Attachment 0001 - RIPD E4000-23-9-20 - OCs LC Replacements final.pdf
PDF 201 KB Posted
- Attached to
- Optical Comparators Federal contract opportunity
- Solicitation number
- W519TC-24-Q-2395
About this file
This document is a Purchase Description for the procurement of three new manual Optical Comparators (OCs) to initiate a life cycle replacement plan at the Rock Island Arsenal (RIA). The Purchase Description provides detailed technical specifications for the required OCs, including dimensions, system features, component requirements, and accessories. It specifies that the replacement OCs should be Starrett Model HF750 MX or equivalent. The document also outlines requirements for installation, training, service/support, and information technology support. Key details include that the OCs must meet various safety, security, and environmental standards, and that the contractor is responsible for delivery, installation, and training at the RIA site. The related federal contract opportunity is a solicitation issued by the Department of the Army Materiel Command Contracting Command Rock Island Arsenal for the procurement of these Optical Comparators.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| W519TC-24-Q-2395 Optical Comparators.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROCK ISLAND ARSENAL RIPD: E4000-23-9-20 R1
PURCHASE DESCRIPTION DATE: 15-Aug-24
OPTICAL COMPARATOR LIFE CYCLE REPLACEMENT (3)
1. General Description….………………………………………………………………2
1.1 Clarification
2. STANDARDS AND PUBLICATIONS………………………………………………2
2.1 Clarification
2.2 National Standards and Specifictions
3. DESIGN…………………………………………………………………………………………….3
3.1 Ownership.………………………………………………………………………………3
3.2 General Design Standards.……………………………………………………….……...3
3.3 Safety, Security and Environmental..……………………………………………………6
4. COMPONENT SPECIFICATION
4.1 Dimensions:
4.2 System Features:
5. INFORMATION TECHNOLOGY SYSTEMS AND SUPPORT
5.1 Installation IT Support:
5.2 INSPECTION/FINAL ACCEPTANCE:
5.3 Media/ Devices
5.4 INFORMATION ASSURANCE AND ACCREDITATION:
6. APPROVAL/SHIPPING
6.1 Shipping
6.2 Installation
6.3 Completion
7. TRAINING. ................ ……………………………………………………………………………14
7.1 Schedule
7.2 Location
7.3 Type
8. SERVICE…
8.1 Service/Support Requirements
1. GENERAL SYSTEM DESCRIPTION This is a purchase description used to purchase three new old style manual Optical Comparators (OC) to initiate the life cycle replacement plan. The old style OC is defined as a non-networkable, non CNC and before modernization of the OC technology.
The suggested replacements are Starrett Model HF750 MX or equivalent. The intended existing OCs to be replaced will be RIA 31607, 32205 & 33107.
2. STANDARDS AND PUBLICATIONS
2.1 Clarification Any ambiguities, questions, requests for clarification or discrepancies between sections of this purchase description, drawings, national or industry standards discovered by the contractor in reviewing this purchase description shall be reported by the bidder in writing to the contracting officer BEFORE THE DATE SCHEDULED FOR CLOSE OF BIDDING/receipt of proposal. Submission of a proposal or bid shall be construed as evidence that such examination has been made. Therefore, later claims for labor, material, or equipment required, or for difficulties encountered, which could have been foreseen had such reasonable examination been made, may be denied.
2.2 National Standards and Specifications
The following specifications in effect on the Date of Invitation for Bid/Request for Proposal form a part of this purchase description. In the case of conflicting requirements, the more stringent shall apply.
2.2.1 Occupational Safety and Health Act of 1970 (OSHA).
2.2.2 American Society of Testing and Materials (ASTM).
2.2.3 American Society of Mechanical Engineers (ASME).
2.2.4 American National Standards Institute (ANSI).
2.2.5 National Electrical Manufacturers Association Standards (NEMA).
2.2.6 Electronic Industries Association (EIA).
2.2.7 Institute of Electrical and Electronics Engineers (IEEE).
2.2.8 American Code for Information Exchange (ASCII).
2.2.9 American Welding Society (AWS).
2.2.10 American Gear Manufacturers Association (AGMA).
2.2.11 National Fire Protection Association (NFPA).
2.2.11.1 NFPA-70 National Electrical Code.
2.2.11.2NFPA-79 Electrical Standard for Industrial Machinery.
2.2.12 International Standards Organization (ISO).
3. DESIGN
3.1 OWNERSHIP
3.1.1 This equipment is a standard product of the manufacturer and shall require either no change or minor design changes to meet requirements of these specifications. Therefore, ownership of the design will remain with the manufacturer.
3.2 General Design Standards
3.2.1 DEVIATION FROM PRODUCT: Modifications to the manufacturer’s standard design to achieve requirements as specified in this document are only permissible as dictated by good design practice. For example, mounting a 20-hp motor in a power train designed and normally using a 10-hp motor would not be acceptable.
3.2.2 UNITS OF MEASURE: Dimensions and capacities in this purchase are given in the English-US (in-lb) system. All dials, gauges, and drawings shall be in the English-US system or both the English-US and the metric systems, unless otherwise specified in this document.
3.2.3 ID DATA PLATE: The equipment shall include a main data plate which will include the following data as a minimum requirement (additional information is acceptable): Manufacturer Name, Manufacturer’s Dunns and
Bradstreet Number, Manufacturer’s Model Number, Manufacturer’s Serial
Number, Year of Manufacture, Contract Number, Machine Weight. This information is necessary for compliance with the governments Unique
Identification Program (UID).
3.2.4 DATA PLATES: All instruction, data, and identification plates and labels attached to this equipment and its controls shall be manufactured of corrosion and oil resistant metal or plastic material. All wording shall be in the
English language using plain, bold face lettering. Lettering shall be permanent and have a contrasting background.
3.2.5 ITEM UNIQUE IDENTIFICATION (IUID) REGISTRATION: The
contractor shall register the equipment in the IUID Registry (as one single system). IUID registration requires the contractor to input Cage Code, Model
Number, and Serial Number into a Government Database to allow for asset and inventory tracking. IUID Registry of the equipment shall be performed at http://dodprocurementtoolbox.com/site/uidregistry/. Training for IUID is available in https://wawftraining.eb.mil. IUID registration of this equipment is required prior to final payment in the Wide Area Work Flow (WAWF). The contractor shall also affix a machine readable 2-dimensional (2-D) matrix representing the IUID registry to the machine. The IUID 2-D matrix may be included on the ID Data Plate outlined in paragraph 3.2.4.
3.2.6 UTILITY CONNECTION: Equipment supplied to the Rock Island
Arsenal will have single point shut-off for each utility supplied to a system. This http://dodprocurementtoolbox.com/site/uidregistry/ https://wawftraining.eb.mil/ means that equipment constituting a single system shall be wired to a single main electrical disconnect point, plumbed to a single pneumatic shut-off valve, etc…
This will be referred to as the “point of first connection”. Each type of power source may have only one point of first connection. E.g. (1) pneumatic shut-off valve, (1) water supply shut-off valve, (1) electrical disconnect, etc… Each point of first connection shall be clearly labeled on the system and shown in the safety lockout portion of the documentation package. These points must be located on a stationary component and positioned such that they will not create a hazard to personnel during normal operation of the system. The first connection points shall be accessible from the shop floor without the use of ladders, steps, or stools. Access cannot be hampered by operation of the system.
3.2.7 UTILITY CONNECTION LABOR: Rock Island Arsenal shall provide only such labor and materials as will be needed to connect facility utilities to each point of first connection of the system. The supplier will be responsible for all connections beyond the point of first connection for each utility.
3.2.8 UTILITIES AVAILABLE: Rock Island Arsenal shall be responsible for providing the following:
3.2.9 Connection of 460-V, 60-Hz, 3-Ph AC electrical power to the fused or breaker type disconnect switch required in the ELECTRICAL DISCONNECT paragraph of this purchase description. Connection does not include filters, surge protection, or any peripheral equipment necessary to make the equipment functional.
3.2.10 Connection of approximately 80-psi compressed air to a single point for each system, if needed. Connection does not include filters, dryers, or any peripheral equipment necessary to make the equipment functional.
3.2.11 ELECTRICAL DISCONNECT: The equipment shall be equipped with a manual, fused or breaker type disconnect switch, readily accessible to the operator, which will deactivate the entire equipment. It shall be located no more than 6-ft 7-in from the floor to the highest point the control device. It shall be capable of being locked in the de-energized state (OFF) only.
3.2.12 CONDUIT: Flexible conduit is not permitted in exposed areas. All wires, cables, and hoses will be enclosed by rigid, oil-proof protection, except where flexibility is necessary for operation of the equipment. Flexible wires, cables and hoses shall be arranged to prevent draping or tripping hazards.
3.2.13 SERVICE ACCESS: Components subject to periodic adjustment, replacement, or servicing shall be readily accessible. Meaning that experienced personnel can access the part after no more than 30-min of labor. If any special tools or equipment are necessary to access these components, said equipment will be supplied as part of the system and provided with a proper storage location within the system.
3.2.14 DEFLECTION: The system shall recover from distortion and deflection at no load. The machine and its components shall be sufficiently rigid that work piece finish and tolerances are not impaired by machine vibration.
3.2.15 NEW EQUIPMENT: The equipment furnished under this purchase description shall be new and unused.
3.2.16 COMPONENT ENVIRONMENT: Under no circumstances shall a
component be used in an application not recommended by the component manufacturer. Components shall not be subjected to conditions of operation beyond the recommendations of the manufacturer, such as excessive heat, lack of lubrication, over-loading.
3.2.17 REPLACEMENT COMPONENTS: All replaceable components shall be manufactured to definite standards for tolerance, clearance, and finish, enabling components to be field installed without further machining.
3.2.18 CASTINGS AND FORGINGS: All castings and forgings shall be free of defects, scale, and mismatching. No process such as welding, peening, plugging, or filling shall be used for reclaiming any defective part for use in this equipment without the prior written consent of the contracting officer.
3.2.19 SURFACE BUILDING AND COATINGS: Welding, brazing, soldering, coating or plating shall be employed only where specified in the original design.
These operations may not be employed as a means of reclaiming a defective part.
3.2.20 FASTENING DEVICES: All screws, pins, bolts, and similar parts shall be installed in such a manner as to prevent change in tightness. Those devices subject to removal or adjustment shall not be swaged, peened, staked, or otherwise permanently deformed. They shall not be installed using permanent bonding adhesives.
3.2.21 CLEANING AND DEBURRING: All surfaces of castings, forgings, molded parts, stampings, and welded components shall be cleaned and free from sand, dirt, fins, flash, scale, flux, and other harmful or extraneous materials. All edges shall be either rounded or beveled unless sharpness is required to perform a necessary function. Except as specified herein, the condition and finish of all surfaces shall be commensurate with the manufacturer’s commercial practice.
3.2.22 PAINTING: All unfinished surfaces of the equipment shall be painted with a lead free and chromium free commercial grade of metal primer and a minimum of one finish coat. The color shall be in accordance with the manufacturer’s standard commercial practice, or as necessary to maintain compliance with OSHA regulations, as applicable.
3.2.23 FILTRATION/REGULATION: Equipment requiring filtered or regulated energy sources shall be supplied with the components necessary to perform this function. E.g. the equipment shall be supplied with a Filter, Regulator, Lubricator (FRL) device, if filtered, lubricated, regulated pressurized air is required for the efficient, proper operation of the equipment. These devices shall be located on the equipment side of the lockout devices at the points of first connections.
3.2.23.1 Equipment which requires compressed air shall have a regenerative type desiccant or refrigerated compressed air dryer capable of drying air down to 35°F pressure dew point, minimum, from air entering the equipment at 110°F, and capable of supplying air to the rated standard cubic feet per minute (SCFM) of the equipment. The unit shall purge condensate automatically. In the case of the latter, the refrigerant used shall not be a Class I or Class II, ozone depleting substance. The air dryer shall be connected and/or piped to the equipment by the contractor.
3.2.23.2 Equipment which requires a high quality constant power source shall have proper isolation and/or power conditioning equipment for the power service designated in this description. All electrical equipment shall have a power factor (ratio of real power to apparent power) of no less than 80%, as read at the equipment main disconnect. Equipment with a power factor of less than 80% shall be fitted with suitable power factor correction capacitance, sized on the basis of the equipment inductive AC load.
3.2.24 DIALS AND GAUGES: All scales, dials, and gauges shall be manufactured of corrosion and oil resistant material. All wording shall be in the
English language using plain, bold face lettering. Lettering shall be permanent and have a contrasting background.
3.2.25 HANDWHEELS: Hand-wheels turned in a clockwise rotation shall produce a linear motion, of the controlled component, to the right, away, or upwards. If rotary motion is produced by the hand-wheel, clockwise rotation of the hand-wheel shall produce clockwise movement of the controlled component.
3.2.26 CONTROL LEVERS: Control levers shall move in the same direction as the motion of the controlled component.
3.3 Safety, Security and Environmental
3.3.1 SECURITY: The RIA-JMTC is an Army installation subject to Department of Defense safeguards, various precautions, and plant protection measures. All of the below requirements will be necessary of contractors visiting RIA to satisfy requirements of this purchase description;
Additional requirements will be placed on contractors requiring access to the Army Network, or
Common Access Card (CAC), as specifically detailed below. At all times during the execution of this work, contractor personnel will maintain adequate plant protection devises to minimize espionage, sabotage, and other malicious destruction and damage. The contractor shall comply with all security requirements of the Rock Island Arsenal. Rock Island Arsenal island-wide
Force Protection levels may be adjusted/changed at any time, which may cause possible delays and will directly affect procedures for accessing the island.
3.3.1.1 Access and General Protection/Security Policy and Procedures: The contractor and any associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Director of Emergency Services. All contractor employees must comply with all personal identity verification requirements (IAW FAR clause 52.204-9) as directed by
Department of Defense (DoD), Headquarters Department of the Army (HQDA), and any local policy. If the Force Protection Condition (FPCON) changes, the Government may require changes in contractor installation access, security matters, or security processes.
3.3.1.2 Access to RIA: Contractor and all subcontractor employees performing work at
RIA shall comply with adjudication standards and procedures using the National Crime
Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening
Database (TSDB) and any applicable installation, facility access screening and local security policies and procedures. The JMTC Representative shall provide guidance to complete the Access Control Records Check request Form though the Rock Island
Arsenal Directorate of Emergency Services.
3.3.1.3 Random Antiterrorist Measures Program (RAMP) participation: Contractor personnel are subject to RAMP security program (i.e. vehicle searches, wearing of ID badges, etc.). Contractor shall comply with any, and all instructions issued by the Rock
Island Arsenal Police Department. The RAMP is discussed in the RIA-JMTC Anti-
Terrorism Training.
3.3.1.4 During FPCONs levels of Charlie or Delta, services may be discontinued/postponed due to a higher National or local security threat. Services will resume when FPCON Level is reduced to Bravo, or lower. FPCON levels are described in Anti-Terrorism Level I Training.
3.3.1.5 Contractor personnel shall return all Installation Badges and access passes as soon as possible prior to contract completion. RIA-JMTC electronic keys and access passes are accountable items, shad shall be returned within 24-hours of no longer being needed.
Items will be returned to the JMTC Representative, or paced in a drop box at a RIA-
JMTC access point.
3.3.2 SECURITY TRAINING: The contractor shall complete the following training:
3.3.2.1 Anti-Terrorism, Level I: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete Anti-Terrorism (AT) Level I Awareness training. The JMTC
Representative will be provided a copy of the Rock Island Arsenal –Joint Manufacturing and Technology Center (RIA-JMTC) AT Level I Awareness Training and assure that the training is complete. The contractor shall sign a memorandum of record for each contractor employees and subcontractor employee to the RIA-JMTC Operations Center prior issuing any electronic keys, or access pass being authorized.
3.3.2.2 iWatch (See Something, Say Something) Training: The Contractor and all associated subcontractors shall complete iWatch Training. iWatch Training shall be provided during the Anti-Terrorism Training.
3.3.2.3 For Contractors requiring Common Access Card (CAC): No CAC will be issued in relation to this project.
3.3.3 FEDERAL MARIJUANA LAWS REMAIN UNCHANGED: Note: Rock Island Arsenal is under the exclusive federal jurisdiction of the United States. Under federal law, marijuana is still defined as a Schedule I drug, and possession and use of marijuana is still illegal. Any person using or in possession of marijuana on Rock Island Arsenal may be criminally prosecuted in federal district court. In addition, such individuals may be permanently barred from entering
Rock Island Arsenal.
3.3.4 REAL ID: Starting 03-May-2025 all personnel entering Rock Island Arsenal will be required to show a Real ID form of identification.
3.3.5 INDUSTRY AND REGULATIONS: The equipment shall comply with the most current
(at the time of contract award) of all local, state, and federal laws and regulations.
3.3.6 MATERIAL EXCLUSIONS: The equipment shall not contain polychlorinated biphenyl
(PCB), ozone depleting substances (Class I or Class II), or asbestos materials.
3.3.7 SAFETY REGULATION COMPLIANCE: The contractor shall comply with standard
OSHA and RIA safety standards, including conforming to confined space work requirements when applicable.
3.3.8 SAFETY LOCKOUTS: Each point of first connection shall be designed and constructed to allow the utility to be completely isolated from the equipment. This isolation shall be insured by application of a standard key locking padlock. The device(s) shall only be lockable in the de-energized (OFF) condition.
3.3.9 LOSS OF PRESSURE: Hydraulic and pneumatic circuits shall be designed such that loss of pressure, or pressure surges, shall not cause a hazard. Means shall be provided to prevent operation of the equipment with insufficient pressure, if such operation could cause a hazard.
3.3.10 TRAPPED ENERGY: Means shall be provided for the controlled release of stored energy. This energy may be in the form of, but not limited to, air and hydraulic pressure accumulators, capacitors, springs, counter balances and flywheels. When appropriate, a label shall be affixed to the stored energy source to identify the hazard.
3.3.11 WORKING RANGE: Hydraulic and pneumatic components shall be selected, which cannot be adjusted outside the safe working range of the circuit and/or equipment.
3.3.12 EMERGENCY STOP: The system will incorporate a clearly identified, red, mushroomed, control button with a yellow backing plate at every operator work station. Upon momentary operation, any emergency stop button shall de-energize all machine motions and override all other controls without creating additional hazards. All motion stopped shall be restarted by the deliberate action of the operator (requiring manual reset). No other red mushroomed buttons shall be allowed on the equipment. It is preferred that there is no other red buttons of any type.
3.3.13 CONTROL GUARDS: Controls shall be guarded against accidental operation.
3.3.14 OPERATOR REACH: Controls shall be within reach and located such that the operator, when in the normal operating position, is not required to reach past moving parts, which may cause injury.
4. COMPONENT SPECIFICATION
Equipment: The supplier shall furnish all equipment normally considered by him to be standard for his machine unless identified in this requirement to be of specific manufacture. The following equipment shall be provided in addition to the equipment specified in other sections of this purchase description, which may not be standard. The inclusion of standard equipment in this paragraph is inadvertent and should not be construed to allow duplication.
4.1 Dimensions:
4.1.1 DOOR ACCESS: The equipment shall be shipped either assembled or disassembled to pass through a door 12-ft wide by 12-ft high, and shall not exceed 25-ft in length.
4.1.2 COMPONENT WEIGHT: The maximum weight of any one piece shall not exceed 1,700-lbs.
4.1.3 INSTALLED FLOORSPACE: When installed complete, the equipment shall be contained .in an area 96-in long and 48-in wide, excluding the operator’s area. Maximum height shall not exceed 91-in. Width is defined as front to back from the operator’s normal operating position.
4.2 System Features:
4.2.1 The system shall have large measuring workstage measuring travel: 20” horizontal and 8” vertical travels (500mm x 200mm) as a minimums travel.
4.2.2 The system shall have a screen diameter of 30” (763mm) with precision cross lines and calibration markings as a minimum screen size.
4.2.3 The system shall have a top plate work stage of 32” x 8” (820mm x
200mm) as a minimum work stages.
4.2.4 The system shall have maximum Load Capacity shall allow for 330 Pounds
(150 kg) evenly distributed at 17” (440 mm) capacity between centers as a standard minimum.
4.2.5 The system shall have a focus travel of 3” (75mm) as a minimum.
4.2.6 The system shall have helix angle adjustment of +/-15 degrees in a swiveling workstage with a Vernier Scale of 5-minute resolution as a minimum standard.
4.2.7 The system shall have a measurement display system providing a linear
Heidenheim glass scale with 0.001 resolution for 0.5 micron (0.00002”) with
Quadra-Chek read out systems as a minimum.
4.2.8 The system shall have floor standing system as a standard.
4.2.9 The system shall have a fan cooled halogen illumination profile that is switchable between low and high intensities with a yellow/green filter as a standard. Also, the surface shall have a fan cooled fiber optic system.
4.3 Lens to be provided -
4.3.1 The system shall provide a 10x, 20x, 25x, 31.2x, 50x, and 100x lenses as minimums.
4.4 Stage Accessories -
4.4.1 The system shall have precision centers and vees as a minimum. See image “A” below on left.
4.4.2 The system shall have precision centers and Vees as a minimum. See image “D” below on right.
Image A→ Image D
4.5 Installation Start Up, Calibration PM Training
4.5.1 Installation start up, Calibration and Preventative Maintenance Training to be at RIA - JMTC site
4.5.2 Training: eight hours (comprised of two four-hour class sessions) at minimum.
4.6 Digital Readout - The optical comparator shall come with a digital readout that performs highly precise and accurate 2 axis measurements which allow recording of desired features as a minimum.
4.6.1 The digital read out shall have a resolution of 0.00005” (0.001”) as a minimum.
4.6.2 The digital read out shall have single key calculation for angles, radius or diameter, and distance as minimums.
4.6.3 The digital read out shall have skew function for rapid part alignment correction, have the display to be in polar or Cartesian coordinates and have a
200-point feature memory as a minimum.
5. INFORMATION TECHNOLOGY SYSTEMS AND SUPPORT
5.1 Installation IT Support:
5.1.1 PERSONNEL: RIA-JMTC will not provide the technician credentials to access the workstation. Access to the workstation will be provided by the RIA-
JMTC IT Support Staff escort. Removable Media e.g., CD/DVD/USB/SD/External hard drive will be scanned prior to use. Programs and software must be ran from RIA-JMTC approved/provided media or
CD/DVD(s). Contractor Devices will not be allowed to connect to the RIA-
JMTC network nor will they be allowed to connect to RIA-JMTC equipment other than to scan and transfer media.
5.2 INSPECTION/FINAL ACCEPTANCE:
5.2.1 LICENSING: The software/ hardware license shall not have an internet connection. A license dongle or license file must be provided for offline use.
5.3 Media/ Devices
5.3.1 REMOVABLE MEDIA: Removable media consists of the following: CD, DVD, USB, SD, and External Hard Drives. Removable media shall be scanned prior to use. Programs and software must be ran from RIA-JMTC approved/ provided media or CD/ DVD(s).
5.3.2 CONTRACTOR DEVICES: Contractor Devices will not be allowed to connect to the RIA-JMTC network and they will not be allowed to connect to
RIA-JMTC equipment other than to scan and transfer media.
5.3.3 NON-GOVERNMENT OWNED SYSTEMS OR DEVICES: The
contractor shall comply with AR 25-1 and AR 25-2. The contractor shall not install or connect non-Government-owned computing systems or devices to
Government networks without the JMTC Representative’s coordination and obtaining the proper authorization from the appropriate Information System
Security Manager (ISSM), ensuring that all software has a Government Assess
Only Authorization. The non-Government-owned computing systems or devices include, but are not limited to, personal or Contractor-owned thumb drives e.g., memory sticks, flash drives, Universal Serial Bus (USB) drives, jump drives, pen drives, removable or external hard drives, Personal Digital Assistants (PDA), PC
Cards/Express Cards, MP3 players, cell phones, digital media, floppy disks, compact disc (CD)/digital video disk (DVD) burners, optical recordings, photo flash cards, laptops, or any devices that can store data.
5.4 INFORMATION ASSURANCE AND ACCREDITATION:
5.4.1 Non-Government-Owned computing systems or devices: The Contractor shall comply with AR 25-1 and AR 25-2. The Contractor shall not install or connect non-Government-owned computing systems or devices to Government networks without a government representative coordinating and obtaining proper authorization from the appropriate Information System Security Manager
(ISSM), ensuring that all software has a Government Assess Only Authorization.
The non-Government-owned computing systems or devices include, but are not limited to, personal or Contractor-owned thumb drives e.g., memory sticks, flash drives, Universal Serial Bus (USB) drives, jump drives, pen drives, removable or external hard drives, Personal Digital Assistants (PDA), PC Cards/Express
Cards, MP3 players, cell phones, digital media, floppy disks, compact disc
(CD)/digital video disk (DVD) burners, optical recordings, photo flash cards, laptops, or any devices that can store data.COMPONENT SPECIFICATION
5.4.2 System Accreditation and Re-Accreditation: The Contractor shall assist in providing system accreditation documentation such as required artifacts and shall answer technical questions required for registration for accreditation. All documents shall be IAW Chapter 5, and Appendices D and E, AR 25-2, Information Systems Security (dated 3 August 2007) and DOD Instruction
8510.01, Risk Management Framework (RMF) Program or future DOD regulation that supersedes these regulations. The Contractor shall assist in performing yearly reviews of the accreditation, or whenever changes/additions are made to the system. The Contractor will assist in preparing risk assessments, as required.
6. APPROVAL/SHIPPING
6.1 Shipping
6.1.1 RESPONSIBILITY: The contractor is responsible for delivery of the equipment to the Rock Island Arsenal. Adequate preserving of equipment surfaces, packing, marking, and skidding of materials for shipment shall be the responsibility of the contractor. If special lifting devices, such as hooks or eyes, are required for ease of handling, they shall be supplied with the equipment. Any special devices shall be returned to the contractor upon request only if they will not be required for future movement of the equipment, and at the contractor’s expense.
6.1.2 SHIPPING SCHEDULE: Be aware, the Rock Island Arsenal will only off-load equipment arriving between 6:00 am and 12:00 am (noon), local time on
Mondays through Thursdays except holidays. For information concerning holidays, the contractor should consult the contracting officer. There is no place to stage transporting vehicles awaiting the arrival of contractors. All equipment shall be delivered at the same time, meaning the same day (multiple trucks are acceptable) unless pre-authorized to deliver on multiple days by the RIA-JMTC contracting officer.
6.1.3 RECEIVER: All shipments to Rock Island Arsenal including installation tools and/or replacement parts, as well as the original shipment of the equipment, shall be marked “ATTN: JMTC Representative will be assigned at time of award”. Items not correctly marked are subject to being returned at the vendor’s expense.
6.1.4 ARRIVAL INSPECTION: Upon receipt of equipment at Rock Island
Arsenal, a preliminary inspection shall be performed to determine condition and/or count. This inspection shall be performed by Rock Island Arsenal personnel.
6.2 Installation
6.2.1 SITE PREPARATION REQUIREMENTS: The contractor shall be solely responsible for any necessary site inspections required for determining the specifications of work that must be completed prior to final system installation.
The contractor will then provide detailed information of any preparation work that the vendor must perform prior to system installation to Rock Island Arsenal.
6.2.2 PREPARATION EXECUTION SUPPORT: Rock Island Arsenal will support the preparation portion of the installation by providing utilities to the points of first connection.
6.2.3 LABOR AND MATERIAL: The supplier is solely responsible for providing all labor, materials, hardware, tools, and equipment necessary for complete installation of this system except as specifically listed in this document as being provided by the Rock Island Arsenal.
6.2.4 SUPERVISION: Supervision of the installation process will be the responsibility of the contractor. Rock Island Arsenal shall retain the right to periodic inspection and evaluation of the process, as it deems necessary.
6.2.5 OFF-LOADING/PLACEMENT: Off-loading of the equipment from the delivery vehicle, and placement of the equipment in position for the installation is the responsibility of the contractor. The contractor shall not be allowed to use government equipment to accomplish this work.
6.2.6 OFF-LOADING/PLACEMENT OPTION: At the request of the
contractor, Rock Island Arsenal will perform the off-loading and placement of the equipment.
6.2.6.1 Any special requirements or precautions to be observed shall be the responsibility of the contractor to provide.
6.2.6.2 The contractor or his representative may be present during this process; however, such person will be responsible for being present upon arrival of the equipment at Rock Island Arsenal. Off-loading and placement shall not be delayed to allow arrival of the contractor or his representative.
6.2.6.3 If, due to contractor caused difficulties, the equipment or components of the equipment must be moved, removed or replaced by Rock
Island Arsenal after initial placement, the contractor shall be billed for such work at current Rock Island Arsenal labor and overhead rates.
6.2.7 LIABILITY: In any case, the equipment remains the property of the contractor, and the contractor shall assume all responsibility and liability for the equipment and the work performed upon it. The government shall be held harmless for any damage done to the equipment at any time up until final acceptance of the equipment by Rock Island Arsenal, except in the case of intentional damage and/or gross negligence on the part of Rock Island Arsenal personnel.
6.2.8 SET-UP: The contractor shall be responsible for set-up and connection of the equipment beyond connections of the utilities to the points of first connection.
6.2.9 SECURITY: The RIA-JMTC is an Army installation subject to
Department of Defense safe guards, various precautions, and plant protection measures. At all times during the execution of this SOW, the contractor will maintain adequate plant protection devises to minimize espionage, sabotage, and other malicious destruction and damage. The contractor shall comply with all security requirements of the Rock Island Arsenal. Rock Island Arsenal Island-wide Force Protection levels may be adjusted/changed at any time, which may cause possible delays and will directly affect procedures for accessing the Island.
6.2.10 Delivery Hours or Service Hours: Service calls, equipment installation, training, and equipment delivery (where the contractor offloads) will only be allowed from 0600 – 1530, Monday through Thursday, except for Government
Holidays. Deliveries of items where the contractor has opted for Government
“off-loading option”, must be received before 1200 hours. These hours are subject to change, however, the Government will notify the contractor of such changes. The vendor will contact the designated JMTC Representative to obtain an electronic key for their representative (i.e. delivery driver) in order to have access to the facility. Deliveries and service calls outside the normal hours stated above will be coordinated with the JMTC Representative to address any emergency situations."
6.3 Completion
6.3.1 Final acceptance of the equipment shall occur after the following:
6.3.1.1 Set-up completion by the contractor.
6.3.1.2 Successful completion of performance testing at Rock Island Arsenal.
6.3.1.3 Final inspection approval by the government representative or inspector. This is to verify full compliance with this description to include amendments and modifications to the final contract. The government representative shall perform any and all tests he deems necessary to insure compliance with this description and industry standards to include, but not limited to ease of control, convenience of operation, safe operation, and adequacy of lubrication devices.
6.3.1.4 All required training is complete.
6.3.1.5 Complete documentation packages are delivered.
7. TRAINING
The contractor shall provide instruction in proper operation and maintenance of the equipment without additional cost to the government. Training shall be of sufficient duration that the recipients are able to demonstrate a reasonable level of competence as determined by the equipment installer and/or the inspector. Acceptance may be delayed as a result of inadequate training.
7.1 Schedule
Training shall be coordinated with the Rock Island Arsenal. Daily training shall begin no later than 6:30 a.m. CST and shall continue until at least 2:15 p.m. CST. This is required to get full coverage of the 1st shift of operation at RIA-JMTC. If training does not begin until after the stated time, RIA-JMTC may at its option require additional training at a different time to compensate for the loss of training caused by the late start. This may include more time than what is represented by the delay (e.g. a 1-hr delay may require 2-hrs later to impart the knowledge lost).
7.2 Location
All training shall be performed at the Rock Island Arsenal. It shall be performed using the equipment purchased in this description.
7.3 Type: Each type of training shall be given independently. Rock Island Arsenal shall coordinate with the contractor to provide the proper personnel for each type of training. The following types of training shall be provided by the contractor.
7.3.1 OPERATOR: Training shall be provided by the contractor for (5) operators. This shall include instruction on the safe, efficient operation of the equipment delivered. The trainees supplied by RIA-JMTC shall be familiar with machine operation, but not necessarily with the style or type of controls provided with the equipment. (E.g. for a new CNC lathe, the operator will be familiar with CNC lathe operation, but may have no experience with a Fanuc control system.)
7.3.2 PROGRAMMING: If the equipment includes a programmable controller, programmer training shall be provided, separate from the operator training for (2) personnel. If programming is normally performed by the operator only, then this training may be combined with the operator training.
7.3.3 MAINTENANCE: Mechanical and electrical control and diagnostic maintenance training shall be provided by the contractor. This shall include information on troubleshooting and preventive maintenance procedures. This shall be provided for (2) personnel.
8. SERVICE
8.1 Service/Support Requirements
The contractor shall have as a minimum, a verifiable service/repair capability which meets or exceeds the following requirements:
8.1.1. STAFF: Staffed by qualified, English-speaking personnel fully knowledgeable in the service/repair of the equipment offered.
8.1.2 TELEPHONE ACCESS: Telephone access to service/repair personnel shall be available for consultation during Rock Island Arsenal normal working hours. Rock Island Arsenal normal working hours are 8:00 am CST to 3:00 pm
CST, Monday through Friday, except legal federal holidays.
8.1.3 SITE RESPONSE: Physical, on-site response shall be possible within 48-hrs of notification that service/repair of the equipment is necessary.
8.1.4 MAINTENANCE PARTS: Parts necessary for periodic replacement such as belts, hoses, filters, and other parts normally considered as spare parts, by the manufacturer, shall be stocked and available for shipment.
8.1.5 PIOR HISTORY: Said service/repair capability shall have been available to the general public prior to the issue date of this purchase description. Adequate proof of prior availability shall be provided upon request.
File details come from the government source that posted it. Updated .