Text version
04/17/2020
M032PRID UA537603-2Part Number
2935-01-112-2979NSN CH-47System
COOLER,LUBRICATINGONomenclature
YAdequate DMWR Available?
DMWR-55-1615-318DMWR ID
04/15/2016DMWR Date
DMWR Chg #
YPre-Award Survey Recommended?
NCorrelation Performance Study Required ? YPVA Recommended?
Nondestructive testing (NDT) procedures for magnetic particle and flourescent penetrant shall be in acccordance with ASTM E1444 and ASTM E1417 as per DMWR 55-1615-318 paragraph 5-7.a. All technique sheets shall be reviewed and approved by a certified Level III NDT Inspector. All personnel performing inspection tasks shall be certified in accordance with AIA/NAS 410.
The overhaul facility is responsible for acquisition, maintenance, calibration, and disposition of all Test, Measurement and Diagnostic Equipment (TMDE). TMDE shall be maintained and controlled in accordance with MIL-I-45607, ISO 10012, NCSL Z540.3, or AS9100/9110. Calibration documents for all TMDE shall be traceable to the National Institute of Standards of Technology (NIST).
See DMWR 55-1615-318 paragraphs 4-2.b through d for Final Performance Test Procedures.
Interactive Authoring and Display System (IADS) Version 4.0 is required to view the latest version of DMWR 55-1615-318. IADS can be procured through the Aviation and Missle Command (AMCOM) Publications office. IADS is cost free.
Identify Any Special Processes, Test Procedures, and/or Instructions
NCritical Safety Item?
The Systems Readiness Directorate (SRD) Cargo Airworthiness Division was tasked to check for emerging airworthiness issues, new Engineering Change Proposals (ECPs) affecting Critical Safety Items (CSIs), and/or concerns over reliability, durability, etc.
for the subject part. Our research did not reveal any of the above issues.
Special Airworthiness Considerations
FCDD-AMA-M-Sustainment has verified the CSI/NST status through the ARISE CIM on 28 Feb 2020 and the NHA is Non-CSI and Non-NST. The subcomponents are Non-CSI and Non-NST. Engineering testing, Fatigue, Endurance, and Interchange are not required for overhaul. No changes made. DEM
Other Requirements / Comments
If the item is not a CSI and no adequate DMWR is available, approved sources, if any, are listed by CAGE as follows:
NSpecial Post-Contract Award Requirements?
FCDD-AMA-M-Sustainment has re-verified through the ARISE CIM database on 8 April 2020 and the part is Non-CSI and Non-NST. DEM
Other Requirements / Comments (Part II)
The applicable DMWR contains detailed procedures regarding IUID requirements for this component. These procedures can be found in MEO(s) D2541, D2542, and D2543.
Other Requirements / Comments (Part III)
Other Requirements / Comments (Part IV)
Other Requirements / Comments (Part V)
NDoes QE-STD-2 Apply?
N
Additional CSI Requirements
CSI Contains CSI Replacement Parts? NEngineering Testing Required?
The solicitation/RFP shall require that all proposals/responses include a special tooling and test equipment section that addresses the contractor's plan to meet all government special tooling and test equipment requirements with either:
1. Physical possession of the required tools, 2. Confirmed requisitions for the required tools, 3. Confirmed arrangements for subcontracting the processes requiring the special tools, or 4. Specific plans describing their technical approach to develop equivalent tools.
RStatus
YTDPL?
Approved Date
M&O AED REQUIREMENTS DATA
Commerciality Determination
Commercial Item? N NBest Commercial Practice Acceptable?
04/17/2020
M032PRID UA537603-2Part Number
2935-01-112-2979NSN CH-47System
D2541
D2542
D2543
See DMWR 55-1615-318 Table 2-1 and 2-2 for critical tools and test/inspection equipment.
Critical Tools and Test and Inspection Equipment Requiring AED Approval for Substitutes
MEOs Required for Competitive Contract?
Special Post-Contract Award Requirements
RStatus
Correlation Performance Study Requirements