Attachment 0001 RIPD E4000-24-3-02 SOW (Bridge Crane)..pdf
PDF 375 KB Posted
- Attached to
- 3-TON SINGLE-GIRDER BRIDGE CRANE Federal contract opportunity
- Solicitation number
- W519TC24Q2328
About this file
This document is a Purchase Description for a 3-Ton Single Girder Bridge Crane to be installed at the Rock Island Arsenal (RIA). The key details are:
The government is seeking a new, free-standing, single-girder, 3-ton bridge crane to support sand printing operations at RIA. The crane must meet various design, safety, and security requirements, including Item Unique Identification (IUID) registration. The contractor is responsible for delivering, installing, and testing the crane, as well as providing maintenance training. The crane must have variable speed drives for the bridge, trolley, and hoist, with specific minimum speed ranges. The contractor must provide a verifiable service and repair capability, including 48-hour on-site response. The solicitation number is W519TC24Q2328.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 24Q2328.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROCK ISLAND ARSENAL RIPD: 24-3-02
PURCHASE DESCRIPTION DATE: 12-Mar-24
3-TON SINGLE-GIRDER BRIDGE CRANES
1. GENERAL
The purpose of this project is to provide a Free Standing, 3-Ton Single Girder Bridge Crane to support the ExOne sand printers. One single-girder 3-ton bridge crane is required to move product, printed molds, and equipment within the new sand printing room.
2. STANDARDS AND PUBLICATIONS
2.1 Clarification
Any ambiguities, questions, requests for clarification or discrepancies between sections of this purchase description, drawings, national or industry standards discovered by the contractor in reviewing this purchase description shall be reported by the bidder in writing to the contracting officer BEFORE THE DATE SCHEDULED FOR CLOSE OF BIDDING/receipt of proposal.
Submission of a proposal or bid shall be construed as evidence that such examination has been made. Therefore, later claims for labor, material, or equipment required, or for difficulties encountered, which could have been foreseen had such reasonable examination been made, may be denied.
3. DESIGN
3.1 General Design Standards
3.1.1 UNITS OF MEASURE: Dimensions and capacities in this purchase description are given in the English-US (in-lb.) system. All dials, gauges, and drawings shall be in the English- US system or both the English-US and the metric systems, unless otherwise specified in this document.
3.1.2 ID DATA PLATE: The equipment shall include a main data plate which will include the following data as a minimum requirement (additional information is acceptable):
Manufacturer Name, Manufacturer’s Dunns and Bradstreet Number, Manufacturer’s Model Number, Manufacturer’s Serial Number, Year of Manufacture, Contract Number, Machine Weight. This information is necessary for compliance with the governments Unique Identification Program (UID).
3.1.3 DATA PLATES: All instruction, data, and identification plates and labels attached to this equipment and its controls shall be manufactured of corrosion and oil resistant metal or plastic material. All wording shall be in the English language using plain, bold face lettering.
Lettering shall be permanent and have a contrasting background.
3.1.4 ITEM UNIQUE IDENTIFICATION (IUID) REGISTRATION: The contractor shall register the equipment in the IUID Registry (as one single system). IUID registration requires the contractor to input Cage Code, Model Number, and Serial Number into a Government Database to allow for asset and inventory tracking. IUID Registry of the equipment shall be performed at http://dodprocurementtoolbox.com/site/uidregistry/. Training for IUID is available in https://wawftraining.eb.mil. IUID registration of this equipment is required prior to final payment in the Wide Area Work Flow (WAWF). The contractor shall also affix a machine readable 2-dimensional (2-D) matrix representing the IUID registry to the machine. The IUID 2-D matrix may be included on the ID Data Plate outlined in paragraph 3.2.4.
3.1.5 ELECTRICAL DISCONNECT: The equipment shall be equipped with a manual, fused or breaker type disconnect switch, readily accessible to the operator, which will deactivate the entire equipment. It shall be located no more than 6-ft 7-in from the floor to the highest point the control device. It shall be capable of being locked in the de-energized state (OFF) only.
3.1.6 CONDUIT: Flexible conduit is not permitted in exposed areas. All wires, cables, and hoses will be enclosed by rigid, oil-proof protection, except where flexibility is necessary for operation of the equipment. Flexible wires, cables and hoses shall be arranged to prevent draping or tripping hazards.
3.1.7 NEW EQUIPMENT: The equipment furnished under this purchase description shall be new and unused.
3.1.8 COMPONENT ENVIRONMENT: Under no circumstances shall a component be used in an application not recommended by the component manufacturer. Components shall not be subjected to conditions of operation beyond the recommendations of the manufacturer, such as excessive heat, lack of lubrication, over-loading.
3.1.9 CASTINGS AND FORGINGS: All castings and forgings shall be free of defects, scale, and mismatching. No process such as welding, peening, plugging, or filling shall be used for reclaiming any defective part for use in this equipment without the prior written consent of the contracting officer.
3.1.10 SURFACE BUILDING AND COATINGS: Welding, brazing, soldering, coating or plating shall be employed only where specified in the original design. These operations may not be employed as a means of reclaiming a defective part.
3.1.11 FASTENING DEVICES: All screws, pins, bolts, and similar parts shall be installed in such a manner as to prevent change in tightness. Those devices subject to removal or adjustment shall not be swaged, peened, staked, or otherwise permanently deformed. They shall not be installed using permanent bonding adhesives. (Structural connections shall be secured with ASTM A325 or A490 Bolts per CMAA 3.13 Structural bolting.)
3.1.12 PAINTING: All unfinished surfaces of the equipment shall be painted with a lead free and chromium free commercial grade of metal primer and a minimum of one finish coat. The color shall be in accordance with the manufacturer’s standard commercial practice, or as necessary to maintain compliance with OSHA regulations, as applicable.
3.2 Safety, Security and Environmental
3.2.1 SECURITY: The RIA-JMTC is an Army installation subject to Department of Defense safeguards, various precautions, and plant protection measures. All of the below requirements will be necessary of contractors visiting RIA to satisfy requirements of this purchase description; Additional requirements will be placed on contractors requiring access to the Army Network, or Common Access Card (CAC), as specifically detailed below. At all times during the execution of this work, contractor personnel will maintain adequate plant protection devises to minimize espionage, sabotage, and other malicious destruction and damage. The contractor shall comply with all security requirements of the Rock Island Arsenal. Rock Island Arsenal island-wide Force Protection levels may be adjusted/changed at any time, which may cause possible delays and will directly affect procedures for accessing the island.
3.2.1.1 Access and General Protection/Security Policy and Procedures: The contractor and any associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Director of Emergency Services. All contractor employees must comply with all personal identity verification requirements (IAW FAR clause 52.204-9) as directed by Department of Defense (DoD), Headquarters Department of the Army (HQDA), and any local policy. If the Force Protection Condition (FPCON) changes, the Government may require changes in contractor installation access, security matters, or security processes.
3.2.1.1.1 Access to RIA: Contractor and all subcontractor employees performing work at RIA shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) and any applicable installation, facility access screening and local security policies and procedures. The COR shall provide guidance to complete the Access Control Records Check request Form though the Rock Island Arsenal Directorate of Emergency Services.
3.2.1.1.2 Random Antiterrorist Measures Program (RAMP) participation: Contractor personnel are subject to RAMP security program (i.e. vehicle searches, wearing of ID badges, etc.). Contractor shall comply with any, and all instructions issued by the Rock Island Arsenal Police Department. The RAMP is discussed in the RIA-JMTC Anti- Terrorism Training.
3.2.1.1.3 During FPCONs levels of Charlie or Delta, services may be discontinued/postponed due to a higher National or local security threat. Services will resume when FPCON Level is reduced to Bravo, or lower. FPCON levels are described in Anti-Terrorism Level I Training.
3.2.1.1.4 Contractor personnel shall return all Installation Badges and access passes as soon as possible prior to contract completion. RIA-JMTC electronic keys and access passes are accountable items, shad shall be returned within 24-hours of no longer being needed. Items will be returned to the COR, or paced in a drop box at a RIA-JMTC access point.
3.2.1.2 Security Training: The contractor shall complete the following training:
3.2.1.2.1 Anti-Terrorism, Level I: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete Anti-Terrorism (AT) Level I Awareness training. The COR will be provided a copy of the Rock Island Arsenal –Joint Manufacturing and Technology Center (RIA-JMTC) AT Level I Awareness Training and assure that the training is complete.
The contractor shall sign a memorandum of record for each contractor employees and subcontractor employee to the RIA-JMTC Operations Center prior issuing any electronic keys, or access pass being authorized.
3.2.1.2.2 iWatch (See Something, Say Something) Training: The Contractor and all associated subcontractors shall complete iWatch Training. iWatch Training shall be provided during the Anti-Terrorism Training.
3.2.1.3 No Common Access Card (CAC) will be issued as part of this project.
3.2.2 FEDERAL MARIJUANA LAWS REMAIN UNCHANGED: Note: Rock Island Arsenal is under the exclusive federal jurisdiction of the United States. Under federal law, marijuana is still defined as a Schedule I drug, and possession and use of marijuana is still illegal. Any person using or in possession of marijuana on Rock Island Arsenal may be criminally prosecuted in federal district court. In addition, such individuals may be permanently barred from entering Rock Island Arsenal.
3.2.3 REAL ID: Starting 03-MAY-2023 all personnel entering Rock Island Arsenal will be required to show a Real ID form of identification.
3.2.4 FIRE PREVENTION AND PROTECTION: The contractor shall comply with all fire prevention measures prescribed in the installation Fire Regulations, a copy of which is on file in the office of the Contracting Officer. A written fire permit shall be obtained from the installation Fire Marshall for use of open flame devices, such as torches, portable furnaces, tar kettles, or gas and electric welding and cutting equipment, in, on, or within 15-ft of the building.
The contractor shall be liable for any fire loss to the Government properly attributable to negligence on the part of the contractor, including failure to comp1y with fire prevention measure described by the terms of this purchase description.
3.2.5 INDUSTRY AND REGULATIONS: The equipment shall comply with the most current of all local, state, and federal laws and regulations listed in Standards and Publications.
3.2.6 MATERIAL EXCLUSIONS: The equipment shall not contain polychlorinated biphenyl (PCB), ozone depleting substances (Class I or Class II), or asbestos materials.
3.2.7 SAFETY REGULATION COMPLIANCE: The contractor shall comply with standard OSHA and RIA safety standards, including conforming to confined space work requirements when applicable.
3.2.8 SAFETY LOCKOUTS: Each point of first connection shall be designed and constructed to allow the utility to be completely isolated from the equipment. This isolation shall be insured by application of a standard key locking padlock. The device(s) shall only be lockable in the de-energized (OFF) condition.
3.2.9 TRAPPED ENERGY: Means shall be provided for the controlled release of stored energy. This energy may be in the form of, but not limited to, air and hydraulic pressure accumulators, capacitors, springs, counter balances and flywheels. When appropriate, a label shall be affixed to the stored energy source to identify the hazard.
3.3 Responsibilities
3.3.1 SITE INSPECTION: Any site inspections and/or measurements, which must be taken in order to determine the suitability of the proposed location or to perform the design of the system, are the sole responsibility of the contractor. This may begin prior to completing the bidding process. Rock Island Arsenal will support this function through the POC (point of contact) by guiding personnel, facilitating security registration, and providing general assistance. The contractor will be responsible for providing any and all equipment necessary for this process.
4. CRANE SPECIFICATION:
The contractor will provide and install (1) new free standing, 3-ton single-girder overhead bridge crane in the foundry sand printing room. It shall include all materials and labor necessary to make the equipment safely operational and to meet all relevant industry and national standards.
4.1 Type:
4.1.1 The new system shall be a free standing, single girder, top-running bridge crane with DC disc type brakes on the bridge and trolley.
4.1.2 The free-standing crane shall be of approximate size 80ft (L) x 48ft (W) x 26ft (H).
4.2 Characteristics:
4.2.1 The crane shall have the capacity to lift 3-ton loads. Bridges, trolleys, and hoists to be sized appropriately.
4.2.2 All electrical power is 460-V, 3-Ph, 60-Hz. All areas have conductor bars with no conductor bar grounds.
4.2.3 The bridge shall have variable speed drives with speed ranges covering at least 8-fpm to 65-fpm. (Wider ranges are acceptable but must include this range as a minimum.)
4.2.4 The contractor shall provide and install bumpers and extensions for the bridge. The bumpers shall be designed to absorb impact from the maximum loads and speeds of the new system or from the existing system with one system held stationary while the other is in full motion. If bumper components are required to be installed on the existing bridge to allow for safe operation of either system, it shall be provided as part of this purchase description.
Note: D-shaped bumpers will not be deemed acceptable.
4.2.5 The trolley shall have at least a 2-speed contactor type drive with brakes. Note: a variable speed drive will be considered acceptable as it exceeds the minimum requirement. The speed(s) of the trollies shall be 20-fpm/80-fpm ±20%. A variable speed drive would need to cover at least the range of 20-fpm to 80-fpm.
4.2.6 The hoist shall bb Variable Frequency Drive (VFD). The high speed may be as high as 20-fpm but no less than 16-fpm.
4.2.7 The system will be designed to allow the hook to extend at least 3-ft below grade level.
4.2.8 The system shall include a hand pendant to operate all drives on the system with festooning (no radio pendants allowed) to allow the crane to be operated at any point along the length of the bridge and at least 15-ft from the hook (to allow the operator to be a safe distance from the load being lifted).
4.2.9 The system will be new installation.
4.2.10 The vendor shall mark the system with the capacities and all other signage as required by national standard and regulations.
4.2.11 The vendor shall mark the bottom of the bridge to indicate the directions of travel corresponding to the labels on the pendant buttons.
5. APPROVAL/SHIPPING
5.1 Shipping
5.1.1 RESPONSIBILITY: The contractor is responsible for delivery of the equipment to the Rock Island Arsenal. Adequate preserving of equipment surfaces, packing, marking, and skidding of materials for shipment shall be the responsibility of the contractor. If special lifting devices, such as hooks or eyes, are required for ease of handling, they shall be supplied with the equipment. Any special devices shall be returned to the contractor upon request only if they will not be required for future movement of the equipment, and at the contractor’s expense.
5.1.2 SHIPPING SCHEDULE: Be aware, the Rock Island Arsenal will only off-load equipment arriving between 6:00 am and 12:00 am (noon), local time on Mondays through Thursdays except holidays. For information concerning holidays, the contractor should consult the contracting officer. There is no place to stage transporting vehicles awaiting the arrival of contractors. All equipment shall be delivered at the same time, meaning the same day (multiple trucks are acceptable) unless pre-authorized to deliver on multiple days by the RIA-JMTC contracting officer.
5.1.3 RECEIVER: All shipments to Rock Island Arsenal including installation tools and/or replacement parts, as well as the original shipment of the equipment, shall be marked “ATTN:
Mr. Bob McClure or Mr. Dave Holgorsen, TARA-PSF”. Items not correctly marked are subject to being returned at the vendor’s expense.
5.1.4 ARRIVAL INSPECTION: Upon receipt of equipment at Rock Island Arsenal, a preliminary inspection shall be performed to determine condition and/or count. This inspection shall be performed by Rock Island Arsenal personnel.
5.2 Installation
5.2.1 SITE PREPARATION REQUIREMENTS: The contractor shall be solely responsible for any necessary site inspections required for determining the specifications of work that must be completed prior to final system installation. The contractor will then provide detailed information of any preparation work that the vendor must perform prior to system installation to Rock Island Arsenal.
5.2.2 LABOR AND MATERIAL: The supplier is solely responsible for providing all labor, materials, hardware, tools, and equipment necessary for complete installation of this system except as specifically listed in this document as being provided by the Rock Island Arsenal.
5.2.3 SUPERVISION: Supervision of the installation process will be the responsibility of the contractor. Rock Island Arsenal shall retain the right to periodic inspection and evaluation of the process, as it deems necessary.
5.2.4 OFF-LOADING/PLACEMENT: Off-loading of the equipment from the delivery vehicle, and placement of the equipment in position for the installation is the responsibility of the contractor. The contractor shall not be allowed to use government equipment to accomplish this work.
5.2.5 Delivery Hours or Service Hours: Service calls, equipment installation, training, and equipment delivery (where the contractor offloads) will only be allowed from 0700 – 1530, Monday through Friday, except for Government Holidays. These hours are subject to change, however, the Government will notify the contractor of such changes. The vendor will contact the designated COR to obtain an electronic key for their representative (i.e. delivery driver) in order to have access to the facility. Deliveries and service calls outside the normal hours stated above will be coordinated with the COR to address any emergency situations."
5.3 Completion
5.3.1 Final acceptance of the equipment shall occur after the following:
5.3.1.1 Set-up completion by the contractor.
5.3.1.2 Successful completion of performance testing at Rock Island Arsenal.
5.3.1.3 Final inspection approval by the government representative or inspector. This is to verify full compliance with this description to include amendments and modifications to the final contract. The government representative shall perform any and all tests he deems necessary to insure compliance with this description and industry standards to include, but not limited to ease of control, convenience of operation, safe operation, and adequacy of lubrication devices.
5.3.1.4 All required training is complete.
5.3.1.5 Complete documentation packages are delivered.
6. MAINTENANCE TRAINING
The contractor shall provide instruction in maintenance of the equipment without additional cost to the government. Training shall be of sufficient duration that the recipients are able to demonstrate a reasonable level of competence as determined by the equipment installer and/or the inspector.
Acceptance may be delayed as a result of inadequate training.
6.1 Schedule
Training shall training shall be coordinated with the Rock Island Arsenal. Daily training shall begin no later than 6:30 a.m. CST and shall continue until at least 2:15 p.m. CST. This is required to get full coverage of the 1st shift of operation at RIA-JMTC. If training does not begin until after the stated time, RIA-JMTC may at its option require additional training at a different time to compensate for the loss of training caused by the late start. This may include more time than what is represented by the delay (e.g. a 1-hr delay may require 2-hrs later to impart the knowledge lost).
6.2 Location
6.2.1 All training shall be performed at the Rock Island Arsenal. It shall be performed using the equipment purchased in this description.
7. SERVICE
7.1 Service/Support Requirements
The contractor shall have as a minimum, a verifiable service/repair capability which meets or exceeds the following requirements:
7.1.1 STAFF: Staffed by qualified, English speaking personnel fully knowledgeable in the service/repair of the equipment offered.
7.1.2 TELEPHONE ACCESS: Telephone access to service/repair personnel shall be available for consultation during Rock Island Arsenal normal working hours. Rock Island Arsenal normal working hours are 8:00 am CST to 3:00 pm CST, Monday through Friday, except legal federal holidays.
7.1.3 ON-SITE RESPONSE: Physical, on-site response shall be possible within 48-hrs of notification that service/repair of the equipment is necessary.
7.1.4 MAINTENANCE PARTS: Parts necessary for periodic replacement such as belts, hoses, filters, and other parts normally considered as spare parts, by the manufacturer, shall be stocked and available for shipment.
7.1.5 PRIOR HISTORY: Said service/repair capability shall have been available to the general public prior to the issue date of this purchase description. Adequate proof of prior availability shall be provided upon request.