Attachement 1_SOW.pdf
PDF 219 KB Posted
- Solicitation number
- 70Z0G820QPCV62500
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 70Z0G820QPCV62500_A Schedule.pdf | ||
| RFQ 70Z0G820QPCV62500_A.pdf | ||
| RFQ 70Z0G820QPCV62500 Schedule.pdf | ||
| Attachment 2_Pricing Spreadsheet.xlsx | XLSX spreadsheet | |
| Attachment 3_Sta Oregon Inlet Boat Ramp Dock.png | PNG image | |
| RFQ 70Z0G820QPCV62500.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Station Oregon Inlet
Scope of Work
1. GENERAL REQUIREMENTS: The work consists of providing all labor, materials and equipment as required to Replace Two (2) Dock Pilings located at USCG Station Oregon Inlet.
Highway 12 South, Nags Head, NC 27959.
2. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: Upon acceptance the contractor shall commence work no later than twenty 21 days after notice to proceed and complete the project within 30 days of contract award.
3. SCOPE OF WORK:
3.1: Using best industry standard for replacing dock pilings, unfasten and remove two deteriorated dock pilings from the Stations Boat Ramp Dock as depicted in drawing. Remove pilings and dispose of offsite in accordance with any applicable federal, state, and/or local regulations.
Note: One of the dock pilings is separated at the mud line; this requirement is to remove the piling in its entirety, including the portion below the mud line.
3.2: At the same locations of the removed pilings, install two new pilings and re-fasten the newly installed piling to the stringer. The new pilings shall meet the following specification: 12-
14 inch top by 30 foot treated round piles. All hardware/fasteners used in the execution of this requirement shall be NEW hot dipped galvanized.
4. SITE VISIT: All bidders are strongly encouraged to visit the site to verify any/all quantities and determine actual dimensions and the nature of the work required before submitting quotes.
Interested parties shall make arrangements for a site visit with MK1 Jared Ebel at 252-982-6354 or by email at: Jared.S.Ebel@uscg.mil. Site visits shall be completed on Thursday, July 23rd, 2020 & Friday, July 24, 2020 from 8:00AM – 3:30PM (EST).
5. DESIGNATED CONTRACTING OFFICER’S QA EVALUATOR (QAE)
REPRESENTATIVE: The designated contracting officer’s QAE representative and Point of
Contact for this project is MK1 Jared Ebel (252-982-6354). Inquiries concerning any phase of the specification before or after award shall be made to MK1 Jared Ebel.
6. CONDITIONS AFFECTING THE WORK: The Offeror should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, the general and local conditions which can affect the cost of the work thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The government will assume no responsibility for any understanding or misrepresentations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the request for quotes, the specification or related documents.
7. AFTER AWARD OF THE CONTRACT: The contractor must immediately notify the contracting officer’s QAE representative of his intended start date. The work shall be done in accordance with the specification.
mailto:Jared.S.Ebel@uscg.mil
8. ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modify, or otherwise affect the terms of this contract.
9. WORKMANSHIP: All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory to the Contracting Officer.
10. PERMITS: The contractor shall without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state and local laws.
11. CLEAN UP: All trash and debris shall be removed from the site daily. The job site shall be left in a clean and neat manner.
12. WORK OUTSIDE REGULAR HOURS: If the contractor desires to carry on work on
Saturday, Sunday, holidays or outside the unit’s regular hours, must submit their request in writing to the Contracting Officer’s QAE Representative for approval consideration. The contractor shall allow ample time to enable satisfactory arrangements to be made by the government for inspecting the work in progress.
13. UPON COMPLETION OF WORK: Contact the Contracting Officer’s QAE
Representative to arrange for inspection/acceptance of work.
14. IDENTIFICATION OF CONTRACTOR PERSONNEL AND VEHICLES: The contractor shall provide a detailed list of all employees to the QAE Representative five (5) days prior to commencing work. The employee list shall contain the employee’s full name, date and place of birth, current address and last four (4) of SSN. The Station Oregon Inlet Security
Officer will be given a copy of the employee list and a pass will be issued for entry. Each contractor provided vehicle or towed trailer shall show the contractor’s name so that it is clearly visible on the vehicle. A valid state license plate and safety inspection sticker is required. All vehicles operated on government property shall be maintained in a good state of repair.
15. SAFETY REQUIREMENTS:
1. Responsibilities:
a. All contractors working on CG Station Oregon Inlet shall abide by all federal safety regulations as published by the Occupational Health and Safety Administration, 29
CFR 1910 (series) and 29 CFR 1926 (series). Contractor written safety programs shall be reviewed by the Base Safety Officer prior to starting work.
b. Written notification must be provided to the CG Sta Oregon Inlet Base Safety Officer, MK1 Jared Ebel in their capacity as Fire Marshal of any activity that could potentially cause fire or explosion or that changes or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are: a fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the unit, and blocking of any egress routes or emergency vehicle routes. Inclusion of this information in the contract constitutes written notification as long as the outsource review sheet is signed by Base Safety Officer.
c. Copies of the following must be provided to the Base Safety Officer prior to starting work in affected areas: Confined Space Entry Permits, Hot Work Chits, and Dig
Chits. Confined space clearance must be conducted by a certified marine chemist and permit required spaces will have a copy of the permit posted on site during work. Hot work will only be conducted with permission and a fire watch must be posted during work.
d. Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a contractor on CG Station Oregon Inlet. A Facilities Division representative is required for all contractor Lock Out/Tag Out needs.
2. Rights:
a. Every employee working on CG Station Oregon Inlet has the right to a safe and healthy work place. The contractor has the responsibility and right to stop unsafe work.
QAE’s and the Safety Officer may also institute a work stoppage relating to unsafe practices or immediate danger to life and health situations.
16. ENVIRONMENTAL PROTECTION REQUIREMENTS:
a. All contractors working on CG Station Oregon Inlet shall abide by all federal environmental regulations as published by the Environmental Protection Agency, 40
CFR (series). Contractor written environmental management and pollution prevention programs shall be reviewed by the Environmental Protection Specialist
Mr. Todd Ogle 252-247-4534 prior to starting work and must be in accordance with the Unit Environmental Guide.
b. Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on CG Station Oregon
Inlet. Some examples of qualifying activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.
c. Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas: Material Safety Data Sheets, permits, and notices of intent.
d. Hazardous materials used by a contractor are required to be disposed of by that contractor. Disposal must be in accordance with federal, state, and local guidelines.