Attachment 001 Statement of Work.pdf

PDF 415 KB Posted

Attached to
PBA Mobile Boiler Federal contract opportunity
Solicitation number
W519TC-23-Q-0269
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

This statement of work details the requirements for a 2023 mobile boiler purchase for Pine Bluff Arsenal. The contractor shall furnish a mobile boiler unit mounted on a trailer including a boiler, feedwater system, and controls. The unit must be sized at 150 BHP with a steam capacity of 5,170 lbs/Hr and design pressure of 150 psi, fueled by natural gas with a maximum input of 6,300,000 BTU/Hr. The feedwater system requires a minimum capacity of 5,175 lbs/Hr including a 150-gallon tank, steam pre-heater, and 150,000 grain water softener. Controls must include a flame safeguard, flame scanner, and specified safety devices. The mobile unit and all associated equipment must be installed outside building 33-530 and connected to existing steam lines by the contractor within five months of contract award. The related federal contract opportunity is solicitation number W519TC-23-Q-0269 for this mobile boiler purchase for Pine Bluff Arsenal through the Department of the Army Materiel Command Contracting Command Rock Island Arsenal.

View the file

Other files for this federal contract opportunity

Other files attached to PBA Mobile Boiler, newest first.
File Type Posted
W519TC-23-Q-0269-0003 Released.pdf PDF
W519TC-23-Q-0269-0002 Released.pdf PDF
W519TC-23-Q-0269-0001.pdf PDF
Attachment 003 Contract Data Requirements (CDRL).pdf PDF
Attachment 002 W519TC-23-Q-0269 - PRICE MATRIX.xlsx XLSX spreadsheet
W519TC-23-Q-0269 Released.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: 8/24/2023 Project Name: 2023 Mobile Boiler Purchase

Subject: Scope of Work

GENERAL STATEMENT OF WORK

The scope of work under this contract is to provide Pine Bluff Arsenal (PBA) with one (1) mobile boiler unit that will be installed outside building 33-530. The mobile boiler shall be a package unit mounted on a trailer to include a boiler, feedwater system, and controls. The mobile boiler unit shall be tied into existing steam lines outside building 33-530. The work to be performed under this specification consists of furnishing all materials, equipment, supplies, labor and transportation.

SCOPE OF WORK:

1. Contractor shall furnish all materials, labor, equipment and supplies necessary to design and construct equipment to meet the scope and intent of this specification.

2. Contractor shall deliver, unload, and unpack all equipment.

3. Contractor shall perform all utility tie-ins to existing utilities. The existing utilities consist of: 480 V, 3-Phase power, potable water, and natural gas. Contractor shall perform all required adjustments to the boiler.

4. The boiler size shall be 150 BHP. The steam capacity shall be as a minimum 5,170 lbs/Hr. The boiler design pressure shall be 150 psi. The fuel for the burner shall be natural gas with a max input of 6,300,000 BTU/Hr. The blowdown separator shall have a capacity range of 50-400 BHP and a 150 psi design pressure. The blowdown separator shall have a l" thermostatic tempering valve aftercooler and 6" 150# flange for the vent and the drain. Contractor shall provide inspection and permitting by the state of Arkansas.

5. The feedwater system shall have a minimum capacity of 5,175 lbs/Hr. the tank shall be made of steel and be at a minimum 150 gallons. The system shall have a steam pre-heater. The makeup range shall be from O to 100%. The water softener shall have a metered type regeneration and have a minimum capacity of 150,000 grains.

6. The burner management controls shall consist of a flame safeguard and a flame scanner. The safeties shall consist of primary low water cutoff, water level pump controller, secondary low water cut off, water level visual indicator, pressure operating control, pressure modulating control, and high limit pressure control. Fuel delivery and control shall consist of a natural gas electric shutoff and natural gas vent valve. The unit shall have a minimum of two emergency cutoff switches with one on the interior and one on the exterior. The container shall contain a minimum of 5 two bulb vapor-proof LED lights 48" long with a 3-way switch at the front and rear. The container shall have an exhaust fan with fan control. The exterior power feed shall be a cam-lock plate 460v/60Hz/3ph. The electrical distribution shall be NEMA 1 panels.

7. Boiler shall have a minimum heating surface area of 700 sq. ft. and a maximum surface area of 800

sq. ft.

8. The container shall be a 40' ISO shipping container with tread plate floor over the ISO flooring. The container shall be mounted on a two axle minimum 40' ISO container chassis.

CONDITIONS:

a. The contractor shall provide all materials, equipment, tools and labor for the execution of this contract. Contractor shall be responsible for loading and unloading of equipment, to include forklift or other equipment, operator and labor.

b. Changes or deviations will be submitted in writing to the contracting officer for approval or rejection.

c. Any alteration to the project shall be approved by the Contracting Officer prior to execution and at the expense of the contractor.

d. Design engineering drawings, software and any other documents including editable copy in AutoCAD developed and submitted to the government as part of this contract become the property of the U.S. Government. The government will have the right to reproduce and subsequently edit any of these documents and will reserve the right to procure parts, components or the entire system from any source capable of producing it.

e. Project shall be completed within 5 months of contract award.

INSTALLATION, TRAINING, AND CLEAN UP: The Contractor shall be responsible for installation of equipment to include training, setup, and final adjustments as needed. The Contractor shall provide the Contracting Officer (KO) a project schedule within ten (10) calendar days after award of contract. The Schedule shall contain all phases of fabrication, installation, training, and start-up. Training at the installation site shall be conducted with four or more people attending. Training shall cover equipment operations, maintenance, and systems trouble-shooting. Upon completion, the entire area shall be cleaned of all debris produced by installation of equipment.

SERVICE MANUALS AND DRAWINGS: Concept drawings and available manufacturer's literature shall be furnished to the KO three (3) business days prior to design review. As-built drawings shall be provided to the KO prior to instillation. All drawings shall be provided as both hard copy and digital format.

Drawings shall be no larger than "D" (22" X 34") in size and digital format in AutoCAD (*.dwg). Upon completion of installation one copy of Maintenance and Operation manual with all drawings shall be submitted to the KO for approval. All manuals and drawings shall be supplied and approved before training and final run-off. The contractor shall furnish two (2) maintenance and operating manuals for all equipment installed under this contract, and one copy in digital format (CD media) in Microsoft Word. These manuals shall be indexed and tabbed, with a hard cover binder and label, to include a list of all replacement parts.

Parts list shall include all information required to purchase the components from the manufacturer or a representative vendor and shall include the list price at the time of purchase. A complete reproducible set of drawings and one copy of those drawings in digital form (CD media) must be AutoCAD (*.dwg) format.

Drawings and schematics of the equipment and controls shall be furnished before acceptance is complete.

Contractor shall furnish two (2) copies of preventive maintenance schedules and one copy in digital format.

The schedule will be broken down into daily, weekly, monthly, semi-annual and annual checks or services that should be performed on the equipment, along with any other frequency that is required. Also to be included shall be a recommended spare parts list with recommended stocking levels, sufficient to properly maintain the equipment.

An estimate of the proposed product's reliability expressed in terms of Mean Time between Failures (MTBF) shall be required. This estimate shall be based upon actual experience with equipment produced by the prospective supplier and must be supported by raw data. Unit downtime for preventive maintenance (PM), routine scheduled and nonscheduled service, repairs and adjustments shall not exceed 1% of normal operating time. Rates for frequency of PM shall not exceed one service day per quarter. Man-hour expenditures per service must not exceed 1% of normal operating time. Maintenance complexity shall not require more than two journeyman grade millwrights or more than standard hand tools for each service.

DESIGN AND CONTRUCTION: All equipment shall be new and in unused condition. Emphasis shall be placed on simplicity of operation and reliability. English and metric fasteners will not be mixed.

Contractor shall employ use of quick release fasteners for non-structural guards, inspection and maintenance access covers. The equipment shall be clean, well made, and free from any and all product defects, which may affect appearance or serviceability. All metal surfaces (other than stainless steel or aluminum) shall be primed and painted with the manufacturer's standard color and finish. Equipment will be installed to provide access to all points where maintenance is required.

All electrical work shall meet the requirements of the latest revision of the National Electric Code (NEC), and Part 1910, title 29 of the Code of Federal Register (OSHA). Wiring shall be stranded copper with THHN insulation for AWG No. 16 and larger. Full size ground wire will be pulled with each circuit (conduit shall not be used as a ground). Terminal strips shall be used in the panels for all wire entering or exiting the panel. Also all wires shall be labeled at both ends of termination and the terminal strips shall be labeled.

The contractor shall use wiring ducts and wire ties in panels where required in order to maintain an organized panel. All necessary step down transformers required for operation of single-phase controls and equipment shall be rated at a minimum of 150 percent of full load current.

All push buttons, indicators, control points, etc. shall be identified with commercially printed legend plates.

All disconnect enclosures, junction boxes, panel boards and all other enclosures shall be permanently marked with 1/2-inch high letters showing function, voltage and phase. The letters shall be marked in accordance with OSHA standards.

Like component parts, such as switches, starters, etc., shall be interchangeable to provide ease m maintenance and reduce spare parts requirements.

All equipment provided by the contractor such as tanks, vessels, valves, etc. shall be designed to meet or exceed applicable ASME, ASTM, and OSHA requirements.

LOCATION OF WORK: The local work covered by this specification is to be performed at Pine Bluff Arsenal. Postal address is Pine Bluff, Arkansas 71602-9500. Carload freight address is Baldwin, Arkansas on either the Union Pacific R.R. or the St. Louis Southwestern R.R. The Arsenal is located off Highway 65, Exit 32, about 12 miles northwest of Pine Bluff and 35 miles southeast of Little Rock. The exact job start and stop locations will be verified in place.

ORDER AND SCHEDULING OF WORK: When performing work on Pine Bluff Arsenal the Contractor shall adhere to the normal duty hours of the Arsenal which are 6:30 AM to 4:00 P.M., Monday thru Thursday. No work will be permitted on Government holidays, days that are observed in lieu of Government holidays and days that are declared non-work days by the Commanding Officer of Pine Bluff Arsenal or officials of higher headquarters. Deviations from the above must be approved in writing by the Contracting Officer at least two working days prior to the proposed deviation.

DISPOSAL OF EXCESS REMOVED MATERIALS: All salvaged rubble, material, and equipment will remain the property of the Government

a. Uncontaminated rubble, materials, and equipment, will be delivered to an erosion control area as directed by the Contracting Officer. Materials and equipment will be placed in "like material" stacks when delivered to the Property Disposal Yard.

b. Contaminated rubble, materials, and equipment will be placed in containers and delivered to a materials holding area as directed by the Contracting Officer.

SAFETY REQUIREMENTS:

a. General: Limited emergency first aid, to prevent loss of life or limb, is available for contractor personnel at the U.S. Army Health Clinic for injuries sustained in the performance of their duties.

This service is normally available from 7:30 A.M. to 4:00 P.M., Monday through Friday. For life threatening emergencies after duty hours, contractor personnel will notify the Medical Officer of the day. For any other injury, contractor personnel should go to Jefferson Regional Medical Center or see their private physician. Use of this Health Clinic constitutes compliance with the First Aid Requirements of the Corps of Engineers Manual EM 385-1 as referenced in, FAR 52.236-13

"Accident Prevention". The requirements of Department of Labor, Occupational Safety and Health Administration (OSHA) Standard 29 CFR 1910 or EM 385-1, General Safety Requirements, whichever is the most stringent, will be followed.

b. No fire or flame producing device will be used on the Arsenal without prior approval of the Contracting Officer. The Contractor shall also be required to obtain a bum permit from the Fire Department. This includes all forms of welding.

c. Smoking will not be permitted in the production area, except in designated areas.

d. Equipment will be maintained in a safe operating condition and a fire safe condition at all times. It shall be stored in a designated area, approved by the Contracting Officer.

e. Hoists, cranes, derricks, or similar equipment shall not be operated where it is possible to bring any part of the machine, suspended load, or lines closer than ten feet to power lines unless the lines have been de-energized and grounded.

f. Work will be performed in a manner which will allow the passage of traffic, especially emergency vehicles, at all times. Where only one lane is open to traffic, adequate warning signs and flagmen will be used.

g. All personnel working at Pine Bluff Arsenal must have a safety briefing given by Safety personnel prior to beginning work.

h. Contractor shall provide the names and personnel data on all employees scheduled for this contract work at PBA, to the Contracting Officer at least one week prior to actual work. This is necessary for proper identification and issue of security pass to each employee for access to PBA job site.

Environmental Requirements:

1. Compliance with Environmental Laws and Regulations: Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement, or Status-of-Forces Agreement. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR).

2. Compliance with Green Procurement Requirements: Contractor shall follow Federal EPA Comprehensive Procurement guidelines (www.epa.gov/cpg) and Army Contracting Command Quick Guide (https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick-Guide-for-Sustainable-Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials; recyclable materials; materials that are resource-efficient; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.

3. Compliance with License and Certification Requirements: Contractor shall obtain all license and certification required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specification of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations shall be considered a contract deliverable upon award.

4. Notification of Federal and State Regulators: Contractor shall immediately notify the Designated Government Representative (DGR) and COR of the arrival on site of any Federal, State, and/or DoD environmental regulator or enforcement agent and/or the receipt of any correspondence from a Federal or State environmental agency.

5. Inspections of Work Sites: Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation. Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements. If an inspection is conducted, it will not stop or disrupt ongoing contract activities.

The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality.

6. Reporting Noncompliance: Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR and DGR.

7. Verification of National Environmental Policy Act Documents: Contractor shall obtain from the COR or DGR, a copy of AMC's National Environmental Policy Act Policy and 32 CFR 651 which addresses actions to be taken by contractor. These documents include but is not limited to the analysis-associated decision document of an Environmental Impact Statement and Record of Decision; Environmental Assessment and Finding of No Significant Impact or Notice to Proceed; or Record of Environmental Consideration on the proposed contract actions prior to commencement of such actions.

8. Conformance with Environmental Management System: Contractor shall take the necessary actions to identify, monitor, and control those contract operations and activities that pose risk of contamination, or can negatively impact the natural and/or human environment.

9. Generation of Solid Waste: Contractor shall remove from the installation and dispose of all solid waste generated, which cam1ot be recycled to an approved and permitted off-post disposal facility.

9.1 Contractor shall make every effort to divert construction, demolition debris, and all other solid waste to comply with the Army Integrated Solid Waste Management Policy.

9.2 Prior to removing any waste from the installation for disposal, the Contractor shall coordinate with the installation Qualified Recycling Program (QRP) Manager, DGR, and COR to arrange for recyclable materials to be removed and diverted from the waste stream.

9.3 Submit in writing the quantities of waste removed and recycled to the DGR and/or COR on a monthly basis. The submittal shall include the date of disposal/recycling, the disposal/recycling facility, the types of material disposed/recycled and the quantities of materials disposed/recycled by weight.

9.4 The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.

9.5 The Contractor shall make maximum effort to reduce and prevent waste.

10. Generation of Hazardous Waste: Contractor shall assign all hazardous waste management responsibilities to the appointed ECD. Contractor shall contact the DGR and/or COR to obtain technical assistance from the Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous waste storage and disposal requirements. Contractor shall properly profile all waste generated as part of this contract to determine if any waste is hazardous waste as defined by 40 CFR. Contractor shall accumulate hazardous waste prior to disposal shipment in a satellite accumulation point at or near the point of generation or in a less-than-90-day site, in accordance with Federal, State, Army, and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement or Status-of-Forces Agreement. The Contractor shall properly package the hazardous waste and complete the hazardous waste manifest, then take the manifest to DGR for approval and signature prior to removing any hazardous waste from the installation.

Contractor shall contact DGR to obtain the installation's hazardous waste EPA ID number for the hazardous waste manifest. The Contractor shall notify the DGR 24 hours prior to removing any hazardous waste from the installation. The contractor shall remove and dispose of manifested hazardous waste generated by contract activities from the installation, to an approved off-post permitted hazardous waste disposal facility. The DGR shall assist contractors with profiling their waste upon request.

11. Use of Hazardous Materials: Contractor shall assign all hazardous materials management responsibilities to the appointed ECD. Contractor shall contact the DGR or COR to obtain technical assistance from Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous material storage, issue, use, and disposal requirements. Contractor shall submit to the COR and/or DGR a hazardous material inventory. The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed 180 consecutive days. The inventory list will contain the hazardous material type and maximum quantities of materials anticipated to be stored on-site. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. The Contractor shall maintain copies of Safety Data Sheets for all hazardous materials used and stored on-site during performance of the contract. Contractor shall not supply or deliver any hazardous materials or chemicals to an installation that are listed on EPA toxic chemical list without prior written approval from DGR and/or COR.

12. Prevention of Storm Water Pollution: The Contractor shall perform, track, participate, implement, and comply with storm water pollution prevention minimwn control measures, protocols, and best management practices (BMP) and ensure that water quality standards are not violated in accordance with all regulations and policies as applicable to the Pollutant Discharge Elimination System general permit requirements.

Applicable permits include:

1. The installation's Small Municipal Separate Storm Sewer System (MS4) Pennit;

2. The Multi-Sector General Permit for Storm Water Discharges Associated with Industrial Activities

(MSGP); and,

3. All Construction Activity Stonn Water permits minimum control measures include, but not limited to:

• Public Education and Outreach on Storm Water Impacts

• Public Involvement and Participation

• Illicit Discharge Detection and Elimination

• Construction Site Storm Water Run-off Control

• Post Construction Storm Water Management in New Development and Redevelopment

• Pollution Prevention/Good Housekeeping for Municipal Operations Contractors will comply with the MSGP permit when the activity is identified as a permitted industrial activity. BMPs include, but are not limited to:

• Practicing spill prevention and good housekeeping.

• Installing and managing erosion and sediment control.

• Meeting the requirements of the MS4 permit.

• Contractors will obtain permit coverage for construction activities disturbing over one acre of land (total acreage is cumulative across all portions of the project). BMPs include, but are not limited to:

• Preparing and implementing a site-specific Storm Water Pollution Prevention Plan (SWPPP) as outlined in the permit and prior to any soil disturbance.

• Installing and managing erosion and sediment control.

• Make available, upon request, permit associated documentation.

• Practicing spill prevention and good housekeeping.

• Meeting the requirements of the MS4 permit.

• Schedule inspections and provide corrective actions for noted deficiencies.

13. Storm Water Management Low Impact Design/Development (LID): The Contractor shall perform, track, participate, implement, and comply with Section 438 of the Energy Independence and Security Act;

Executive Order 13514; and the DOA memorandum (2010) for full implementation of low impact design/development (LID) techniques to restore predevelopment hydrology to the maximum extent technically feasible for both new and renovation construction projects regardless of size. In support of LID, Contractors will adhere to installation landscape codes and the guidance found in the Installation Design Guide concerning Low Impact Design/Development for storm water management. The following LID practices include, but are not limited to:

• Restoring predevelopment hydrology to the maximum extent technically feasible

• Promoting natural removal of pollutants such as nutrients, oil and grease, and sediments from storm water

• Managing rainfall at the point where it falls

• Meeting the requirements of the MS4 permit

• Important Note: Utilization of permanent retention/detention ponds is prohibited without authorization from the Installation Planning Division.

14. Use of Pesticides: Contractor shall submit the type and quantity of regulated pesticides to be applied, the application purpose, and location to the DGR and COR for approval 10 working days prior to the initial application. The Contractor shall submit the actual quantities applied (DD1532 or equivalent) to the DGR and COR within 2 working days (48 hours) after each approved application. The Contractor shall utilize Integrated Pest Management (1PM) technology and procedures in strict compliance with all applicable Federal, State, Army, and installation regulations, to include the installation's integrated pest management plan. Pesticide applicators shall be certified and licensed in accordance with the State where work is being performed and/or Department of Defense regulations. The Contractor shall provide evidence of personnel licenses and certifications to the Contracting Officer and the DGR prior to the initial application of pesticides. Only those pesticides registered with the US Environmental Protection Agency (EPA) and approved by Army Materiel Command Pest Management Consultant shall be utilized and then only in strict accordance with product labeling. The installation reserves the right to prohibit and limit the amount and type of pesticides used.

15. Protection of Work Site Resources: Contractor shall confine all activities to areas defined by the drawings and specifications. Prior to the beginning of any work, the Contractor shall identify any land resources to be preserved within the work area. Except in areas indicated on the drawings or specified to be cleared, the Contractor shall not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms. The Contractor shall provide effective protection for land and vegetative resources at all times. Prior to site clearing and grubbing, the Contractor shall coordinate harvesting of saleable timber with the DGR and/or COR. Contractor shall notify the DGR and/or COR if any trees are required to be disposed or removed. The Contractor is not authorized to remove or dispose of any tree greater than 6 inches in diameter unless permission has been granted in writing by the DGR or COR.

16. Prevention of Spills: Contractor shall adopt the installation's Spill Prevention Control and Countermeasures Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. In case of a spill, the person in control of the spill site or their designated representative shall take appropriate action to protect workers and bystanders; contain the spill (if it can be done safely); secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department).

17. Protection of Sensitive Areas: Contractor shall comply with all installation designated sensitive and/or off-limit area restrictions. Sensitive areas are generally demarked indicating what activities (e.g., driving, digging, foot traffic) are prohibited. The Contractor shall also adhere to the following installation sensitive areas requirements:

17.1. Cultural Resources Sites: Do not excavate, remove, damage, or otherwise deface any archeological resource located on public lands.

17.2 Endangered Species Habitats: Do not initiate any action that may disturb, endanger, or damage to any degree the habitat of a threatened and endangered species.

17.3 Wetlands: Do not excavate or take any action that could fill or damage any wetland unless working under a project specific Corps of Engineers 404 permit. Wetlands include streams, riparian areas, bogs, marshes, and swamps.

18. Corrective Action for Noncompliance: Contractor shall when given a verbal and/or written notice of environmental noncompliance or nonconformance by the COR, take immediate corrective action. Failure or refusal to comply promptly may be grounds for the Contracting Officer to invoke the appropriate contractual remedies. This may cause all or part of the work to be stopped immediately until satisfactory corrective action has been taken.

19. Noise: Make the maximum use of low-noise emission products, as certified by the EPA. Blasting or use of explosives will not be permitted without written permission from the Contracting Officer, and then only during the designated times. Pile-driving operations shall be coordinated through the DGR and COR.

20. Mercury: Mercury is prohibited, unless specified otherwise, and with the exception of mercury vapor lamps and fluorescent lamps. Dumping of mercury-containing materials and devices such as mercury vapor lamps, fluorescent lamps, and mercury switches, in rubbish containers is prohibited. Remove without breaking, pack to prevent breakage, and transport out of the activity in an unbroken condition for disposal as directed. Immediately report to the DGR and COR instances of breakage or mercury spillage. Clean mercury spill area to the satisfaction of the Contracting Officer. Cleanup of a mercury spill shall not be recycled and shall be managed as a hazardous waste for disposal.

21. Universal Waste/ e-Waste Management: Universal waste including but not limited to some mercury containing building products such florescent lamps, mercury vapor lamps, high pressure sodium lamps, CRTs, batteries, aerosol paint containers, electrical equipment containing PCBs, and consumed electronic devices, shall be managed in accordance with applicable environmental law and installation instructions.

22. Pollution Prevention/ Hazardous Waste Minimization: Minimize the use of hazardous materials and the generation of hazardous waste. Consult with the Environmental Office for suggestions and to obtain a copy of the installation's pollution prevention/hazardous waste minimization plan for supporting waste minimization goals.

23. Anti-Terrorism and Operations Security: AT Level I Training.

All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil

Access and general protection/security policy and procedures.

Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

For contractors that do not require CAC, but require access to a DoD facility or installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

iWATCH Training The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 45 calendar days after contract award.

-End SOW-