which are received from sources other than through contractor's office will be returned by the COR "without action."

3.03 Samples

A. Items and materials as required per manufacture specifications and guidance.

3.04 Substitution

A. Materials in the specifications may be followed by the words "or approved equal." In these cases, wherever the name or brand of a manufacturer's article is specified, it is used as a measure of quality and utility or a standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution and his decision shall be final. Unless

Cooling Tower Maintenance substitutions are requested within the time stated above and as provided below, no deviation from the specifications will be allowed.

B. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

END OF SECTION 01 33 30

SECTION 01 40 00

QUALITY REQUIREMENTS

PART I – GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specific quality-assurance and control requirements for individuals and project activities that are addressed in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products.

2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.

3. Requirements for Contractor to provide quality-assurance and -control services required by Design Professional, Owner, CO, or authorities having jurisdiction are not limited by provisions of this Section.

C. Related Sections include the following:

Division 01 Section "Cutting and Patching" for repair and restoration of the project disturbed by testing and inspecting activities. Division 02 through 49 Sections for specific test and inspection requirements.

1.03 DEFINITIONS

A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed service work will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the service work and completed work complies with requirements. Services do not include contract enforcement activities performed by the service Project Manager.

Cooling Tower Maintenance

C. Pre-service Testing: Tests and inspections that are performed specifically for the service project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.

D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.

E. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.

F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular the service operation, including installation, erection, application, and similar operations.

1. Using a term such as "carpentry" does not imply that certain service project activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name.

I. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

1.04 CONFLICTING REQUIREMENTS

A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to the service Project Manager for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.

To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.

1.05 SUBMITTALS

A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

B. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.06 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in a record of successful in-service performance.

C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

Cooling Tower Maintenance

D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where this project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent.

F. Specialists: Certain sections of the Specifications require that specific project service activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1. Requirement for specialists shall not supersede building codes and regulations governing the Work.

1.07 QUALITY CONTROL

A. Owner Responsibilities: All quality-control services are indicated as Contractor’s responsibility.

B. Contractor to provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.

1. Contractor shall engage a qualified testing agency to perform these quality control services.

a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.

b. It is the Contractor's responsibility to submit a certified written report, in duplicate, of each quality-control service.

c. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.

2. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor's responsibility.

3. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

C. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Division 01 Section "Submittal Procedures."

D. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid the necessity of removing and replacing associated project items to accommodate testing and inspecting. Schedule times for tests, inspections, obtaining samples, and similar activities.

END OF SECTION 01 40 00

TABLE OF CONTENTS
SECTION 00 00 50 - PROJECT DESCRIPTION
SECTION 00 01 00 - MEASUREMENT AND PAYMENT
SECTION 00 11 00 - WORK RESTRICTIONS
SECTION 01 33 30 - SUBMITTALS
SECTION 01 40 00 - QUALITY REQUIREMENTS
a. Measured volume container.
b. Metered volume. Use an approved metering system.
c. Commercially packaged volumes.