Attachment 001 - Rev 1 SCHEDULE OF ITEMS.pdf
PDF 201 KB Posted
- Solicitation number
- 12445124B0014
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is an Attachment 001 - Rev 1 SCHEDULE OF ITEMS for the rehabilitation of the Uwharrie Hunt Camp in the National Forests in North Carolina. The work includes demolition, grading, installation of new tent pads, waterline, hydrants, ramps, bridges, and other associated site work. The total estimated cost for the base bid items is provided, along with a list of individual bid items, their method of measurement, estimated quantities, and unit and total prices. There is also a separate additive bid schedule for additional items, including a concrete ramp and steel handrail. The related federal contract opportunity is a pre-solicitation for this project, with a site visit scheduled for 07/25/2024, last day for questions on 08/01/2024, and bids due by 08/16/2024 at 12:00 ET. The project is a Total Small Business Set-Aside under NAICS code 237990 - Other Heavy and Civil Engineering Construction, with a magnitude between $25,000 and $100,000. The contract will be a firm-fixed price award to the lowest priced responsive and responsible bidder.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 001- Rev1 SCHEDULE OF ITEMS Uwharrie Hunt Camp Rehabilitation
04/17/2024
National Forests in North Carolina
PAY ITEM
NO.
DESCRIPTION
METHOD
OF
MEASURE
PAY
UNIT
EST.
QTY.
UNIT PRICE TOTAL PRICE
Mobilization and Payment/Performance Bonds LSQ LSQ 1
Site Demolition and Disposal Includes demolition of all tent pads, drinking fountains, hydrants, and stairs.
LSQ LSQ 1
Tent Pad Landscape Timbers (6"x8") Includes Rebar
CQ LF 950
Timber Stairs and Handrail CQ EA 2
Minor Excavation and Embankment
Includes excavation and embankment for rebuilt tent pads, and fine grading of relocated tent pads.
LSQ LSQ 1
Placement of 4" NCDOT ABC AQ TON 80
Placement of 2" #78 Stone Surfacing AQ TON 40
Installation of 2" SCH40 PVC Waterline CQ LF 128
3/4" Curb Stop Including Valve Box CQ EA 2
Double Check Valve Assembly
Includes conc pad, and insulated enclosure
LSQ LSQ 1
Yard Hydant Includes all components per detail, less valve (3/4" PVC, hydrant with fittings, post, reinforced concrete, aluminum grate, timbers, drain pipe, sump)
CQ EA 2
Silt Fence CQ LF 450
Seeding, Mulching and Fertilizer Includes biodegradable geotextile or jute mesh
CQ SY 200
Pedestrian Bridge (Complete and in place)
CQ EA 2
Uwharrie Ranger District National Forests in North Carolina
Montgomery County
001 BASE BID SCHEDULE
TOTAL PRICE ‐‐ FOR BASE BID PAY ITEMS
4/23/2024 Page 1 of 2
SCHEDULE OF ITEMS
Uwharrie Hunt Camp Rehabilitation
04/17/2024
National Forests in North Carolina
PAY ITEM
NO. DESCRIPTION
METHOD
OF
MEASURE
PAY
UNIT
EST.
QTY. UNIT PRICE TOTAL PRICE
4" Thick Concrete Ramp
Includes minor timber demolition and grading, aggregate base, reinforcement, and associated work. Complete and in place.
CQ CY 3.5
003 Galvanized Steel Handrail LSQ LSQ 1
Additive BID SCHEDULE
TOTAL PRICE ‐‐ FOR OPTION 1 BID PAY ITEMS
TOTAL PRICE ‐‐ FOR ALL BID PAY ITEMS
4/23/2024 Page 2 of 2
PROPOSED WORK SCHEDULE
CONTRACTOR NAME:
UNIQUE SAM ID:
SIGNATURE
to
| UNIT PRICE1: |
| TOTAL PRICE1: |
| UNIT PRICE1_2: |
| TOTAL PRICE1_2: |
| UNIT PRICE950: |
| TOTAL PRICE950: |
| UNIT PRICE2: |
| TOTAL PRICE2: |
| UNIT PRICE1_3: |
| TOTAL PRICE1_3: |
| UNIT PRICE80: |
| TOTAL PRICE80: |
| UNIT PRICE40: |
| TOTAL PRICE40: |
| UNIT PRICE128: |
| TOTAL PRICE128: |
| UNIT PRICE2_2: |
| TOTAL PRICE2_2: |
| UNIT PRICE1_4: |
| TOTAL PRICE1_4: |
| UNIT PRICE2_3: |
| TOTAL PRICE2_3: |
| UNIT PRICE450: |
| TOTAL PRICE450: |
| UNIT PRICE200: |
| TOTAL PRICE200: |
| UNIT PRICE2_4: |
| TOTAL PRICE2_4: |
| TOTAL PRICETOTAL PRICE FOR BASE BID PAY ITEMS: |
| UNIT PRICE35: |
| TOTAL PRICE35: |
| UNIT PRICE1_5: |
| TOTAL PRICE1_5: |
| TOTAL PRICETOTAL PRICE FOR OPTION 1 BID PAY ITEMS: |
| TOTAL PRICE FOR ALL BID PAY ITEMS: |
| Text2: |
| Text3: |
| Date4_af_date: |
| Date5_af_date: |
File details come from the government source that posted it. Updated .