Attachment 002 Jessieville Work Center 2024 Bathroom Specifications R4.pdf
PDF 486 KB Posted
- Attached to
- 12445124Q0004 Jessieville Shower/Bath
- Solicitation number
- 12445124Q0004
About this file
This federal contract opportunity document solicits quotes for a construction project to improve bathroom facilities and office space at a USDA Forest Service work center. The scope of work includes repairing and replacing walls, installing a new bathroom and lift station, and completing associated electrical, plumbing and painting. Quotes are due by April 16, 2024. The award will be a firm-fixed price contract made to the lowest priced responsive, responsible offeror. The period of performance is 60 days from notice to proceed. The project is set aside 100% for small businesses. The NAICS code is 236220 and PSC code is Z2FB.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12445124Q0004 AMD 0001 Package.pdf | ||
| Attachment 003 Jessieville Work Center 2024 Bathroom Plans.pdf | ||
| Attachment 001 Schedule of Items.docx | DOCX document | |
| Attachment 004 Davis-Bacon Act WD AR20240116.txt | TXT text file | |
| 12445124Q0004 Jessieville Bath RFQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
JESSIEVILLE WORK CENTER
BATHROOM CONSTRUCTION
USDA FOREST SERVICE
OUACHITA NATIONAL FOREST
JESSIEVILLE RANGER DISTRICT
JESSIEVILLE, ARKANSAS
SPECIFICATIONS INDEX
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01 10 00 SUMMARY OF WORK
SECTION 01 31 13 COORDINATION
SECTION 01 33 00 SUBMITTAL PROCEDURES
SECTION 01 45 00 QUALITY CONTROL
SECTION 01 77 00 PROJECT CLOSEOUT
DIVISION 2 – EXISTING CONDITIONS
SECTION 02 41 00 - DEMOLITION
DIVISION 3 - CONCRETE
SECTION 03 30 00 - CAST IN PLACE CONCRETE
DIVISION 6 – WOOD AND PLASTICS
SECTION 06 10 00 – ROUGH CARPENTRY
SECTION 06 20 00 - FINISH CARPENTRY
DIVISION 7 – MOISTURE CONTROL
SECTION 07 24 00 – EXTERIOR INSULATION AND FINISH SYSTEM
DIVISION 8 – OPENINGS
SECTION 08 71 00 – DOOR HARDWARE
DIVISION 9 – FINISHES
SECTION 09 21 16 - GYPSUM BOARD ASSEMBLIES
SECTION 09 91 00 - PAINTING
DIVISION 22 – PLUMBING
SECTION 22 00 00 – PLUMBING
DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING (HVAC)
SECTION 23 34 00 - VENTILATING EQUIPMENT
DIVISION 26 – ELECTRICAL
SECTION 26 01 00 - BASIC ELECTRICAL REQUIREMENTS
SECTION 26 50 50 – LIGHTING
DIVISION 27 –COMMUNICATIONS
SECTION 27 10 00 – STRUCTURED CABLING FOR VOICE AND DATA
DIVISION 1
GENERAL REQUIREMENTS
01 10 00 – SUMMARY OF WORK
The project is located at the Jessieville Work Center 8402 N Hwy 7, Jessieville, AR 71949.
The contractor shall provide all labor, tools, equipment, and materials to perform the work listed below per the specifications:
1. Relocate existing data entering building to the break room area.
2. Relocate network cabling and equipment to new, contractor provided, ventilated, lockable cabinet in break room area.
3. Repair EFIS and paint to match after removing data cable. (est. 1 sq ft)
4. Repair two damaged areas in the EFIS and paint to match. (est. 2 sq ft)
5. Open existing wall and frame opening for new door.
6. Remove existing concrete floor as needed for shower recess and plumbing installation (estimated at 80 sq ft)
7. Install new supply, drain and vent plumbing according to plans. Core drill footing for drain if needed.
8. Pour new concrete floor with recess for shower pan.
9. Remove one existing door, fill in opening with materials matching existing construction and paint to match.
10. Construct partition wall between shower and sink.
11. Install new receptacles where shown on plans.
12. Provide and install automatic humidity sensing exhaust fan vented through wall.
13. Remove one existing light fixture and install new.
14. Provide, install and wire tank hot water heater in bathroom on elevated platform with drip pan to serve shower and sink
15. Paint the bathroom floor with epoxy paint
16. Repair drywall, texture, install trim and paint
17. Provide and install and plumb shower, sink and toilet
18. Provide and install bathroom handrails
19. Provide and install, plumb and wire lift station behind building
20. Saw cut and remove asphalt 3 feet from building on east and south sides
21. Trench new forcemain around east and south sides of building and connect to existing sewer main with a wye
22. Pour 3 ft wide concrete to repair parking lot with positive slope from building
23. Clean bathroom
01 31 13 – PROJECT COORDINATION
The contractor shall perform work in a manner that will protect the safety of the public and employees. The contractor shall perform the work between the hours of 7:00 AM and 5:00 PM Monday through Friday excluding Federal Holidays unless arrangements have been made with the COR.
During the Contract, the construction area will be open for employees to work in the buildings. The Contractor’s work shall not adversely affect the operation. The Contractor is responsible for keeping the site in a safe condition. Hazards to the public and government employees shall be well marked in compliance with OSHA regulations.
01 33 00 – SUBMITTAL PROCEDURES
The contractor shall furnish submittals on items they intend to use on the project.
Submittals shall be made within fifteen (15) days prior to commencing any work that relates to a respective submittal. Approvals are not automatic. Incomplete information on the proposed items will result in rejection.
The contractor shall submit one electronic copy of the manufacturer's description of all "or equals" proposed materials that will be used on the project. This description shall include:
1) Product name and model number
2) Manufacturer
3) Product description (include sizes if different from specified"
4) Technical data
5) Warranty
All differences between the specifications or name brands listed shall be highlighted on the submittal noting all differences.
01 45 00 – QUALITY CONTROL
It is the Government's intent that expert and experienced workers perform the work described in this contract. The Contractor shall provide workers with the necessary skills and knowledge to complete the work in an expert and competent manor even if this requires bringing in outside help such as factory representatives, subcontractors, or consultants.
01 77 00 – CONTRACT CLOSEOUT
The contractor shall remove all materials and construction debris as well as impacted vegetation from the site.
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced.
The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION
OFFICIALS (AASHTO)
AASHTO M 145 (1991; R 2012) Standard Specification for Classification of Soils and Soil-Aggregate Mixtures for Highway Construction Purposes
AASHTO T 180 (2017) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations
ASTM INTERNATIONAL (ASTM)
ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
Demolition is the process of tearing apart and removing any feature of a facility together with any related handling and disposal operations.
1.2.1.2 Deconstruction
Deconstruction is the process of taking apart a facility with the primary goal of preserving the value of all useful building materials.
1.2.1.3 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
1.2.1.4 Deconstruction Plan
Deconstruction Plan is the planned steps and processes for dismantling all or portions of a structure or assembly, to include managing sequencing activities, storage, re-installation activities, salvage and disposal mechanisms.
1.2.2 Demolition/Deconstruction Plan
Prepare a Deconstruction Plan and submit proposed salvage, demolition, deconstruction, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged.
1.2.3 General Requirements
Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site. The work includes demolition, deconstruction, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Comply with FAR 52.236-9 to protect existing vegetation, structures, equipment, utilities, and improvements. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Do not overload pavements to remain. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction.
1.3.2 Trees
Protect trees within the project site which might be damaged during demolition or deconstruction, and which are indicated to be left in place. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer.
1.3.3 Utility Service
Maintain existing utilities in service and protect against damage during demolition and deconstruction operations.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted.
1.5 AVAILABILITY OF WORK AREAS
Areas in which the work is to be accomplished will be available at contract award.
1.6 QUALITY ASSURANCE
Comply with federal, state, and local hauling and disposal regulations.
1.6.1 Dust and Debris Control
Prevent the spread of dust and debris into the stream and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep pavements as often as necessary to control the spread of dirt and debris that may result in foreign object damage potential to vehicles or be tracked off site.
1.7 PROTECTION
1.7.1 Traffic Control Signs
a. Where pedestrian and driver safety is endangered in the area of work, use traffic barricades.
1.8 EXISTING CONDITIONS
Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer or the Contracting Officer's Representative showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs or electronic images with a minimum resolution of 3072 x 2304 pixels, capable of a print resolution of 300 dpi, will be acceptable as a record of existing conditions. Include in the record the location and extent of existing cracks and other damage and description of conditions that exist prior to starting work.
Submit survey results to the Contracting Officer or the Contracting Officer's Representative.
PART 2 PRODUCTS
2.1 FILL MATERIAL
a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill voids, depressions or excavations resulting from demolition or deconstruction of structures.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
Disassemble existing structure scheduled to be removed. Dismantled and removed materials are to be separated, set aside and prepared as specified.
3.1.1 Structures
a. Remove existing structures indicated to be removed.
b. Deconstruct structure in a systematic manner from the top of the structure to the ground.
3.1.2 Utilities and Related Equipment
Do not interrupt existing utilities in the area, except when authorized in writing by the Contracting Officer.
3.1.3 Concrete
Saw or break out concrete floor and/or footings.
3.2 CONCURRENT EARTH-MOVING OPERATIONS
Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed.
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials removed and not reused or salvaged, become the property of the Contractor and must be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials to be removed, is vested in the Contractor upon approval by the Contracting Officer. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.3.2 Reuse of Materials
Remove and store materials listed in the plans to be reused or relocated to prevent damage, and reinstall as the work progresses.
3.4 CLEANUP
Remove debris and rubbish from project site and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas.
Apply local regulations regarding hauling and disposal.
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other non-salvageable materials resulting from removal operations with all applicable federal, state and local.
3.5.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.
3.5.3 Removal from Government Property
Transport waste materials removed from demolished and deconstructed structures from Government property for legal disposal.
3.6 REUSE OF SALVAGED ITEMS
Recondition salvaged materials designated for reuse before installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.
DIVISION 3
SECTION 03 30 00
CAST IN PLACE CONCRETE
A. This section covers cast in place concrete, including curing and finishing of concrete. The concrete for this project shall be for the bathroom floor and the parking lot patching.
B. Items requiring submittals shall include;
1. Concrete Mix Design
C. The latest editions of the following specifications and recommended practices shall govern:
1. ACI 301 Specifications for Structural Concrete
2. ACI 306 Recommended Practice for Winter Concrete
3. ACI 305 Recommended Practice for Hot Weather Concrete
PART 2 PRODUCTS
A. Aggregate shall conform to the requirements of Federal Specification SS A 281, Classes 1 and 2, and shall be well graded from fine to coarse within designated limits.
B. Portland Cement shall comply with ASTM C150, Type 1. Supplier shall provide mill certification of compliance with specification.
C. Water shall be clean, fresh, and free from injurious amounts of minerals or foreign substances.
D. Additives, air entrainment agents shall comply with ASTM C 260.
E. Concrete Mix Design
1. All concrete shall have a minimum "compressive strength" of 3000 psi at 28 days.
2. The design of the concrete mixture shall be the responsibility of the contractor and must be approved by the COR prior to pour.
PART 3 EXECUTION
A. Vapor barrier of at least 10 mils or 6 inch thickness of washed rock shall be installed under all interior concrete.
B. "Ready Mixed Concrete" may be employed if the time interval between mixing at the plant and discharge into the form does not exceed 1 1/2 hours.
C. All concrete shall be placed within 1 1/2 hours from the time of mixing.
1. No concrete shall be placed after it has started its initial set.
2. No concrete with a temperature above 90F shall be placed.
D. Concrete shall be placed in such a manner as to avoid segregation of the mixture.
1. Concrete shall be spread in horizontal layers when practicable.
2. No concrete shall be freely dropped more than 5'.
3. Depositing a large quantity of concrete and flowing or working it along the forms will not be permitted.
E. Concrete shall be placed and protected as specified for temperature conditions.
F. Concrete plant standards and truck mixer and agitator standards shall be as recommended by the National Ready-Mix Association.
G. Finishing
1. All finishes shall be made without use of cement or other dusting materials.
2. Concrete shall be struck to proper grade.
3. Interior surface finish with float trowels.
4. Broom finish exterior surfaces.
H. Concrete shall be protected against rapid drying for seven days.
I. Testing
1. Concrete shall have a minimum 28 day breaking strength of 3000 psi when tested in accordance with ASTM C 39.
2. Slump shall not exceed 4 inches for concrete.
DIVISION 6
SECTION 06 10 00
ROUGH CARPENTRY
PART 1 - GENERAL
A. WORK INCLUDED: Framing
B. Grading and Standards
1. All plywood shall conform to PS-1-74 and to the latest standards of the
American Plywood Association or Hardwood Plywood Institute. All plywood shall be certified by the appropriate grade trademark of the Association.
2. All dimensional lumber shall conform to the latest standards of the American Lumber Standard Committee.
PART 2 - PRODUCTS
A. PLYWOOD Sheathing shall be exterior type "C-D" EXT APA or better, as defined by the American Plywood Association. Thickness shall be the same as what is on the existing wall.
B. Nails ASTM F547, size and type best suited for purpose. For sheathing length of nails must be sufficient to extend 1 inch into supports. In general, 8-penny or larger nails must be used for nailing through 1 inch thick lumber and for toe nailing 2 inch thick lumber; 16-penny or larger nails must be used for nailing through 2 inch thick lumber. Nails used with treated lumber and sheathing must be hot-dipped galvanized in accordance with ASTM A153/A153M. Nailing must be in accordance with the recommended nailing schedule contained in AWC WFCM. Where detailed nailing requirements are not specified, nail size and spacing must be sufficient to develop an adequate strength for the connection.
The connection's strength must be verified against the nail capacity tables in AWC NDS. Reasonable judgment backed by experience must ensure that the designed connection will not cause the wood to split. If a load situation exceeds a reasonable limit for nails, a specialized connector must be used.
C. Dimensional Lumber shall be locally available, kiln-dried, whitewood, spruce, pine or fir.
PART 3 - EXECUTION
A. General Requirements
1. Notify COR before removing any rotten or damaged sheathing.
2. After getting approval from the CO or COR rotten or damaged sheathing can be removed and replaced.
3. Do not install building construction materials that show visual evidence of biological growth.
B. Sheathing
a. Install with the grain of the outer plies or long dimension at right angles to supports. Stagger end joints and locate over the centerlines of supports.
Allow 1/8 inch spacing at panel ends and edges. Nail panels with 8-penny common nails or 6-penny annular rings or screw-type nails spaced 6 inches o.c. at supported edges and 12 inches o.c. at intermediate bearings. Do not use staples in sheathing. Where the support spacing exceeds the maximum span for an unsupported edge, provide adequate blocking in accordance with APA E30.
C. Wall Framing
a. Studs
Select studs for straightness and set plumb, true, and in alignment. In walls and partitions more than 8 feet tall, provide horizontal bridging at not more than 8 feet o.c. using nominal 2 inch material of the same width as the studs; install the bridging flat. Sizes and spacing of studs must be nominal 2 inches by 4 inches on 16 inch centers. Double studs at jambs and heads of openings and triple at corners to form corner posts. Frame corner posts to receive interior finish. Truss over openings exceeding 4 feet in width or use a header of sufficient depth. Toe-nail studs to sills or sole plates with four 8-penny nails or fasten with metal nailing clips or connectors. Anchor studs abutting concrete or masonry walls thereto near the top and bottom and at midheight of each story using expansion bolts or powder-actuated drive studs.
b. Plates Use plates for walls and partitions of the same width as the studs to form continuous horizontal ties. Splice single plates; stagger the ends of double plates. Double top plates in walls and bearing partitions, built up of two nominal 2 inch thick members. Top plates for nonbearing partitions must be single or double plates of the same size as the studs. Nail lower members of double top plates and single top plates to each stud and corner post with two 16-penny nails. Nail the upper members of double plates to the lower members with 10-penny nails, two near each end, and stagger 16 inches o.c. intermediately between. Nail sole plates on wood construction through the subfloor to each joist and header; stagger nails.
Anchor sole plates on concrete with expansion bolts, one near each end and at not more than 6 feet o.c., or with powder-actuated fasteners, one near each end and at not more than 3 feet o.c. Provide plates cut for the passage of pipes or ducts with a steel angle as a tie for the plate and bearing for joist.
c. Ceiling Joists
Size as indicated and set accurately and in alignment. Toe-nail joists to all plates with not less than three 10-penny nails. Frame openings in ceilings with headers and trimmers.
SECTION 06 20 00
FINISH CARPENTRY
PART 1 – GENERAL
A. This section covers all trim and related items.
B. Deliver products to the jobsite in an undamaged condition. Stack materials to ensure ventilation and drainage. Protect against dampness before and after delivery. Store materials under cover in a well-ventilated enclosure and protect against extreme changes in temperature and humidity. Keep materials wrapped and separated from off-gassing materials (such as drying paints and adhesives). Do not use materials that have visible moisture or biological growth.
PART 2 – PRODUCTS
A. Size references, unless otherwise specified, are nominal sizes.
B. Interior Door: Solid core, non-MDF, 36in x 80in x 1-3/8in, 5 or 6 panel door
C. Interior trim: 9/16” x 3-1/4” Royal Building Products PVC Baseboard Molding or equal. 11/16” x 2-1/4” Royal Building Products PVC Casing Molding or equal.
D. Use nails of a size and type best suited for each application and in accordance with
ASTM F547. Where nailing is impractical, provide screws of a size and type best suited for each application.
PART 3 – EXECUTION
A. SAFETY:
Contractor shall follow all OSHA required safety procedures while performing work, including use of FALL PROTECTION and PPE when required.
DIVISION 7
SECTION 07 24 00
EXTERIOR INSULATION AND FINISH SYSTEMS
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM B117 (2019) Standard Practice for Operating Salt Spray (Fog) Apparatus ASTM C67/C67M (2023) Standard Test Methods for Sampling and Testing Brick and Structural Clay Tile ASTM C150/C150M (2022) Standard Specification for Portland Cement ASTM C473 (2019) Standard Test Methods for Physical Testing of Gypsum
Panel Products ASTM C578 (2022) Standard Specification for Rigid, Cellular Polystyrene
Thermal Insulation ASTM C847 (2014a) Standard Specification for Metal Lath ASTM C920 (2018) Standard Specification for Elastomeric Joint Sealants ASTM C1177/C1177M (2017) Standard Specification for Glass Mat Gypsum
Substrate for Use as Sheathing ASTM C1186 (2022) Standard Specification for Flat Fiber-Cement Sheets ASTM C1278/C1278M (2017) Standard Specification for Fiber-Reinforced
Gypsum Panel ASTM C1325 (2022) Standard Specification for Fiber-Mat Reinforced
Cementitious Backer Units ASTM D968 (2022) Standard Test Methods for Abrasion Resistance of Organic
Coatings by Falling Abrasive ASTM D2247 (2015; R 2020) Standard Practice for Testing Water Resistance of
Coatings in 100 Percent Relative Humidity ASTM D3273 (2021) Standard Test Method for Resistance to Growth of Mold on the Surface of Interior Coatings in an Environmental Chamber ASTM E84 (2023) Standard Test Method for Surface Burning Characteristics of
Building Materials ASTM E136 (2022) Standard Test Method for Assessing Combustibility of
Materials Using a Vertical Tube Furnace at 750 Degrees C ASTM E330/E330M (2014; R 2021) Standard Test Method for Structural
Performance of Exterior Windows, Doors, Skylights and Curtain Walls by Uniform Static Air Pressure Difference
ASTM E331 (2000; R 2023) Standard Test Method for Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air Pressure Difference
ASTM E695 (2022) Standard Test Method of Measuring Relative Resistance of Wall, Floor, and Roof Construction to Impact Loading
ASTM E2098/E2098M (2013; R 2018) Standard Test Method for Determining Tensile Breaking Strength of Glass Fiber Reinforcing Mesh for Use in Class PB Exterior Insulation and Finish Systems (EIFS), after Exposure to a Sodium Hydroxide Solution
ASTM E2486/E2486M (2022) Standard Test Method for Impact Resistance of Class PB and PI Exterior Insulation and Finish Systems (EIFS)
ASTM E2570/E2570M (2007; R 2019) Standard Test Methods for Evaluating Water-Resistive Barrier (WRB) Coatings Used under Exterior Insulation and Finish Systems (EIFS) or EIFS with Drainage
ASTM G153 (2013; R 2021) Standard Practice for Operating Enclosed Carbon Arc Light Apparatus for Exposure of Nonmetallic Materials
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2021) International Building Code
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 268 (2022) Standard Test Method for Determining Ignitability of Exterior Wall Assemblies Using a Radiant Heat Energy Source
NFPA 285 (2023) Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Wall Assemblies Containing Combustible Components
1.2 SYSTEM DESCRIPTION AND REQUIREMENTS
The exterior insulation and finish system (EIFS) must be a job-fabricated, drainable, exterior wall covering consisting of sheathing, air and moisture barrier, insulation board, reinforcing fabric, base coat, finish coat, adhesive and mechanical fasteners as applicable. The system components must be compatible with each other and with the substrate as recommended or approved by, and the products of, a single manufacturer regularly engaged in furnishing Exterior Insulation and Finish Systems. All materials must be installed by an applicator approved by the system manufacturer. EIFS must be match existing materials, color and finish.
1.3 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Product Data Warranty SD-02 Manufacturer's Instructions Manufacturer's Instructions
1.4 QUALITY CONTROL
1.4.1 Qualifications of EIFS Manufacturer
The EIFS must be the product of a manufacturer who has been in the practice of manufacturing and designing EIFS.
1.4.2 Qualification of EIFS Installer
The Contractor must employ qualified workers trained and experienced in installing the manufacturer's EIFS.
1.4.3 Qualification of Sealant Applicator
The sealant applicator must be experienced and competent in the installation of high performance industrial and commercial sealants.
1.4.5 Insulation Board
Insulation Board must be approved and labeled under third party quality program as required by applicable building code.
1.5 DELIVERY AND STORAGE
Deliver materials to job site in original unopened packages, marked with manufacturer's name, brand name, and description of contents. Store materials off the ground and in accordance with the manufacturer's recommendations in a clean, dry, well-ventilated area. Protect stored materials from rain, sunlight, and excessive heat. Keep coating materials which would be damaged by freezing at a temperature not less than 40 degrees F. Do not expose insulation board to flame or other ignition sources.
1.6 ENVIRONMENTAL CONDITIONS
a. Do not prepare materials or apply EIFS during inclement weather unless appropriate protection is provided. Protect installed materials from inclement weather until they are dry.
b. Apply sealants and wet materials only at ambient temperatures of 40 degrees F or above, unless supplemental heat is provided. The system must be protected from inclement weather and maintain this temperature for a minimum of 24 hours after installation.
c. Do not leave insulation board exposed to sunlight after installation.
1.7 WARRANTY
Furnish manufacturer's standard warranty for the EIFS. Warranty must run directly to Government and cover a period of not less than 5 years from date Government accepted the work.
PART 2 PRODUCTS
2.1 COMPATIBILITY
Provide all materials compatible with each other and with the substrate, and as recommended by EIFS manufacturer.
2.2 SHEATHING BOARD
2.2.1 Fiber Reinforced Cement Sheathing Board
a. Meet ASTM C1186, Type A
b. Meet ASTM C1325, Type A
c. Non-combustible in accordance with ASTM E136.
d. Nail Pull Resistance: No less than 120 lb when tested in accordance with
ASTM C473.
e. Thickness no less than 1/2 inch.
f. Water Absorption not to exceed 17 percent.
2.2.2 Glass Mat Gypsum Sheathing Board
a. Conform to ASTM C1177/C1177M; or.
b. ASTM C1278/C1278M, Water Resistant Exterior Type only
c. Nail Pull Resistance: No less than 120 lb when tested in accordance with
ASTM C473.
2.3 ADHESIVE
Manufacturer's standard product, including primer as required, must be compatible with substrate and insulation board to which the system is applied.
2.4 LATHING AND FURRING
Conform to ASTM C847, 2.5 lb/sqyd, self-furring, galvanized.
2.5 MECHANICAL FASTENERS
Corrosion resistant and as approved by EIFS manufacturer. Select fastener type and pattern based on applicable wind loads and substrate into which fastener will be attached, to provide the necessary pull-out, tensile, and shear strengths.
2.6 THERMAL INSULATION
2.6.1 Manufacturer's Recommendations
Provide only thermal insulation recommended by the EIFS manufacturer for the type of application intended.
2.6.2 Insulation Board
Insulation board must be standard product of manufacturer and must be compatible with other system components. Boards must be factory marked individually with the manufacturer's name or trademark, the material specification number, the R-value at 75 degree F, and thickness. No layer of insulation can be less than 3/4 inch thick. The maximum thickness of all layers must not exceed 4 inches. Insulation Board must be certified as aged, in block form, prior to cutting and shipping, a minimum of 6 weeks by air drying, or equivalent. Insulation board must be compatible with existing system.
2.7 BASE COAT
Manufacturer's standard product and compatible with other system components.
2.8 PORTLAND CEMENT
Conform to ASTM C150/C150M, Type I or II as required, fresh and free of lumps, and approved by the systems manufacturer.
2.9 REINFORCING FABRIC
Reinforcing fabric mesh must be alkali-resistant, balanced, open weave, glass fiber fabric made from twisted multi-end strands specifically treated for compatibility with the other system materials, and comply with ASTM E2098/E2098M and as recommended by EIFS manufacturer.
2.10 FINISH COAT
Manufacturer's standard product conforming to the requirements in the paragraph on Sub-Component Requirements and Tests. For color consistency, use materials from the same batch or lot number.
2.11 SEALANT PRIMER
Non-staining, quick-drying type recommended by sealant manufacturer and EIFS manufacturer.
2.12 ACCESSORIES
Conform to recommendations of EIFS manufacturer, including trim, edging, anchors, and expansion joints. All metal items and fasteners to be corrosion resistant.
2.13 JOINT SEALANT
Non-staining, quick-drying type meeting ASTM C920, as Type S or M, minimum Grade NS, minimum Class 25 and compatible with the finish system type and grade, and recommended by both the sealant manufacturer and EIFS
2.14 BOND BREAKER
As required by EIFS manufacturer and recommended by sealant manufacturer and EIFS manufacturer.
2.15 BACKER ROD
Closed cell polyethylene free from oil or other staining elements and as recommended by sealant manufacturer and EIFS manufacturer. Do not use absorptive materials as backer rod. Size the backer rod 25 percent larger than the width of the joint.
PART 3 EXECUTION
3.1 EXAMINATION
Examine substrate and existing conditions to determine that the EIFS can be installed as required by the EIFS manufacturer and that all work related to the EIFS is properly coordinated. Surface must be sound and free of oil, loose materials or protrusions which will interfere with the system installation. If deficiencies are found, notify the Contracting Officer and do not proceed with installation until the deficiencies are corrected. The substrate must be plane, with no deviation greater than 1/4 inch when tested with a 10 foot straightedge.
Determine flatness, plumbness, and any other conditions for conformance to manufacturer's instructions.
3.2 SURFACE PREPARATION
Prepare existing surfaces for application of the EIFS to meet flatness tolerances and surface preparation according to manufacturer's installation instructions.
Provide clean surfaces free of oil and loose material without protrusions adversely affecting the installation of the insulation board. For adhesively attached EIFS, existing deteriorated paint must be removed. Due to substrate conditions or as recommended by the system manufacturer, a primer may be required. Apply the primer to existing surfaces as recommended by the manufacturer. Use masking tape to protect areas adjacent to the EIFS to prevent base or finish coat to be applied to areas not intended to be covered with the EIFS. The Contractor must not proceed with the installation until all noted deficiencies of the new substrate are corrected.
3.3 INSTALLATION
Install EIFS as indicated, comply with manufacturer's instructions except as otherwise specified. Submit manufacturer's standard printed instructions for the installation of the EIFS; include requirements for condition and preparation of substrate, installation of EIFS, and requirements for sealants and sealing. Also include detailed finish repair procedures and information regarding compatibility of sealants with base and finish coatings. Specifically, include all manufacturer recommended provisions regarding flashing and treatment of wall penetrations.
Any materials that show visual evidence of biological growth due to the presence of moisture must not be installed on the building project.
3.3.1 Sheathing Board
Edges and ends of boards must be butted snugly with vertical joints staggered to provide full and even support for the insulation. Provide support at both vertical and horizontal joints. Attach sheathing board. Place fasteners sufficiently close to support imposed loads, but not more than:
a. Maximum of 8 inches apart on each supporting stud
b. Maximum of 16 inches apart horizontally and 8 inches apart vertically.
3.3.2 Insulation Board
Unless otherwise specified by the system manufacturer, place the long edge horizontally from level base line. Stagger vertical joints and interlock at corners.
Butt joints tightly. Provide flush surfaces at joints. Align drainage channels of integral drainage system or provide polypropylene drainage lath space to provide a path for any water weeped from behind the insulation to escape wall construction. Joints of insulation must be butted tightly. Surfaces of adjacent insulation boards must be flush at joints. Gaps greater than 1/16 inch between the insulation boards must be filled with slivers of insulation. Uneven board surfaces with irregularities projecting more than 1/16 inch must be rasped in accordance with the manufacturer's instructions to produce an even surface.
Attach insulation board as recommended by manufacturer. The adhered insulation board must be allowed to remain undisturbed for 24 hours prior to proceeding with the installation of the base coat/reinforcing mesh, or longer if necessary for the adhesive to dry. However, do not leave insulation board exposed longer than recommended by insulation manufacturer.
3.3.2.1 Mechanically Fastened Insulation Boards
Fasten with manufacturer's standard corrosion resistant anchors, spaced as recommended by manufacturer, but not more than 2 feet horizontally and vertically.
3.3.2.2 Adhesively Fastened Insulation Boards
Apply insulation board using adhesive spread with a notched trowel to the back of the insulation boards in accordance with the manufacturer’s instructions.
3.3.3 Base Coat and Reinforcing Fabric Mesh,
3.3.3.1 Class PB Systems
Allow the adhered insulation board to dry for 24 hours, or longer if necessary, prior to proceeding with the installation of the base coat/reinforcing fabric mesh.
Install reinforcing fabric in accordance with manufacturer's instructions. Mix base coat in accordance with the manufacturer's instructions and apply to insulated wall surfaces to the thickness specified by the system manufacturer and provide any other reinforcement recommended by EIFS manufacturer. Trowel the reinforcing fabric mesh into the wet base coat material. Fully embed the mesh in the base coat. When properly worked-in, the pattern of the reinforcing fabric mesh must not be visible. Provide diagonal reinforcement at opening corners.
Back-wrap or edge wrap all terminations of the EIFS. Overlap the reinforcing fabric mesh a minimum of 2.5 inches on previously installed mesh, or butted, in accordance with the manufacturer’s instructions.
3.3.3.2 Class PM Systems
Mechanically fasten reinforcing fabric mesh to the insulated wall using the type and spacing of fasteners specified in the manufacturer’s instructions. Provide diagonal reinforcement at opening corners. Mix base coat in accordance with manufacturer's instructions. Apply base coat in accordance with manufacturer's instruction to provide a complete, tight coating of uniform thickness as specified by the manufacturer. Cover all fiberglass reinforcing fabric, including at back wrapped areas at panel joints and at fasteners.
3.3.4 Finish Coat
The base coat/reinforcing mesh must be allowed to dry a minimum of 24 hours prior to application of the finish coat. Surface irregularities in the base coat, such as trowel marks, board lines, and reinforcing mesh laps, must be corrected prior to the application of the finish coat. Apply and level finish coat in one operation.
Obtain final texture by trowels, floats, or by spray application as necessary to achieve the required finish matching approved [sample] [mock-up installation].
Apply the finish coat to the dry base coat maintaining a wet edge at all times to obtain a uniform appearance. The thickness of the finish coat must be in accordance with the system manufacturer’s current published instructions. Apply finish coat so that it does not cover surfaces to which joint sealants are to be applied.
3.4 JOINT SEALING
Seal EIFS at openings as recommended by the system manufacturer. Apply sealant only to the base coat with EIFS Manufacturer's color coating. Do not apply sealant to the finish coat.
3.4.1 Surface Preparation, Backer Rod, and Primer
Immediately prior to application, remove loose matter from joint. Ensure that joint is dry and free of finish coat, or other foreign matter. Install backer rod. Apply primer as required by sealant and EIFS manufacturer. Check that joint width is no less than 0.5 inch for perimeter seals and 0.75 inch for expansion joints. The width must not be less than 4 times the anticipated movement. Check sealant manufacturer's recommendations regarding proper width to depth ratio.
3.4.2 Sealant
Do not apply sealant until all EIFS coatings are fully dry. Apply sealant in accordance with sealant manufacturer's instructions with gun having nozzle that fits joint width. Do not use sealant that has exceeded shelf life or cannot be discharged in a continuous flow. Completely fill the joint solidly with sealant without air pockets so that full contact is made with both sides of the joint. Tool sealant with a round instrument that provides a concave profile and a uniformly smooth and wrinkle free sealant surface. Do not wet tool the joint with soap, water, or any other liquid tooling aid. During inclement weather, protect the joints until sealant application. Use particular caution in sealing joints between window and door frames and the EIFS wall and at all other wall penetrations. Clean all surfaces to remove excess sealant.
3.5 FIELD QUALITY CONTROL
Throughout the installation, the Contractor must establish and maintain an inspection procedure to assure compliance of the installed EIFS with Contract requirements. Work not in compliance must be removed and replaced or corrected in an approved manner.
3.6 CLEANUP
Upon completion, remove all scaffolding, equipment, materials and debris from site. Remove all temporary protection installed to facilitate installation of EIFS.
SECTION 08 71 00
FINISH HARDWARE
A. This section covers all finish door hardware and related items.
B. Should specific items of hardware not specified be required for completion of the work, the contractor shall furnish such items of the type and quality for approval by the engineer.
PART 2 – PRODUCTS
A. INTERIOR DOOR:
1. Door Knob: Schlage F51 V FLA 505 or equal
PART 3 – EXECUTION
A. Install hardware in accordance with manufacturer’s instructions and applicable codes.
B. Use templates provided by hardware item manufacturer.
C. Do not install surface mounted items until finishes applied to substrate are complete.
D. Mounting heights for hardware from finished floor to center line of hardware item:
1. Comply with the Architectural Barriers Act Standards.
E. Adjust hardware for smooth operation.
F. Clean finished hardware per manufacturer’s instructions after final adjustments have been made. Replace items that cannot be cleaned to manufacturer’s level of finish quality at no additional cost.
G. Do not permit adjacent work to damage hardware or finish.
DIVISION 9
SECTION 09 21 16
GYPSUM BOARD ASSEMBLIES
PART 1 - GENERAL
A. SECTION INCLUDES
1. Gypsum wallboard.
B. REFERENCES
1. ASTM C 1396 - Standard Specification for Gypsum Wallboard.
2. ASTM C 475 - Standard Specification for Joint Compound and Joint Tape for
Finishing Gypsum Board; 1994.
3. ASTM C 514 - Standard Specification for Nails for the Application of Gypsum
Board; 1996.
4. ASTM C 840 - Standard Specification for Application and Finishing of Gypsum
Board; 1996.
5. ASTM C 1002 - Standard Specification for Steel Drill Screws for the Application of Gypsum Panel Products or Metal Plaster Bases; 1996.
6. GA-201 - Using Gypsum Board for Walls & Ceilings; Gypsum Association;
1990.
7. GA-216 - Application and Finishing of Gypsum Board; Gypsum Association;
1996.
PART 2 - PRODUCTS
A. MANUFACTURERS - GYPSUM BOARD SYSTEM
1. Gypsum board at walls shall be gypsum board by CertainTeed M2Tech Mold
Resistant Moisture Resistant Regular Drywall Panel or equal. Edge shall be tapered with round edge.
B. GYPSUM BOARD MATERIALS
1. Mold Resistant Moisture Resistant Gypsum Wallboard: ASTM C1396.
2. Thickness: ½ inch.
C. ACCESSORIES
1. Joint Materials: ASTM C 475 and as recommended by gypsum board manufacturer for project conditions.
2. Textured Finish Materials: Latex-based compound; plain.
3. Screws: ASTM C 1002; self-drilling type; cadmium-plated for exterior locations.
4. Nails: ASTM C 514.
PART 3 - EXECUTION
A. EXAMINATION
1. Verify that project conditions are appropriate for work of this section to commence.
B. GYPSUM BOARD INSTALLATION
1. Comply with ASTM C 840. Install to minimize butt end joints, especially in highly visible locations.
2. Single-Layer Non-Rated: Gypsum Sheathing Board Apply gypsum sheathing board either horizontally or vertically. Butt joints and locate over the centerlines of supports. Stagger vertical joints and abut sheet closely to frames of openings. Nail sheathing with 11 gage, 3/8 inch head, zinc-coated nails 1-1/2 inches long for 1/2 inch sheathing and 1-3/4 inches long for 5/8 inch sheathing, spaced 3/8 inch minimum from edges. Screw sheathing with 1-1/4 inch long drywall screws for 1/2 inch sheathing and 1-5/8 inch long drywall screws for 5/8 inch sheathing. Provide 2 by 4 blocking for horizontal edges of 4 foot wide panels not otherwise supported.
3. Install gypsum board in most economical direction, with ends and edges occurring over firm bearing.
4. Installation on Wood Framing: For rated assemblies, comply with requirements of listing authority. For non-rated assemblies, install as follows: Single-Layer Applications: Screw attachment.
C. INSTALLATION OF TRIM AND ACCESSORIES
1. Corner Beads: Install at external corners, using longest practical lengths.
2. Edge Trim: Install at locations where gypsum board abuts dissimilar materials and as indicated.
D. JOINT TREATMENT
1. Tape, fill, and sand exposed joints, edges, and corners to produce smooth surface ready to receive finishes.
2. Feather coats of joint compound so that camber is maximum 1/32 inch.
E. TEXTURE FINISH
1. All gypsum board shall have a light “orange peel” finish.
SECTION 09 91 00
PAINTING
A. This section includes all interior and exterior paint and related items. This includes all material and labor required to paint the following new interior and exterior surfaces included in this contract.
B. Quality Assurance
1. All paints, enamels, varnishes, and stains shall be furnished in original, unopened containers bearing a label to include the manufacturer's name, type of paint or stain, manufacturer's stock number, color, VOC content, SDS, and instructions for surface preparation and application.
C. Environmental Requirements
1. Comply with the manufacturer's recommendations as to environmental conditions under which coating and coating system can be applied.
2. Do not apply stain or paint in areas where dust is being generated.
3. Storage: Store and dispose of solvent-based materials, and materials used with solvent-based materials, in accordance with requirements of local authorities having jurisdiction.
4. Store materials in an area that is within the acceptable temperature range, per manufacturer’s instructions. Protect from freezing.
PART 2 – PRODUCTS
A. PRIMER
1. Paint chosen is a paint and primer in one.
B. PAINT & STAIN
1. Paint Type #1 (gypsum board) shall be Sherwin Williams Duration Home
Interior Acrylic Latex Paint:
a. COLOR: Extra white or as approved by the COR.
2. Paint Type #2 (exterior) shall be Sherwin Williams Duration Exterior Acrylic Latex or as approved by the COR.
a. COLOR: Match existing
3. Paint Type #3 (bathroom floor) shall be Rust-Oleum EpoxySheild epoxy paint or as approved by the COR.
a. COLOR: Gray or as approved by the COR.
B. Conform to the coating specifications and standards referenced in PART 3. Submit product data sheets for specified coatings and solvents. Provide preprinted cleaning and maintenance instructions for all coating systems.
C. Submit Manufacturer's Instructions on Mixing: Detailed mixing instructions, minimum and maximum application temperature and humidity, potlife, and curing and drying times between coats.
PART 3 – EXECUTION
A. Preparation of Surfaces
1. All existing signage shall be removed and remounted or protected from coating being applied to adjacent surfaces.
2. Remove vegetation from surfaces.
3. Prepare surfaces as necessary to receive stain or paint as specified. Retouch shop coats and prime coats as necessary.
4. Fill, sand, and prime as necessary to provide a suitable surface for stain or paint.
5. Clean surfaces to be stained or painted. Exterior spaces in which staining or painting will be done shall be pressure washed clean and dust-free.
6. Apply protective cover to areas not to be pressure washed. Examples include covering electrical supplies with plastic cover and placing water- absorbent socks at strategic locations to prevent seepage.
7. Adjust water pressure and temperature to the appropriate amount to provide optimal cleaning power without damaging the property. For instance, different settings must be applied for pressuring washing a siding vs. wooden decks.
8. Contractor shall provide a detergent that cleans tough stains if required.
9. Remove soil, prints, stains, and adhered materials prior to beginning of work.
10. Clean rusty metal surfaces as per SSPC requirements. Use solvent, mechanical, or chemical cleaning methods to provide surfaces suitable for painting.
11. Testing: Due to the wide variety of substrates, preparation methods, application methods and environments, contractor shall test the product in an inconspicuous spot for adhesion and compatibility prior to full-scale application.
12. Meet requirements of other portions of Specifications for preparation of specific items.
13. Maintenance painting will frequently not permit or require complete removal of all old coatings prior to repainting. However, all surface contamination such as oil, grease, loose paint, mill scale, dirt, foreign matter, rust, mold, mildew, mortar, efflorescence, and sealers must be removed to assure sound bonding and tightly adhering the surfaces.
14. Glossy surfaces of old paint films must be clean and dull before repainting.
Thorough washing with an abrasive cleanser will clean and dull in one operation, or, wash thoroughly and dull by sanding.
15. Spot prime any bare areas with an appropriate primer.
B. Application
1. All interior painting will require two coats paint.
2. All exterior trim shall receive two coats stain minimum (no primer) but shall be sufficient to cover the existing paint and have a uniform color and finish.
3. No exterior painting shall be done in rainy, damp, or frosty weather or until the surface is thoroughly dry.
4. No paint shall be applied when the temperature is below 40 degrees F or when the temperature is likely to be reached within 48 hours.
5. No paint shall be applied when the temperature is less than 5 degrees F above the dew point.
6. All paint shall be applied in accordance with the manufacturer's recommendations unless otherwise directed.
7. All coats shall be thoroughly dried before applying succeeding coats with sanding between coats where necessary. Comply with manufacturer's recommendation for drying time between succeeding coats.
8. Finish coats shall be smooth, free of brush marks, streaks, laps, or pole of paints, and skipped or missed areas.
9. Regardless of number of coats specified, apply as many coats as necessary for complete hide and uniform appearance.
10. Keep brushes, rollers, and spraying equipment clean, dry, free from contaminates, and suitable for the finish required.
11. Make edges of paint adjoining other materials or colors stain and sharp with no overlapping.
C. Cleaning
1. Touch up and restore finish where damaged.
2. Remove spilled, splashed, or splattered paint from all…