This document is a pre-planning study for a new Facilities Management/Warehouse building for Christopher Newport University (CNU) in Virginia. The study was conducted by HBA Architecture and Interior Design, Inc. to define the space needs requirements, including adjacency requirements, for the proposed new building. The existing Facilities Management/Warehouse building is at the end of its useful life and no longer meets the functional needs of the departments located within. The pre-planning study outlines the current and future space requirements for Facilities Management Administration, Housekeeping, Carpentry, Electrical, HVAC, and Plumbing shops, as well as the Warehouse and Mailroom functions. The study includes block diagrams, site development and phasing plans, applicable codes and regulations, and an order of magnitude cost estimate for the new building, which is projected to be approximately 62,000 SF.
The related state and local contract opportunity is for A/E services for the preliminary design through construction administration of the new Plant Operations and Warehouse building. The contract is being solicited through a Request for Proposal (RFP) process by the City of Newport News, Virginia. The RFP number is 242-18704-000, and the contract number is 1261/71621. No additional details are provided regarding pricing terms, set asides, incumbents, funding sources, or other salient information.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attach B - dgs-30-360_06-20_small-and-diverse-businesses-participation.xlsx | XLSX spreadsheet | |
| Attach D - RFP Question Form.docx | DOCX document | |
| Attach A - dgs-30-004_03-19_ae_data_forms.xlsx | XLSX spreadsheet | |
| Attach F - Proprietary & Confidential Form.docx | DOCX document | |
| Attach E - 2024 campus map.pdf | ||
| AE RFP - Plant Ops and Warehouse (3).pdf | ||
| Attach C - dgs-30-384_01-21_eva-regist1 (1).docx | DOCX document | |
| Attach H - AE Terms and Conditions.docx.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COLLABORATIVE DESIGN + EFFECTIVE SOLUTIONS THAT ENHANCE | YOUR BUSINESS OUR COMMUNITY THE ENVIRONMENT
One Columbus Center Suite 1000 Virginia Beach, VA 23462 757.490.9048 www.HBAonline.com
5001 Libbie Mill East Boulevard Suite 110 Richmond, VA 23230 804.367.4027
PRE-PLANNING STUDY
FOR
CHRISTOPHER NEWPORT UNIVERSITY
FACILITIES MANAGEMENT/WAREHOUSE BUILDING
Plot
FINAL REPORT
HBA PROJECT #22105
Plot
February 1, 2024
Pre-Planning Study for Christopher Newport University Facilities Management/Warehouse Building
Christopher Newport University
Pre-Planning Study
Table of Contents
Introduction/Executive Summary
Statement of Program (Space Needs Summary)
Block Diagram/Plan
Site Development/Phasing
Applicable Codes and Regulations
Cost Estimate
Facili�es Management/Warehouse Building
Introduc"on/Execu"ve Summary
• HBA was engaged by CNU to complete a preplanning study for replacement of the exis�ng
Facili�es Management/warehouse building.
• Currently, Facili�es Management/Warehouse is in a building at 11 Sweetbriar Drive that was originally constructed in 1960 and occupied by a grocery store. The exis�ng building is at the end of its useful life and is no longer serving the func�onal needs of the departments located within.
• Facili�es Management also occupies a por�on of Commonwealth Hall, a former motel building on a site adjacent to the exis�ng Facili�es Management/Warehouse site. The Mailroom func�on managed by Warehouse staff is also located in Commonwealth Hall.
• The exis�ng Facili�es Management/warehouse building is approx. 35,717 SF and currently houses the following departments. The exis�ng building plan is included herein for reference.
o Facili�es Management Administra�on which maintains and repairs all buildings, facili�es and infrastructure on campus. Facili�es Management also includes the following groups:
F.M. Housekeeping
Carpentry Shop
Electrical Shop
HVAC Shop
Plumbing Shop o Warehouse which includes supplies storage, archives storage, furniture storage, and receiving/processing of goods for the university.
• The goal of the pre-planning study is to define the space needs requirements (statement of program), including adjacency requirements, for a proposed new Facili�es
Management/Warehouse building.
• Space needs requirements (Statement of Program) were developed in workshop mee�ngs with the stakeholder departments, informa�on gathered by staff comple�on of survey ques�onnaires distributed by HBA, and tours of exis�ng facili�es.
• Space block diagrams were developed to graphically indicate the general size and arrangement of spaces for the proposed new Facili�es Management/warehouse building. The block diagrams are intended to indicate adjacency and proximity of spaces, but the diagrams do not represent a floor plan.
• An “order of magnitude” es�mate of probable project and construc�on cost at a “cost per square foot” level is included.
Facili es Management/Warehouse Building
Statement of Program (Space Needs Summary)
The space needs summary on the following pages outlines the space requirements for the proposed new facili es management/warehouse building. The space needs are grouped by department. Space needs are indicated as current (2022), an cipated 5-year needs (2027) and 10-year needs (2032). Spaces are color coded to indicate space type with different levels of gross building factors applied to each space.
The total gross building space needs requirements are as follows:
Current 59,500 SF
5-Year 60,827 SF
10-Year 61,999 SF
The proposed new Facili es Management/Warehouse building will include the following departments:
• Facili es Management Administra on – 10,376 net SF
• Housekeeping Administra on – 1,600 net SF
• Carpentry Shop – 9,162 net SF
• Electrical Shop – 1,356 net SF
• HVAC Shop – 1,432 net SF
• Plumbing Shop – 936 net SF
• Future Staffing – 3,695 net SF
• Warehouse and Mailroom (supplies storage, archives, receiving/processing) – 18,482 net SF
• Shared Spaces (Cart Storage and Maintenance) – 6,312 net SF
Block Diagram/Plan
The block diagram plan included herein represents the adjacency requirements and poten al configura on of spaces as they relate to each other and to the site. The intent is locate spaces together that require a lower height, such as office, shop spaces, and building support spaces. Higher bay spaces, such as warehouse and storage areas would also be grouped together, in addi on to being located in close proximity to the loading dock area. It is an cipated that the building would be a single story, with two building heights as described herein.
Site Development/Phasing
It is an cipated the proposed new Facili es Management/Warehouse building will be constructed on a por on of Christopher Newport University Real Estate Founda on owned property behind (east of) the exis ng Facili es Management/Warehouse building, as well as the exis ng Facili es
Management/Warehouse site. The exis ng Facili es Management/Warehouse building will be required to remain occupied and in opera on un l the Phase 1 por on of the new building is complete and designated departments are moved in. The Phase 1 por on of the building is an cipated to include the majority of the trades shop spaces, storage and warehouse spaces. The Phase 2 por on of the building is an cipated to include the remaining storage spaces, and office spaces. The Phase 2 departments will require temporary facili es on addi onal Christopher Newport University Real Estate Founda on owned property adjacent to the new building. Once all departments are relocated from the exis ng building, the exis ng building will be demolished. Phase 2 of the new building will be constructed at the area where the exis ng building once stood. Improvements to the exis ng parking area will be completed at the west end of the site.
Christopher Newport University Pre-planning Study HBA Architecture and Interior Design, Inc.
Facilities Management/Warehouse
Pre-Planning Study
Statement of Program - Draft February 1, 2024
Operations/Warehouse
Space ASF 2022 2027 2032 Comments Private Office Open Office/Cubicle
Facilities Management
Director Office 150 150 150 X
Associate Director 300 300 300 150 s.f. (2) = 300 X
Manager of Bus. Opperations 120 120 240 X
Admin Asst. Senior 208 208 208 Including interns X
Energy Manager 120 240 240 Including interns X
Sustainability Manager 120 120 120 X
Safety/Compliance Tech 64 X
Shop Supervisors 360 480 480 120 s.f. (4) = 480 X
I.T. Room 48 48 48 area estimate
Reception Area 200 200 200 large desk, area estimate
Conference Room 400 400 400 16-20 seats
Training Room 375 375 375 25 people (15) s.f. = 375
Team Space one 120 120 120 area estimate
Team Space two 200 200 200 area estimate
Copy Fax Area 48 48 48 area estimate
File Room 100 100 100
FM Storage/Parts Issue 2,500 2,500 2,500
Air Filter Storage 400 400 400 combined w/ storage & parts
Delivery Area 144 144 144 area estimate
Inventory Manager/Purchasing 120 120 120 X
Tent Storage 500 500 500 area estimate
Chemical Storage 200 200 200 area estimate
Hazardous Waste Room 144 144 144 area estimate
Locker Room 2,000 2,000 2,000 20 s.f.(100) = 2,000
Break Room 375 375 375 12 - 15 seats
Plans Room w/ Storage 900 900 900
F.M.Housekeeping
F.M. Housekeeping Manager 150 150 150 X
F.M. Housekeeping Supervisors 360 360 360 120 s.f. (3) = 360 X
F.M. Housekeeping QC & Training 120 120 120 X
F.M. Housekeeping Leads 288 430 430 area estimate 48 s.f.(6)=288 X
F.M. Housekeeping Work Shop & Stor. 400 400 400 area estimate
Washer/Dryer (2) each 140 140 140 area estimate
Carpentry
Lead Carpenter 96 96 96 X
Locksmith 64 128 128 64 s.f. (2) = 128 X
Locksmith Secured Workroom 150 150 150 area estimate
Carpenters 384 384 384 64 s.f.(6) = 384 X
Carpentry Shop 3,200 3,200 3,200 area estimate
Tool Storage Area 150 150 150 area estimate
Painters 128 128 192 64 s.f.(3) = 128 X
Paint Room w/ Spray Booth 650 650 650 area estimate
Wood, Carpet & Tile Storage 1,700 1,700 1,700 area estimate
Sign Graphic Ass't. 64 64 64 X
Senior Trades Utility 96 96 96 X
General Facilities Technician 64 192 192 64 s.f.(3) = 192 X
Welding Area 160 160 160 area estimate
Sign Shop Work Room 670 670 670
Laser Engraving Room 480 480 480
CNC Sign Shop 450 450 450 area estimate
Vinyl Sign Shop 400 400 400
Electrical
Lead Electrician 96 96 96 X
Electrician 192 192 192 64 s.f.(3) = 192 X
Electrician Assistant 128 128 128 64 s.f.(2) = 128 X
Electrical Training Area 200 200 200 area estimate
Pipe Rack Storage 280 280 280 area estimate
Light Pole Storage 300 300 300 area estimate, some outside storage
Electrical Shop 160 160 160 area estimate
HVAC
Lead HVAC 96 96 96 X
HVAC Technician 448 448 512 64 s.f.(8) = 512 X
HVAC Assistant 128 128 128 64 s.f.(2) = 128 X
HVAC Controls Tech 96 96 X
Parts Inventory 200 200 200 area estimate
HVAC Training Area 200 200 200 area estimate
HVAC Shop 200 200 200 area estimate
Plumbing
Lead Plumber 96 96 96
Plumber 128 128 128 64 s.f.(2) = 128 X
Plumber Assistant 64 64 64 X
Pipe Storage Area 280 280 280 area estimate
Pipe Shop 320 320 320 area estimate
Flammables Area 48 48 48 area estimate
Facilities Management Subtotal 24,080 24,750 25,062
University Future Staffing
Assistant Director Maintenance 0 150 150 X
Maintenance Supervisor 0 360 480 120 s.f.(2) = 240 X
Assistant Director Housekeeping 0 150 150 X
Supervisor 0 360 360 120 s.f.(2) = 240 X
Operations Support 0 250 250 X
Operations Manager 0 120 120 X
Filing in Open Area 0 19 19 area estimate
Equipment in Open Area 0 12 12 area estimate
Reception Area 0 190 190
File Room 0 64 64 area estimate
Workshop 0 400 400
Storage 0 1,500 1,500
University Future Staffing Subtotal 0 3,575 3,695 0
Warehouse and Mailroom
Warehouse Manager 150 150 150 X
Assistant Director 150 150 150 X
Storekeeper Senior 96 96 96 X
Storekeeper 64 64 64 X
Storekeeper 64 64 64 X
Technical Coordinator 64 128 128 X
Other Coordinator 192 192 192 48 s.f.(4) = 192 X
Conference Room 200 200 200 25 s.f.(8) = 200, area estimate
File Room 100 100 100 area estimate
Secure Records 1,200 1,200 1,200 area estimate
Furniture Storage 4,000 4,000 4,200 can be vertical
Warehouse Receiving / Processing 2,000 2,000 2,200 area estimate
Warehouse Storage 7,000 7,000 7,200 area estimate
Dry Storage 2,000 2,000 2,000 mezzanine may reduce area
Storage Room 150 150 150
Work Room 120 120 120 area estimate
Coffee Area 120 120 120 can also use building break room
Holliday Tree Storage 200 200 200 area estimate
Mail Room 300 300 300
Mail Room Staff 120 120 120 X
Mail Room Open Office Staff 128 128 128 64 s.f. (2) = 128 X
Warehouse and Mailroom Subtotal 18,418 18,482 19,082
Shared Spaces
Cart Storage/Forklift/Utility Trailer 5,000 5,000 5,000 to include power washer
Cart Circulation Area 1,024 1,024 1,024 area estimate
Cart Maintenance 288 288 288 area estimate
Shared Spaces Subtotal 6,312 6,312 6,312
TOTAL YELLOW PARTITIONED OFFICE 5,286 7,201 7,441
GROSSING FACTOR OF 30% 6,872 9,361 9,673
TOTAL GREEN OPEN OFFICE 816 880 944
GROSSING FACTOR OF 10% 898 968 1,038
TOTAL BLUE MAINTENANCE GARAGE 26,508 28,838 28,966
GOSSING FACTOR OF 15% 30,484 33,164 33,311
TOTAL RED WAREHOUSE 16,200 16,200 16,800
GROSSING FACTOR OF 7% 17,334 17,334 17,976
TOTAL ASSIGNABLE AREA (ASF) 48,810 53,119 54,151
TOTAL GROSS AREA (GSF) 55,588 60,827 61,999
Grossing Factor includes areas for support spaces such as mechanical, plumbing, fire sprinkler, toilet/shower and circulation.
Also includes area for physical building elements such as walls and columns.
Exterior space requirements are not represented in this spreadsheet which include:
Exterior storage space requirements
Loading dock areas
Dumpster space requirements
Applicable Codes and Regulations
Virginia Uniform Statewide Building Code (VUSBC) – Current adopted edition in effect at the time of design completion.
Construction and Professional Services Manual (CPSM) – Current adopted edition in effect at the time of design completion.
2010 ADA Standards for Accessible Design
Other State Regulations
Art and Architecture Review Board (AARB)
Baby Changing Facilities in State-Owned Buildings
Virginia High Performance Buildings Act
Electric Vehicle Parking Spaces/Charging Stations
Shielded Outdoor Light Fixtures
Cost Estimate
The estimate of probable construction cost included herein is an “order of magnitude” estimate based on historical cost data for projects of similar scope. The building and site estimated costs are based on cost per square foot values and do not represent a detailed cost estimate. In addition to the estimate of probable construction costs, there are estimated costs for other project requirements, including design and related service fees, inspection and testing services, other miscellaneous costs, and furnishings & equipment costs.
The estimated project costs also include a contingency to cover items that are unanticipated at the time of this report and an escalation factor that reflects the anticipated mid-point of construction of early
2026.
Project Cost Summary - 02-07-2024
Construction Cost
Building 62,000 SF X $400 per SF = $24,800,000
Sitework 1 LS $5,200,000 Lump Sum = $5,200,000
Construction Cost Total $30,000,000
Design and Related Service Items
AE Fees $2,067,996
Geotechnical Investigation and Report $20,000
Site Survey $10,000
Hazmat Survey $40,000
Cost Estimating $25,000
Environmental Impact Report $73,750
Design and Related Service Total $2,236,746
Inspection and Testing Allowances
Project Inspection Services $228,553
Project Testing Services $77,500
Total Inspection and Testing Services $306,053
Other Cost Allowances
Land Acquisition $400,000
Work by Owner (Landscaping) $100,000
CNU Project Management $250,000
DEB Services $150,000
PRE-PLANNING STUDY
FOR
CHRISTOPHER NEWPORT UNIVERSITY
PLANT OPERATIONS/WAREHOUSE BUILDING
Advertisements $15,000
Printing & Reproduction $3,000
Moving, Relocation, & Temporary Facilities $750,000
IT Cabling/Security $750,000
Signage $10,000
Building Demolition $650,000
Hazardous Material Abatement $150,000
Utility Connection Fees $80,000
Utility Relocations $250,000
Commissioning $150,000
Miscellaneous Other Costs $125,000
Total Other Costs $3,833,000
Furnishings and Equipment $1,644,526
Subtotal Project Cost $38,020,325
Construction Contingency $1,000,000
Subtotal Project Cost $39,020,325
Escalation to Mid Point of Construction $7,618,654
Total Project Cost $46,638,979