Attachment 0001 RIPD E4000-24-3-02.pdf

PDF 419 KB Posted

Attached to
Sand Handling Room Buildout Federal contract opportunity
Solicitation number
W519TC24Q2212
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

This purchase description outlines requirements for a sand printer room buildout project at Rock Island Arsenal. Key details include constructing a new 91' x 48' x 30' climate-controlled room within an existing factory near the foundry. Work includes demolishing existing materials; installing CMU walls, steel stud walls, or steel walls; adding man doors, roll up doors and a high-speed overhead door; constructing a 4,400 square foot mezzanine; installing high-bay LED lights, HVAC system to control temperature and humidity, and a fire protection system. The contractor must also relocate busduct, disconnects and a transformer to the new room. The solicitation number for this opportunity is W519TC24Q2212 and it was issued by the Department of the Army Materiel Command Contracting Command located at Rock Island Arsenal.

View the file

Other files for this federal contract opportunity

Other files attached to Sand Handling Room Buildout, newest first.
File Type Posted
Attachment 0003 CDRL.pdf PDF
24Q2212.pdf PDF
24Q2212 Released.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROCK ISLAND ARSENAL RIPD: E4000-24-3-02

PURCHASE DESCRIPTION DATE: 04-DEC-23

SAND PRINTER ROOM BUILD-OUT

1. GENERAL SYSTEM DESCRIPTION

This purchase description is to fit-out a sand printing room of approximately 91ft (L) x 48ft (W) x 30ft (H) in size. This new room buildout will be within the existing factory near the foundry.

2. STANDARDS AND PUBLICATIONS

2.1 Clarification

Any ambiguities, questions, requests for clarification or discrepancies between sections of this purchase description, drawings, national or industry standards discovered by the contractor in reviewing this purchase description shall be reported by the bidder in writing to the contracting officer BEFORE THE DATE SCHEDULED FOR CLOSE OF BIDDING/receipt of proposal.

Submission of a proposal or bid shall be construed as evidence that such examination has been made. Therefore, later claims for labor, material, or equipment required, or for difficulties encountered, which could have been foreseen had such reasonable examination been made, may be denied.

2.2 National Standards and Specifications

All National specifications and Standards in effect on the date of this solicitation form a part of this purchase description and must be followed. In the case of conflicting requirements, the more stringent shall apply.

3. DESIGN

3.1 General Design Standards

3.1.1 DEVIATION FROM PRODUCT: Modifications to the manufacturer’s standard design to achieve requirements as specified in this document are only permissible as dictated by good design practice. For example, mounting a 20-hp motor in a power train designed and normally using a 10-hp motor would not be acceptable.

3.1.2 CONDUIT: Flexible conduit is not permitted in exposed areas. All wires, cables, and hoses will be enclosed by rigid, oil-proof protection, except where flexibility is necessary for operation of the equipment. Flexible wires, cables and hoses shall be arranged to prevent draping or tripping hazards.

3.1.3 NEW EQUIPMENT: The equipment furnished under this purchase description shall be new and unused.

3.1.4 COMPONENT ENVIRONMENT: Under no circumstances shall a component be used in an application not recommended by the component manufacturer. Components shall not be subjected to conditions of operation beyond the recommendations of the manufacturer, such as excessive heat, lack of lubrication, over-loading.

3.1.5 REPLACEMENT COMPONENTS: All replaceable components shall be manufactured to definite standards for tolerance, clearance, and finish, enabling components to be field installed without further machining.

3.1.6 FASTENING DEVICES: All screws, pins, bolts, and similar parts shall be installed in such a manner as to prevent change in tightness. Those devices subject to removal or adjustment shall not be swaged, peened, staked, or otherwise permanently deformed. They shall not be installed using permanent bonding adhesives.

3.1.7 FOUNDATION: The requirement for a separate foundation is permissible, if necessary to meet the specified alignment tolerances, to provide isolation, or to conform to a standard system configuration. The contractor shall describe the foundation requirements at the time of bid. RIA-JMTC shall be responsible for installation of the foundation based upon the drawings provided by the vendor.

3.2 Safety, Security and Environmental

3.2.1 SECURITY: The RIA-JMTC is an Army installation subject to Department of Defense safeguards, various precautions, and plant protection measures. All of the below requirements will be necessary of contractors visiting RIA to satisfy requirements of this purchase description; Additional requirements will be placed on contractors requiring access to the Army Network, or Common Access Card (CAC), as specifically detailed below. At all times during the execution of this work, contractor personnel will maintain adequate plant protection devises to minimize espionage, sabotage, and other malicious destruction and damage. The contractor shall comply with all security requirements of the Rock Island Arsenal. Rock Island Arsenal island-wide Force Protection levels may be adjusted/changed at any time, which may cause possible delays and will directly affect procedures for accessing the island.

3.2.1.1 Access and General Protection/Security Policy and Procedures: The contractor and any associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Director of Emergency Services. All contractor employees must comply with all personal identity verification requirements (IAW FAR clause 52.204-9) as directed by Department of Defense (DoD), Headquarters Department of the Army (HQDA), and any local policy. If the Force Protection Condition (FPCON) changes, the Government may require changes in contractor installation access, security matters, or security processes.

3.2.1.1.1 Access to RIA: Contractor and all subcontractor employees performing work at RIA shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) and any applicable installation, facility access screening and local security policies and procedures. The COR shall provide guidance to complete the Access Control Records Check request Form though the Rock Island Arsenal Directorate of Emergency Services.

3.2.1.1.2 Random Antiterrorist Measures Program (RAMP) participation: Contractor personnel are subject to RAMP security program (i.e. vehicle searches, wearing of ID badges, etc.). Contractor shall comply with any, and all instructions issued by the Rock Island Arsenal Police Department. The RAMP is discussed in the RIA-JMTC Anti- Terrorism Training.

3.2.1.1.3 During FPCONs levels of Charlie or Delta, services may be discontinued/postponed due to a higher National or local security threat. Services will resume when FPCON Level is reduced to Bravo, or lower. FPCON levels are described in Anti-Terrorism Level I Training.

3.2.1.1.4 Contractor personnel shall return all Installation Badges and access passes as soon as possible prior to contract completion. RIA-JMTC electronic keys and access passes are accountable items, shad shall be returned within 24-hours of no longer being needed. Items will be returned to the COR, or paced in a drop box at a RIA-JMTC access point.

3.2.1.2 Security Training: The contractor shall complete the following training:

3.2.1.2.1 Anti-Terrorism, Level I: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete Anti-Terrorism (AT) Level I Awareness training. The COR will be provided a copy of the Rock Island Arsenal –Joint Manufacturing and Technology Center (RIA-JMTC) AT Level I Awareness Training and assure that the training is complete.

The contractor shall sign a memorandum of record for each contractor employees and subcontractor employee to the RIA-JMTC Operations Center prior issuing any electronic keys, or access pass being authorized.

3.2.1.2.2 iWatch (See Something, Say Something) Training: The Contractor and all associated subcontractors shall complete iWatch Training. iWatch Training shall be provided during the Anti-Terrorism Training.

3.2.1.3 For Contractors requiring Common Access Card (CAC): No CAC will be issued in connection to this project.

3.2.2 FEDERAL MARIJUANA LAWS REMAIN UNCHANGED: Note: Rock Island Arsenal is under the exclusive federal jurisdiction of the United States. Under federal law, marijuana is still defined as a Schedule I drug, and possession and use of marijuana is still illegal. Any person using or in possession of marijuana on Rock Island Arsenal may be criminally prosecuted in federal district court. In addition, such individuals may be permanently barred from entering Rock Island Arsenal.

3.2.3 REAL ID: Starting 03-May-2025 all personnel entering Rock Island Arsenal will be required to show a Real ID form of identification.

3.2.4 FIRE PREVENTION AND PROTECTION: The contractor shall comply with all fire prevention measures prescribed in the installation Fire Regulations, a copy of which is on file in the office of the Contracting Officer. A written fire permit shall be obtained from the installation Fire Marshall for use of open flame devices, such as torches, portable furnaces, tar kettles, or gas and electric welding and cutting equipment, in, on, or within 15-ft of the building. The contractor shall be liable for any fire loss to the Government properly attributable to negligence on the part of the contractor, including failure to comp1y with fire prevention measure described by the terms of this purchase description.

3.2.5 MATERIAL EXCLUSIONS: The equipment shall not contain polychlorinated biphenyl (PCB), ozone depleting substances (Class I or Class II), or asbestos materials.

3.2.6 SAFETY REGULATION COMPLIANCE: The contractor shall comply with standard OSHA and RIA safety standards, including conforming to confined space work requirements when applicable.

3.2.7 SAFETY LOCKOUTS: The contractor shall incorporate safety lockouts where applicable to allow the utility to be completely isolated from the equipment. This isolation shall be insured by application of a standard key locking padlock. The device(s) shall only be lockable in the de-energized (OFF) condition.

3.3 Responsibilities

3.3.1 SITE INSPECTION: Any site inspections and/or measurements, which must be taken in order to determine the suitability of the proposed location or to perform the design of the system, are the sole responsibility of the contractor. This may begin prior to completing the bidding process. Rock Island Arsenal will support this function through the POC (point of contact) by guiding personnel, facilitating security registration, and providing general assistance. The contractor will be responsible for providing any and all equipment necessary for this process.

4. COMPONENT SPECIFICATION

This is to define the requirements for the build of a climate controllable room. This specification shall include all equipment and labor necessary to build and establish an environmentally controllable room with which to move two ExOne sand printers and all the support equipment needed to produce sand printed molds.

4.1 Dimensions of room Build-Out:

4.1.1 Approximately 91ft (L) x 48ft (W) x 30ft (H).

4.2 Construction Necessities:

4.2.1 The contractor will supply any needed permits, dumpsters, job site supervision and transportation.

4.3 Demolition of Materials in New Sand Printer Room:

The contractor will be responsible for the demolition of any concrete (including but not limited to Concrete Masonry Unit (CMU) wall, flooring, etc.), conduit, or wiring that will be no longer necessary to support the build-out of the new climate-controlled sand printer room.

4.4 Wall:

The contractor will install a new CMU wall or steel stud with steel wall (must support the mezzanine requirements listed below and provide a fire rated assembly). This wall will be eight inches thick concrete masonry unit construction approximately 91ft (L) and 30ft (H). With any needed new structural steel columns, beams, and footings necessary to support the new build (see sketch 1below).

4.5 Doors:

The contractor will supply, install or modify the existing facility as necessary to support these new doors, 2 – 7ft x 3ft Man doors at the locations shown on sketch 1, 1 – 12ft x 12ft Roll Up Overhead Door at the location shown on the sketch 1, and 1 – High-Speed Overhead Roll Up Door at the location shown on the sketch 1. The High-Speed Overhead Roll Up Door shall be equipped with a fusible fire connection with automatic reset, and bottom collision protection.

The new overhead doors will have pipe bollards installed for their protection.

4.6 Service Door for Dust Collector Area:

A 12ft x 12ft service door will be added to the dust collector area of the current mezzanine. The current CMU wall will be cut and a 12ft x 12ft overhead door from old mezzanine out to the Foundry shop will be added (see sketch 1 for general location).

4.7 Mezzanine:

The contractor will supply and install a mezzanine also known as “Wide Rib Roof Deck” for the roof of the build-out room. This mezzanine will be approximately 4,400 sq-ft, type B decking with a minimum load rating of 850lb/ft, along with an OSHA compliant access to the mezzanine.

Access must be sufficient for personnel and for the installation/future replacement of mechanical equipment.

4.8 High-Bay Lights:

The contractor will supply, install, and provide power to High-Bay LED lights with motion sensors and shut-off timers to achieve at least 50-fc average with minimal spotlighting. Include a lighting panel box with 20-amp breakers, with a minimum of seven breakers beyond just those for the lights.

4.9 Heating, Ventilation, and Air Conditioning (HVAC):

The contractor will develop and install a HVAC system to establish a climate controllable room.

This system will include a new canister style wall mounted humidifier, (2) Rooftop HVAC units each sized for approximately 75% of the total load, along with the supply and return ducting, grilles, registers, and diffusers for the HVAC system. The contractor shall provide and install all necessary wiring and conduit to power these items as well as any necessary plumbing. The room’s system shall be able to maintain a relative air humidity of 30 – 50%, with a temperature range of 72 – 82 degrees Fahrenheit. The equipment emissions include a thermal output of 1.7kW with a required cooling performance of 3.55kW.

4.10 Fire Protection:

The contractor will supply and install a fire protection system with-in the build-out room and re-configure the existing over-head sprinklers above the new mezzanine. A drawing of the system will be provided which can be certified by Fire Protection Engineer at the RIA.

4.11 Movement:

The contractor shall disconnect the existing Busduct, Disconnects, and Transformer from the current Sand Printer room and relocate and connect these items to the new build-out room. (see sketch 1 below for suggested location).

SKETCH 1

5. APPROVAL/SHIPPING

5.1 Shipping

5.1.1 RESPONSIBILITY: The contractor is responsible for delivery of the equipment to the Rock Island Arsenal. Adequate preserving of equipment surfaces, packing, marking, and skidding of materials for shipment shall be the responsibility of the contractor. If special lifting devices, such as hooks or eyes, are required for ease of handling, they shall be supplied with the equipment. Any special devices shall be returned to the contractor upon request only if they will not be required for future movement of the equipment, and at the contractor’s expense.

5.2 Installation

5.2.1 SITE PREPARATION REQUIREMENTS: The contractor shall be solely responsible for any necessary site inspections required for determining the specifications of work that must be completed prior to final system installation. The contractor will then provide detailed information of any preparation work that the vendor must perform prior to system installation to Rock Island Arsenal.

5.2.2 SITE PREPARATION EXECUTION: The contractor will be solely responsible for site preparation except as specifically excluded in this document. This includes but is not limited to excavation, foundation work, and surface preparation. This work may be performed through the use of a sub-contractor, but the specification, supervision, and certification of the work remains the responsibility of the primary contractor.

5.2.3 LABOR AND MATERIAL: The supplier is solely responsible for providing all labor, materials, hardware, tools, and equipment necessary for complete installation of this system.

5.2.4 SUPERVISION: Supervision of the installation process will be the responsibility of the contractor. Rock Island Arsenal shall retain the right to periodic inspection and evaluation of the process, as it deems necessary.

5.2.5 OFF-LOADING/PLACEMENT: Off-loading of the equipment from the delivery vehicle, and placement of the equipment in position for the installation is the responsibility of the contractor. The contractor shall not be allowed to use government equipment to accomplish this work.

5.2.6 LIABILITY: In any case, the equipment remains the property of the contractor, and the contractor shall assume all responsibility and liability for the equipment and the work performed upon it. The government shall be held harmless for any damage done to the equipment at any time up until final acceptance of the equipment by Rock Island Arsenal, except in the case of intentional damage and/or gross negligence on the part of Rock Island Arsenal personnel.

5.2.7 Delivery Hours or Service Hours: Service calls, equipment installation, training, and equipment delivery (where the contractor offloads) will only be allowed from 0600 – 1530, Monday through Thursday, except for Government Holidays. These hours are subject to change, however, the Government will notify the contractor of such changes. The vendor will contact the designated COR to obtain an electronic key for their representative (i.e. delivery driver) in order to have access to the facility. Deliveries and service calls outside the normal hours stated above will be coordinated with the COR to address any emergency situations."

5.3 Completion

5.3.1 Final acceptance of the equipment shall occur after the following:

5.3.1.1 Set-up completion by the contractor.

5.3.1.2 Successful completion of performance testing at Rock Island Arsenal.

5.3.1.3 Final inspection approval by the government representative or inspector. This is to verify full compliance with this description to include amendments and modifications to the final contract. The government representative shall perform any and all tests he deems necessary to insure compliance with this description and industry standards to include, but not limited to ease of control, convenience of operation, safe operation, and adequacy of lubrication devices.

5.3.1.4 Complete documentation packages are delivered.